ATTACHMENT II

Page 1 of 2 ends

Table 1. Existing and Proposed EV Charging Requirements Proposed Changes are in Red. Definitions of key terms are provided below.

A B C D E
Land Use
Type
CalGreen Requirements
Effective July 1, 2024
CalGreen Requirements
Effective January 1, 2026
Current Reach Code
Requirements
Effect of
Proposed Amendment
Single Family &
Townhome
 One L2 EV Capable space
per D.U.  No change  Two L2 EV Ready spaces
per D.U.  None proposed.

Multi-Family
Residential
 10% L2 Charger
 40% LP L2 EV Ready
Unassigned spaces:
 25% L2 Charger
 75% LP L2 EV Ready

Assigned Spaces:
 100% LP L2 EV Ready
+ Direct Wiring*
Unassigned spaces:
 20% 25% L2 Charger
 80% 75% LP L2 EV Ready

Assigned Spaces:
 100% LP L2 EV Ready +
Direct Wiring
 Current and proposed
requirements both result in
100% of spaces with EV
readiness.
 Proposed requirements will be
easier to comply with as majority
of spaces will have lower
amperage.

Office and Retail  5% L2 Charger
 10% L2 EV Capable  No change  20% L2 Charger;
 30% L2 EV Capable
 Retail uses were previously
categorized as “other non-
residential.”
 Retail is now subject to the same
requirements as Offices.

Other Non-
Residential
Uses
 5% L2 Charger
 10% L2 EV Capable
 10% L2 Charger
 10% L2 EV Capable
 10% L2 Charger
 10% L2 EV Capable  None proposed.

Hotel/Motel  10% L2 Charger
 40% LP L2 EV Ready
 25% L2 Charger
 40% LP L2 EV Ready
 15% 25% L2 Charger
 25% 40% LP L2 EV Ready**
 Hotels/Motels would be
required to add more Level 2
chargers and more low power
Level 2 Ready spaces.
* Direct Wiring specifies that EV Charging circuits will be directly tied to the unit’s electric panel or meter.

** Increasing the requirement for hotels and motels from 25% to 40% of parking spaces to be Low Power Level 2 EV Ready is the only change required by the intervening code requirements that took effect on July 1, 2024. All other changes shown in column D are proposed for consistency with 2025 CalGreen Requirements.

ATTACHMENT II

Page 2 of 2 ends

Definitions:
 EV Capable means the electric panel has necessary capacity and conduit is installed to parking spaces.  EV Ready means EV Capable and wiring and outlet are installed.  EVCS means Electric Vehicle Charging Station (charger) is installed.  Level 1 (L1): 15-20 Amp, 120 Volt (standard household outlet). Driving distance provided: 3-4 miles per hour of charge.  Low-Power Level 2 (LP L2): 20 Amp, 208/240 Volt. Driving Distance provided: 10-15 miles per hour of charge.  Level 2 (L2): 40+ Amp, 208/240 Volt. Driving Distance provided: 25-30 miles per hour of charge.  Level 3(L3) (Direct Current or DC Fast Charging): 80-400 Amp, 200-600 Volt DC. Driving Distance provided: 100+ miles per hour of charge.
 D.U.: dwelling unit