ATTACHMENT II
Capital Improvement Program (CIP) Progress Report
FY25 Quarter 1 & 2 In Progress Projects
(July 1 to December 31, 2024)
Project
No. Project Title Q1/2 Activities
Q1/2
Completion
%
Status
Target
Completion
Date
Fund
06988
21st Century Library
& Community
Learning Center -
Construction
Elevator completed.
Closing out 99% N/A N/A 406
07074
250' Zone for
Pressure Reducing
Strategy at Decoto
In progress 75% On track TBD 604
07019 250’ P/S Motor
Starter Replacements Obtaining quotes 0% Pending TBD 603 07716
27 Inch Force Main
Bypass Pumping - I-
880/Industrial
Not started 0% Not started TBD 612
07193
750 Pump Station
Foundation
Stabilization
No improvements
needed at this time,
keep monitoring
0% N/A N/A 604
05328
A St, Silva, and
Tennyson Complete
Streets
Combining with
another project
06942 - High Injury
Network Safety Plan
0% On track 2029 213,
215
06830 Access Control
System
New cameras
installed. Additional
card readers
required.
Contingent on
contract update
with Facilities
90%
Delayed due
to
cyberattack.
Dec 2025 621
06937
Active
Transportation
Incentive and
Promotion Program
Program design
underway 10% On track Apr 2027 460
07010
Air Release with
Blow Off Access and
Rehabilitation
Not started 0% Not started TBD 603
07678
Air Release with
Blowoff Access and
Rehab
No activities yet 0% N/A TBD 611
07762 Airport Lift Station
Improvements
New pumps are
installed 50% On track Jun 2025 611
Project
No. Project Title Q1/2 Activities
Q1/2
Completion
%
Status
Target
Completion
Date
Fund
06851 ALP Update with
Narrative
Delayed, FAA
requires further
study.
60% Delayed Jun 2025 621
07765
Annual
Emergency/Spot
Line Repairs
Ongoing 0% Ongoing Ongoing 611
07789 Annual Line
Replacements FY24
Design 65%
complete 20% On track
Construction
end by Q2
2027
611
07072 Annual Line
Replacements FY24
Design 90%
complete 30% On track
Construction
end by Q4
2026
603
07799 Annual Line
Replacements FY25 Not yet started 0% Not started TBD 611 07746
Arf, Tennyson Trash
Capture Device
Installations
Construction
substantially
complete.
95%
Delayed due
to supply
chain
Apr 2025 612
06867 ATC Tower Siting
Study
Not selected for FAA
grant. FAA prefers
shovel ready
project. Will
continue to pursue
funding
0% On hold until
FY26 N/A 621
05257 Bridge Structures
Maintenance Ongoing 0% Ongoing Ongoing 450
05344
Campus Drive
Sidewalk
Improvements -
Phase I 2nd St to
Oakes Dr
Design phase.
Construction to
follow.
5% Pending TBD 212
05345
Campus Drive
Sidewalk
Improvements -
Phase II Oakes Dr to
Highland Blvd
No activities yet 0% N/A TBD 212
07080
Cast Iron Water
Pipeline
Replacement - Local
Streets FY25
Not started 0% Pending TBD 603
Project
No. Project Title Q1/2 Activities
Q1/2
Completion
%
Status
Target
Completion
Date
Fund
07273
City Conference
Room Audio Video
Upgrade
In progress and
ongoing. Working
with vendor to
standardize based
on work in
Conference Room
4A.
25% On track Ongoing 731
06923
Citywide EV
Charging Strategy
Update
Staff is seeking
funding to
implement the
strategy. Staff plans
to present an update
to Council in FY25.
75% Delayed Jun 2025 405
05713 Clawiter Bike Lane
Design complete.
Will be constructed
in FY25 Pavement
Improvement Plan.
20% On track Aug 2025 450
07785 Coating of South
Primary Clarifier No activities 0% Pending TBD 611
07422 Community Service
Officers (3) Vehicles
Ongoing project. In
progress. 50% On track Ongoing 736
06940 Community-Based
Transportation Plan
Onboarded
consultant 5% On track Dec 2026 460
05116
Congestion
Management
Program
Ongoing. Completed
yearly 0% Ongoing Ongoing 210
07810 Connection Fee Study Public hearing on
2/18/25 95% On track Feb 2025 612
05856
Controller Cabinet
Replacement and
Battery Back Up
Program
Ongoing 0% Ongoing Ongoing 460
07103 Corporation Yard
Needs Assessment In progress 5% On track TBD 604
07266 Council Chambers
Technology Upgrade
Building fund for
screen
replacements.
0% Pending Ongoing 731
07412
Criminal
Investigations
Equipment
Ongoing 20% N/A N/A 405
Project
No. Project Title Q1/2 Activities
Q1/2
Completion
%
Status
Target
Completion
Date
Fund
05225
D Street Traffic
Calming &
Implementation
In design, Pursuing
grant funding 15% On track Dec 2026 212
07763
Daisy Ct Access Road
Erosion Mitigation
Project
Retaining wall has
been replaced 50% Delayed TBD 611
07106 Dead-End Water
Main Improvements
Ongoing, as needs
are identified 0% Ongoing Ongoing 604
06925 Decorative
Crosswalks - MSD On track 0% On track Jun 2025 405
07253
Desktop Computer
Replacement
Program
In progress and
ongoing. Expended
43% for FY25.
43% On track Ongoing 731
06913 Downtown Parking
Program
Restarting business
coordination 75% On track Dec 2025 406
05237
Downtown Specific
Plan Implementation
(Foothill Blvd., A St.,
B St., and C St.)
Planning and design
are ongoing 10% On track Dec 2026 215
07421 Drones for Hazard
Mitigation
Will pursue with
new chief 0% Delayed Jun 2025 406
07009
Easement Protection
& Landscape
Clearing at Various
Locations
Ongoing 0% Ongoing Ongoing 603
07516
EBDA Outfall
Replacement
Payment
Billed 2x year by
EBDA. First
payment in process
50% Pending Ongoing 611
07277 EBRCS Subscription Ongoing, Annual 0% Ongoing Ongoing 406 07073 Emergency Annual
Line Repairs FY24 As needed 0% Ongoing Ongoing 603
07032
Emergency
Line/Leak Repairs
FY25
As needed 0% Ongoing Ongoing 603
07484 Emergency
Management System
Not currently
pursuing 0% N/A N/A 405
07006
Emergency
Mechanical/Electric
Replacement
Program
Ongoing 0% Ongoing Ongoing 603
Project
No. Project Title Q1/2 Activities
Q1/2
Completion
%
Status
Target
Completion
Date
Fund
07486 Emergency Vehicle
Preemption Annual, ongoing 0% Ongoing
Ongoing,
units will
reach end of
usable life
again
405
07284 Enterprise Data
Strategy Not started. 0% Pending TBD 731
05337 EV Compact Bike
Lane Sweeper
Ordered. ETA
delivery Jan 2025. 0% On track TBD 210
06945 Evaluate Alternatives
to Downtown Loop Initiating project 0% On track Jun 2028 460 07227 Facility Security
Improvements
Phase 3 Council
Approved 0% Jan-25 Jun 2025 726
07411 Field Operations
Equipment Ongoing 21% N/A N/A 405
07216
Fire Alarm/Smoke
Detector
Replacement
Obtaining quotes 0% N/A Jun 2025 726
06929
Fire Department
Protective Ballistic
Vests and Helmets
Vendors being
solicited 10% On track May 2025 405
07304 Fire Fleet
Replacement - Grants
Ongoing project. In
progress. 50% On track Ongoing 736
07144
Fittings Upgrade for
Fire Department -
Various Reservoirs
Completed on
several water tanks 30% Ongoing Ongoing 603
07259
Geographic
Information System
Improvements
In progress and
ongoing. 0% Ongoing Ongoing 731
07177
GIS Data
Development and
Conversion
Anticipate
completion March
2025
80% On track Mar 2025 604,
612
07191
Groundwater
Sustainability Plan
Implementation
Activities
Ongoing 0% Ongoing Ongoing 604
07116
Groundwater
Sustainability Plan
Projects
In planning 0% Pending TBD 604
Project
No. Project Title Q1/2 Activities
Q1/2
Completion
%
Status
Target
Completion
Date
Fund
07498
Harder Corridor
Median
Improvement
To begin in FY26 0% N/A TBD 406
07624 Harder Road Sewer
System Improvement In planning 0% Pending TBD 611,
612
05217
Hayward Blvd. Safety
Improvement
Feasibility Study
Restarted efforts for
feasibility study 75% On track Jun 2026 212
05310 Hayward Boulevard
Safety Improvements
Pending completion
of feasibility study 0% Pending Dec 2026 212
07796
Hazardous Tree
Removal and
Replacement MSD
In progress 67% In progress Nov 2027 405
05742
Hesperian Frontage
Road Improvement -
Sueirro St to Phillips
Way
Design complete.
Construction not yet
started.
20% On track Jun 2025 450
07061 Hesperian P/S Main
Braker Replacement Obtaining quotes 0% Pending TBD 603
07062
Hesperian P/S VFD
and Motor Drive
Replacements
Not started 0% Not started TBD 603
07070
Hesperian Pump
Station Underground
Diesel Fuel Tank
Replacement
Looking into
refurbishing versus
need for
replacement
0% Pending TBD 603
06930 HFD Recruit
Academy
Academy 24-02
Complete 90% On track Awaiting
final invoices 405
06942 High Injury Network
Safety Plan Initiating project 0% On track Jun 2028 460 06926 HPD Locker Rooms
Construction
Construction not
started. 0% Pending TBD 406
07420 HPD Locker Rooms
Design
Design 75%
complete 20% On track Summer
2026 405
06869 Infrastructure for
Electric Aircraft
Pending technical
review 0% N/A N/A 621
07418 Integrated Cameras
and Equipment Ongoing 73% N/A N/A 405
05712 Intersection
Improvement Project Ongoing 0% Ongoing Ongoing 460
Project
No. Project Title Q1/2 Activities
Q1/2
Completion
%
Status
Target
Completion
Date
Fund
07282 Inventory / Asset
Management
In Progress. Phase 1
complete. 75% On track Jul 2025 731
07488
Jackson Corridor
Median
Improvement
In progress 0%
Delayed due
to project
scope/spec
change
Jun 2025 405
06914 La Vista Park
Design is complete.
Bids in late
Feb/early March.
0% On track End of 2026 405
06862
Landscape
Improvements and
Cleanup - Sulphur
Creek Sites
Ongoing 0% Ongoing Ongoing 621
05102
Landscape
Material/Median
Tree/Shrub
Replacements
Ongoing project. In
progress. 0% Ongoing Ongoing 405
06827 LED Lighting Retrofit
Exterior complete.
Interior remainder
will be as needed
80% On track Jun 2026 621
07018
Lift Station Valve
Upgrade at Various
Stations
As needed 0% As needed Ongoing 611
07744 Linden Lift Station
Upgrades Not started 0% Not started TBD 612
05283 Main Street Complete
Street Project Underway 30% On track May 2025 219,
450
07764
Marathon Lift Station
Pump Replacement
Project
Pumps delivered,
need to schedule
installation
10% On track Jun 2025 611
05839
Mission Blvd
Southend Frontage
Island Improvement
In design - 10% 5% On track Dec 2025 410
05002 Mutual Aid Fire
Equipment Ongoing 50% Ongoing Ongoing 405
07809
Nature-Based
Solution Feasibility
Study
RFP issued.
Selecting consultant
early Feb.
0% In progress TBD 612
Project
No. Project Title Q1/2 Activities
Q1/2
Completion
%
Status
Target
Completion
Date
Fund
07481 New Fire Station No.
6 Construction
complete. Working
on close out
99% On track Mar 2025 406
07482 New Fire Training
Center
Construction
complete. Working
on close out
99% On track Mar 2025 406
07016
New Pressure
Regulating Stations
at New 265' Zone
Needs being
reassessed, not
moving forward at
this time
0% Pending TBD 604
05305 New Sidewalks -
FY23 Design 50% 50% On track Jun 2026 213
05331 New Sidewalks -
FY24 Design 50% 50% On track Jun 2026 213
07187
New University
Pressure Reducing
Station
New development
planning application
review in progress
5% On track TBD 604
06898 Noise Monitoring Ongoing service 0% Ongoing Ongoing 621 05312 Orchard Avenue
Traffic Calming
Short term pilot
substantially
complete
45% On track Dec 2026 213
05307
Patrick/Gading
Complete Street
Project
Striping plans
complete 60% On track Fall 2025 210
05110
Pavement
Management
Program
Ongoing 0% Ongoing Ongoing 210
06890 Pavement
Rehabilitation Ongoing 10% Ongoing Ongoing 621
05338
Pavement
Rehabilitation - Gas
Tax - FY25
Going out to bid in
February. 0% On track Nov 2025
210,
211,
212,
218
05175
Pedestrian Traffic
Signal Modifications
and Improvements
Ongoing 0% Ongoing Ongoing 216
06823 Perimeter Fence
Replacement Perform as needed 0% Ongoing Ongoing 621
06924 Publicly Accessible
Fast Chargers
Staff is working on
the design of an EV
charging hub at
Muni Lot 4
35% On track Jun 2026 405
Project
No. Project Title Q1/2 Activities
Q1/2
Completion
%
Status
Target
Completion
Date
Fund
(between B and C
Streets, east of
Foothill Blvd). It
may be completed
sometime in 2026,
but might not be FY
26 07722 Rt 238 Parcel Group
5 Delayed 0% Delayed TBD 411
07723 Rt 238 Parcel Group
6 No progress 0% No progress TBD 411
07725 Rt 238 Parcel Group
8 Delayed 0% Delayed TBD 411
07726 Rt 238 Parcel Group
9 No progress 0% No progress TBD 411
07303 Police Fleet
Replacement
Ongoing project. In
progress. 50% On track Ongoing 736
07305 Police Fleet
Replacement - Grants
Ongoing project. In
progress. 50% On track Ongoing 736
07409 Police Officer
Equipment Ongoing 21% N/A N/A 405
07423
Public Safety Center
– Conceptual Facility
and Site Design
In progress 5% On track Fall 2025 406
07256
Public Safety Mobile
Laptop Replacement
Project
In progress and
ongoing. Expended
12% for FY25.
12% On track Ongoing 731
05893
Quick Response
Traffic Safety
Projects
Ongoing 0% Ongoing Ongoing 460
07419 Rapid Turnaround
DNA Testing (RADS) Ongoing 0% N/A N/A 405
07709 Recycled Water
Master Plan
On track –
Completed RFP
process, awarded
consultant contract,
signed agreement
and issued Notice to
Proceed.
1% In progress Fall 2026 612
07066 Recycled Water
Phase II
Dependent on
Recycled Water
System Master Plan
0% Pending TBD 604
Project
No. Project Title Q1/2 Activities
Q1/2
Completion
%
Status
Target
Completion
Date
Fund
07475
Replacement
Equipment for
Maintenance
Services
On track 0% On Track Jun 2025 405
07059
Reservoir Coating
Inspection/Recoating
at Various Reservoirs
Not started 0% Not started TBD 603
07102
Reservoir Water
Quality Improvement
Project
Not started 0% Not started TBD 604
07057 Restore Water Mains
Crossing at I-880 Not started 0% Not started TBD 603
07784 Root Foaming Working on
preparing RFQ 0% On track TBD 611
05014
Route 238
Administrative
Expenses
On Track 50% On track June 2025 411
05276 Route 238 Bypass
Property Disposition Ongoing 0% Ongoing Ongoing 411
05287
Route 238 Corridor
Improvement Project
- Phase 3 Final
Design and
Construction
Construction
ongoing. 90% On track Mar 2025 410
06922 Russell City
Engagement & Art Ongoing 0% Ongoing Ongoing 405
05323 Safe Routes for
Seniors - Tennyson
Concepts complete.
Engineering design
in spring
10% On track Dec 2026 219
05341 Safe Routes to School
- Harder
Being incorporated
into CIP project
06941
0% N/A N/A 212
05333 Safe Routes to School
- Palma Ceia
Being incorporated
into CIP project
06941
0% N/A N/A 212
06941
Safe Routes to School
Implementation
Project
Started final design 5% On track Apr 2027 460
05313
Santa Clara Street
Traffic Calming Study
and Implementation
Ongoing 10% On track Dec 2026 213
Project
No. Project Title Q1/2 Activities
Q1/2
Completion
%
Status
Target
Completion
Date
Fund
07761 Sewer Line
Improvement FY21
Contract work
completed –
punchlist remaining
99% On track Feb 2025 611
07693
Sewer Manhole
Rehabilitation -
Various Locations
No activities 0% Pending Ongoing 611
05340
Sidewalk
Rehabilitation +
Wheelchair Ramps
FY25
In design 5% On track Jan 2026 450
05343 Simme Seat Pilot
Program
First set of seats
installed. Pursuing
additional funding
for more seats
50% On track Jun 2025 216
07197
Skywest & Hesperian
Pump Station
Generator Fuel
Replacement and
Line Repairs
50% of lines have
been repaired. Fuel
has not been
replaced.
50% Ongoing Ongoing 603
06861 Skywest Property
Maintenance Ongoing 0% Ongoing Ongoing 621
07071
Skywest Pump
Station Underground
Diesel Fuel Tank
Replacement
Looking into
refurbishing vs,
replacement need
0% Pending TBD 603
07105
Solar Power at
Various Water
Facilities
Not started due to
lack of need for
additional power
0% N/A N/A 604
07672 Soto Road Sewer
Improvement
Design 65%
complete 20% On track
Construction
end by Q2
2027
611
06960
South Hayward
Youth and Family
Center (STACK)
Split in 3 phases.
Phase 1 will
complete in Feb.
Phase 2 - applying
for permits in
January 2025.
Funding gap for
Phase 2.
33% On track 2029 405
06943 Speed Management
Plan
Onboarded
consultant 5% On track Jun 2028 460
Project
No. Project Title Q1/2 Activities
Q1/2
Completion
%
Status
Target
Completion
Date
Fund
06932
Storm Drain Pipe
Replacement at Kings
Court
No activities yet 0% Not started TBD 406
07795
Stormdrain
Infrastructure Repair
- MSD
Pending PW
confirmation 6% Delayed Jun 2025 405
05188 Streetlight Energy Ongoing 0% Ongoing Ongoing 210 05189 Streetlight
Maintenance Ongoing 0% Ongoing Ongoing 210
06816
Sulphur Creek 10-
Year Environmental
Monitoring
Ongoing 0% Ongoing Ongoing 621
07402 Supporting Services
Equipment Ongoing 15% N/A N/A 405
05160 Surplus Property
Maintenance On Track 15% On Track Jun 2025 405
06819
Taxiway Zulu
Pavement
Rehabilitation Design
Pending FAA review
and approval 95% On track Apr 2025 621
06864
Taxiway Zulu West
Pavement
Rehabilitation
Construction
No activities 0% Pending TBD 621
07788
Tennyson Lift Station
Emergency Standby
Generator
Replacement
In process of getting
quotes 0% Pending TBD 611
07798 Tennyson Median
Repair - MSD/PW On track 0% Pending Jun 2025 405
05342
Tennyson Rd and
Winton Ave Adaptive
Signal Coordination
Project
Design complete.
Implementation in
spring 2025
30% On track Jul 2027 212,
460
06944
Tennyson Road
Crossing Safety
Improvements
Onboarded
consultant 5% On track Dec 2026 460
06826 T-Hangar
Improvements
Completed roof
work. Wheels
replaced as needed
20% Ongoing Ongoing 621
06828 Tower Renovations Ongoing. Next phase
is fire alarm 10% On track Dec 2027 621
Project
No. Project Title Q1/2 Activities
Q1/2
Completion
%
Status
Target
Completion
Date
Fund
upgrades. Project
tied to Tower HVAC
05734
Traffic Calming
Implementation
Program
Ongoing 50% On track Jun 2025 460
05709
Traffic Control
Device
Repair/Replacement
- MSD
On track 38% On track Jun 2025 460
05233 Traffic Management Ongoing 0% Ongoing Ongoing 212 05186 Traffic Signal Energy Ongoing 0% Ongoing Ongoing 210 05187 Traffic Signal
Maintenance Ongoing 0% Ongoing Ongoing 210
05714
Transportation
Software
Improvements
Ongoing 0% Ongoing Ongoing 460
05877
Transportation
System Management
Projects
Ongoing 0% Ongoing Ongoing 460
06868 Tree Removal Project On hold, funding
pending 5% On hold End of FY28 621
07500 Turnout Gear & PPE
Replacement Ongoing 50%
On track,
annual
expirations
Ongoing 405
06865
Upgrade ATC Tower
Fire Alarm System
Panel and HVAC
New project. Bid
required 5% On track Jun 2026 621
07555 Upgrade Valle Vista
Station Discharge Not started 0% Not started TBD 612
07176
Utility Center
Renovation/Training
Center Addition (2nd
Floor)
To be incorporated
in results of need
assessment in
07103
0% Pending TBD 604
07766
UV Disinfection
System for Recycled
Water
Waiting until
Recycled Water
Master Plan is
completed
0%
On hold due
to Recycled
Water Master
Plan
N/A 612
07546
Valle Vista Sewer
Force Main
Reliability
Implementation
Not started 0% N/A TBD 611
Project
No. Project Title Q1/2 Activities
Q1/2
Completion
%
Status
Target
Completion
Date
Fund
07626
Valle Vista
Submersible Pump
Repl and Wet Well
Rehabilitation
All pumps replaced.
Wet well rehab not
needed at this time.
50% On track As needed 611
07739 Valle Vista VFD
Replacement VFDs installed 75% On track Jun 2025 611
06833 View Park On hold 0% On hold 2028 621
07093 Water Line
Improvement FY21
Contract work
completed –
punchlist remaining
99% On track Feb 2025 603,
604
07150 Water System RRA &
ERP Update
In progress,
consultant selected 10% On track Sept 2025 603
07063 Water System RRA
Mitigation Measures
Dependent upon
update in 07150
Water System RRA
& ERP Update
0% Pending TBD 603
07196
Well Field All-
Weather
Improvements
In progress 15% On track TBD 604
07199 Well Field Storage
Building Project Not started 0% Pending TBD 604
07531 WPCF (WRRF) Asset
Management Plan No activities 0% Pending TBD 611
07673
WPCF (WRRF)
Chlorination System
Improvement
No activities 0% Pending TBD 611
07807
WPCF (WRRF)
Digester Annual
Cleaning
In process 0% In progress Dec 2025 611
07804
WPCF (WRRF)
Digester Inspection
and Rehabilitation
No activities 0% Pending TBD 611
07806
WPCF (WRRF)
Effluent Channel
Return Pump
Improvements
No activities 0% Pending TBD 611,
612
07618
WPCF (WRRF) Gas
Conditioning System
Skid Media
Replacement
Media replaced 75% On track End FY 26 611
Project
No. Project Title Q1/2 Activities
Q1/2
Completion
%
Status
Target
Completion
Date
Fund
07741 WPCF (WRRF) Levee
Road Maintenance No activities 0% Pending TBD 611
07656
WPCF (WRRF) Main
480V MCC Electrical
Distribution
Rehabilitation
In process 20%
Delayed due
to supply
chain
N/A 611
07529
WPCF (WRRF)
Miscellaneous
Replacements
Ongoing 0% Ongoing Ongoing 611
07786
WPCF (WRRF) New
Administration
Building & Lab
Project
Currently bidding. 5% On track May 2027 612
07775
WPCF (WRRF) New
Digester Mixing
Pumps for Digesters
No. 2 & 3
New pump arrived.
Receiving quotes on
installation. Only
installed as needed.
25% On track TBD 611
07803 WPCF (WRRF) On-
site Spoils Removal No activities 0% Pending TBD 611
07802
WPCF (WRRF)
Oxidation Pond Rock
Slope Protection
Working on scope 0% Pending TBD 611
07760
WPCF (WRRF) Phase
II Improvement
Project
60% design
complete 3% On track Jul 2030 612
07749
WPCF (WRRF)
Primary Effluent
Flow Equalization
Project
Incorporating into
07760 0% Pending TBD 612
07569
WPCF (WRRF)
Roofing for Heating
and Mixing Building
No. 1
No activities 0% Pending TBD 612
07801
WPCF (WRRF)
SCADA System
Master Plan and
Upgrades
No activities. To be
completed as part of
WRRF Phase II
upgrades
0% Pending TBD 611
Project
No. Project Title Q1/2 Activities
Q1/2
Completion
%
Status
Target
Completion
Date
Fund
07648
WPCF (WRRF)
Seismic Retrofit of
Miscellaneous
Buildings
Based on evaluation,
no retrofits are
needed at this time.
Improvements will
be included in any
future rehabilitation
projects on an as
needed basis
0% N/A N/A 611
07769
WPCF (WRRF)
Selective Catalyst
Reduction for Cogen
Engine
No activities 0% Pending TBD 612
07559
WPCF (WRRF) Solids
Pumping
Improvements
Ongoing 0% On track Ongoing 612
07771
WPCF (WRRF)
Trickling Filter Pump
Station Pump
Rebuilds
Performed as
needed 0% As needed As needed 612
07625
WPCF (WRRF)
Underground
Conduit Repair (494
Pump & Sludge Beds)
No activities 0% Pending TBD 611