ATTACHMENT III
Resolution No. 26-______
TDA Article 3 Project Application Form
1. Agency City of Hayward
2. Primary Contact Lucas Woodward
3. Mailing Address 777 B Street, 4th Floor
4. Email Address Lucas.Woodward@Hayward-
CA.gov
5. Phone Number 510-583-4783
6. Secondary Contact (in
the event primary is
not available)
Byron Tang
7. Mailing address (if
different) N/A☒
8. Email Address Byron.Tang@Hayward-
CA.gov
9. Phone Number 510-583-4784
10. Send allocation
instructions to (if
different from above):
11. Project Title
12. Amount requested $600,000 13. Fiscal Year of
Claim
2027
14. Description of Overall Project:
15. Project Scope Proposed for Funding: (Project level environmental, preliminary planning, and ROW are ineligible uses of TDA funds.)
16. Project Location: A map of the project location is attached or a link to a online map of the project location is provided below:
• Quick-build crossing improvements at the City’s highest-ranked intersections in the Local Road Safety Plan (LRSP), including high-visibility crosswalks, intersection daylighting, and Rectangular Rapid Flashing Beacons
• Concrete islands that separate existing bike lanes from traffic and that provide median refuges at crosswalks.
• Ongoing replacement of materials such as safe-hit posts that currently provide separated bike lanes and painted bulb-outs at intersections.
TDA Article 3 Funds will be used for construction phase, including labor and materials. https://www.google.com/maps/d/edit?mid=1o8NPBvjVYpTrOZwrMos3nXqd04LIbGo&usp=shari ng
MTC Prog. & Alloc. Section April. 2005TDA Article 3 Claim Applications Appendix A Page 2
Project Relation to Regional Policies (for information only)
17. Is the project in an Equity Priority Community? Partially Yes☐ No☐
18. Is this project in a Priority Development Area or a Transit-Oriented Community?Partially Yes☐ No☐
19. Project Budget and Schedule
Project Phase TDA 3 Other Funds Total Cost Estimated Completion (month/year)
Bike/Ped Plan
ENV
PA&ED
PS&E
ROW
CON $600,000 $600,000 June 2027
Total Cost $600,000 $600,000 June 2027
Project Eligibility
A. Has the project been reviewed by the Bicycle and Pedestrian Advisory Committee? Yes☒ No☐
April 30, 2026
https://alamedactc.granicus.com/AgendaViewer.php?view_id=1&clip_id=916
B. Has the project been approved by the claimant's governing body? Yes☐ No☒
If "NO," provide expected date:_June 16, 2026
C. Has this project previously received TDA Article 3 funding? Yes☐ No☒
(If "YES," provide an explanation on a separate page)
D. For "bikeways," does the project meet Caltrans minimum safety design criteria pursuant to Chapter 1000 of the California Highway Design Manual? Yes☒ No☐
1. Is the project categorically exempt from CEQA, pursuant to CCR Section 15301(c), Existing Facility? Yes☒ No☐
MTC Prog. & Alloc. Section April. 2005TDA Article 3 Claim Applications Appendix A Page 3
2. If “NO” above, is the project is exempt from CEQA for another reason? Yes☐ No☐
Cite the basis for the exemption. __________________________ N/A☒ If the project is not exempt, please check “NO,” and provide environmental documentation, as appropriate.
E. Estimated Completion Date of project (month and year): June 2027
F. Have provisions been made by the claimant to maintain the project or facility, or has the claimant arranged for such maintenance by another agency? (If an agency other than the Claimant is to maintain the facility, please identify below and provide the agreement.
Yes☒ No☐
G. Is a Complete Streets Checklist required for this project ? Yes☒ No☐
If the amount requested is over $250,000 or if the total project phase or construction phase is over $250,000, a Complete Streets checklist is likely required. Please attach the Complete Streets checklist or record of review, as applicable. More information and the form may be found here: https://mtc.ca.gov/planning/transportation/complete-streets