AMENDMENTNO. 1TOMEMORANDUMOFUNDERSTANDINGBETWEENTHECITYOFHAYWARDANDHAYWARDAREARECREATIONANDPARKDISTRICTFORTHELAVISTAPARKPROJECT THISAmendmentNo. 1totheMemorandumofUnderstanding (“MOU”), datedforconveniencethis _______ dayof ___________ 2025, isbetweentheCityofHayward (“City”), amunicipalcorporationoftheStateofCalifornia, andtheHaywardAreaRecreationandParkDistrict (“HARD”), aCaliforniaspecialdistrict, hereinafterreferredtoindividuallyasa “Party” andcollectivelyas “Parties,” andamendstheMOUwhichwasenteredintoonJanuary29, 2025, forthedesign, construction, funding, operationandmaintenanceofLaVistaParkinHayward, California. RECITALS: WHEREAS, byResolutionNo. 24-259, onDecember17, 2024, theCityCouncilauthorizedanddirectedtotheCityManagertoexecuteanewMemorandumofUnderstandingwiththeHaywardAreaRecreationandParkDistrictforthefunding, operations, andmaintenanceofLaVistaPark; andWHEREAS, CityandHARDexecutedtheaforementionedMOUonthe29thdayofJanuary, 2025; andWHEREAS, afterreceivingandreviewingconstructionbids, Staffdeterminedanadditional $6,444,000isneededtofullyfundtheconstructionofLaVistaParkincludingdesign, construction, administration, inspections, andtestingcosts; andNOW, THEREFORE, CityandHARDagreetothefollowingamendmentstotheMOUasfollows:
3. Funding of Construction of Park Project Improvements a) Park In-Lieu Fees. ThePartiesagreethatCitywillallocateNineteenMillionFourHundredForty-fourThousandDollars ( $19,444,000.00) inaccumulatedparkin-lieufees (QuimbyActfees) collectedbyCityasoftheEffectiveDatefromcertainresidentialdevelopmentprojectsinthecommunitiestobeservedbytheParkProperty, including, butnotlimitedto, theDeveloperFeeContribution (“ParkIn-LieuFees”). Inaddition, andasfurthersetforthinSection3(d), below, thePartiesagreethatCitywillallocateSixMillion, SevenHundredThousandDollars ($6,700,000.00) ofexistingand/orfutureparkin-lieufeescollectedbyCityfromdevelopersofresidentialdevelopmentprojectsincommunitiestobeservedbytheParkPropertytoHARDasareimbursementofaportionofHARD’sfinancialcontributiontotheProjectasdescribedinSection3(c), below.
Docusign Envelope ID: 02F57E4C- 8ABF- 4C93- 8AFD- D34DFF03E0BE July17th
Attachment III
Page2of3
e). Summary of Total Available Funding.
ParkIn-LieuFeeAllocation $19,444,000.00CityofHaywardContribution $5,785,000.00CityPreviouslyIncurredCosts $2,140,000.00HARDContribution $15,400,000.00Total $ 42,769,000.00
4. Project CostsEstimate. Basedonconstructionbidsreceived, Cityhasdeterminedthetotalprojectcostasshownbelow: ConstructionContract $32,850,547Contingency (12%) $ 3,942,066 ConstructionSubtotal $ 36,792,613
Design $ 998,387Administration $998,000GeotechnicalInspection, TestingandReporting $1,840,000PreviouslyIncurredCityCosts $2,140,000TotalProjectCost $ 42,769,000 Exceptasspecificallyamendedherein, allothertermsandconditionsoftheMOUshallremaininfullforceandeffect.
Docusign Envelope ID: 02F57E4C- 8ABF- 4C93- 8AFD- D34DFF03E0BE Page3of3
INWITNESSWHEREOF, CityandHARDhaveexecutedthisAmendmentNo. 1asofthedatesetforthabove.
HAYWARDAREARECREATIONANDPARKDISTRICT
Dated: By: JamesWheeler, GeneralManager
CITYOFHAYWARD
Dated: ______________________________ By: AlexAmeri, DirectorofPublicWorks Dated: ______________________________ By: JayantiAddleman, InterimCityManager Attest: MiriamLens, CityClerkApprovedastoformandprocedure:
MichaelS. Lawson, CityAttorney
Docusign Envelope ID: 02F57E4C- 8ABF- 4C93- 8AFD- D34DFF03E0BE 7/ 10/ 2025
7/ 10/ 2025
7/ 16/ 2025