1 SR 92/CLAWITER-
WHITESELL INTERCHANGE
UPGRADE PROJECT
Project Initiation Document Phase
February 2024
ATTACHMENT II
2 “SR-92/Clawiter – Whitesell Interchange and Reliever Route Project” Project Background
Phase I - Complete
Provide for better access in and out of the
industrial area and to help relieve congestion on
major arterials.
Whitesell St — Depot Rd to Breakwater Ave:
Roadway extension and widening with bike lanes,
curb, gutter, sidewalk, landscaping, utilities, and
street lighting.
Phase II
Provide new interchange access off Whitesell St
for better local and regional traffic circulation.
3 Project Overview
1. San Mateo T oll Plaza and
Bridge
2. SF Bay Trail
3. Eden Landing Ecological
Reserve
4. Hayward Wastewater
Treatment Facility
5. Hayward’s Industrial
Technology and Innovation
Corridor
6. Dow Chemical
7. Bay Center Business Park
8. Britannia Point Eden
9. Eden Plaza
Need:
Lack of bicycle/pedestrian facilities on
Clawiter Road across SR 92.
The existing SR 92/Clawiter Road
interchange has high traffic congestion
and is deficient in meeting the current
and future traffic demand of the
industrial/western portion of the city.
Significant roadway deficiencies
resulting in inefficient traffic
operations.
Purpose:
Improve multimodal access and
connectivity across SR 92 at
Clawiter Road, including access to
regional recreational facilities.
Improve access to the
industrial/business western
portion of the City of Hayward
from SR 92.
Improve and optimize traffic
operations at the SR 92/Clawiter
interchange and along local
roadways in proximity to the
interchange.
Clawiter Rd
Enterprise Ave
Depot Rd
2 3
7 6
1 4
5 8 9
Hayward’s Industrial Technology
and Innovation Corridor
4 Physical Constraints:
1. High Voltage Transmission Power
Lines through Interchange
2. Clawiter Rd Overcrossing Structure
3. Columns of Existing Pedestrian
Overcrossing
Design Considerations:
4. Lack of Bike Lanes and Poor
Sidewalk Connectivity
5. High Truck Volumes from Whitesell
St accessing SR 92
1 2
53 4
Risks and Opportunities
5 Schedule by Phase
Planning/Scoping:
The City, in cooperation with Caltrans
and Alameda CTC have initiated the
Project Initiation Document (PID).
The PID defines the general scope of
the environmental studies and
engineering reports that will be
necessary to comply with California
Environmental Quality Act (CEQA) and
National Environmental Policy Act
(NEPA) in the next phase.
We Are
Here
6 Current Phase Schedule
1. PID Kick-Off – February 2023
2. Project update to Hayward CIC – June 28, 2023
3. Draft scoping document (PID) to Caltrans – November 2023
4. Updated draft scoping document (PID) to Caltrans – February 2024
5. Anticipated PID Approval from Caltrans – April 2024
Benefits:
Least Right of Way acquisition.
Breakwater Ave access maintained.
Minimal improvements targeted to
meet traffic demand.
Scalable
Disadvantages:
No direct access to Whitesell St
industrial parcels from Westbound
SR 92.
Does not provide Class II or Class IV
bike Lanes on the existing Clawiter
Rd Structure.
Relative Project Cost:
Low ($)
7 Alternative 1: Combined Whitesell/Clawiter
X
X
WESTBOUND
EASTBOUND
Existing Bicycle Facilities Proposed
Bike Lane
Ped Sidewalk
Shared Bike Facility
Benefits:
New Interchange at Whitesell St.
Improves SR 92 by increasing spacing to
Industrial Blvd Interchange.
Access to Clawiter Rd from WB 92 is
maintained.
Clawiter Rd provides local circulation.
Disadvantages:
Significant Right of Way acquisition.
Provides only partial access to Clawiter Rd
from SR 92.
Requires new local connection for
Breakwater Ave.
Class II or Class IV Bike lanes not provided
on the existing Clawiter Rd Structure.
Relative Project Cost:
Medium ($$)
8 Alternative 2: Full Diamond with Partial Access
X
X
X
X
WESTBOUND
EASTBOUND
Existing Bicycle Facilities Proposed
Bike Lane
Ped Sidewalk
Shared Bike Facility
9 Alternative 3: Whitesell Interchange Only
Benefits:
New Interchange at Whitesell St.
Improves SR 92 by increasing spacing to Industrial
Blvd Interchange.
Reduced skew across SR 92 increases intersection
spacing and improves operations.
Existing Clawiter Rd overpass to be demolished.
Disadvantages:
Significant Right of Way acquisition.
Provides no access to Clawiter Rd from SR 92.
Requires new local connection for Breakwater Ave.
Requires new structure over SR 92.
Relative Project Cost:
High ($$$)
X
X
X
X
X
LOCAL CIRCULATION
ROUTE
WESTBOUND
EASTBOUND
Existing Bicycle Facilities Proposed
Bike Lane
Ped Sidewalk
X
10 Whitesell Street Overcrossing
11 Project Cost Estimate
Alternative 1:
Combined
Whitesell/Clawiter
Alternative 2:
Full Diamond
with Partial
Access
Alternative 3:
Whitesell
Interchange Only
Construction Cost: $49,600,000 $71,500,000 $102,300,000 Right of Way: $3,800,000 $26,100,000 $33,900,000
Support Cost: $17,400,000 $27,200,000 $38,300,000
Total Project Cost (Today) $70,800,000 $125,000,000 $175,000,000 Total Project Cost (Escalated to 2032) $95,300,000 $167,000,000 $233,000,000 12 Next Steps
1. Recommend City Council authorize the Director of Public Works to sign the final PID on behalf of the city.
2. Seek Caltrans approval on the PID which defines the scope and cost of the Environmental Review Phase*.
Notes: * Initiation of the Environmental Review Phase is contingent upon funding. * Preliminary Alternatives will be refined during the Environmental Review phase with public stakeholder input.
13 Q & A