Projects Fund Project
Number Activities General Fund/Measure C
Impact
Finish a preliminary feasibility report on a
new Police Building
406 - Measure
C Capital
Projects
07423
Programming, space needs, conceptual design
and site assessment for the new Public Safety
Center are completed. This included a final
study report which was presented to the CIAC
on 2/25/26.
This project is funded by
Fund 406 - Measure C Capital
Projects - Measure C Capital,
in the amount of $625,000.
Hesperian Frontage Road Improvement -
Sueirro St to Phillips Way
450 - Street
System
Improvements
05742
Substantial completion on December 31,
2025. Final completion on January 30, 2026.
Acceptance of Work on March 24, 2026.
This project has no General
Fund or Measure C impact.
Public Art Crosswalk Project
405 - Capital
Projects
(Governmental)
06925 Project complete.
This project has a budget of
$50,000 (Fiscal Year 2025)
and is by funded by Fund 405
- Capital Projects
(Governmental) - Capital
Projects (Governmental),
which includes transfers from
Route 238 Corridor Improvement Project -
Phase 3 Final Design and Construction
410 - Route 238
Corridor
Improvement
05287
The construction contract was completed on
November 13, 2025 and was accepted as
complete on January 7, 2026.
This project has no General
Fund or Measure C impact.
Sidewalk Rehabilitation + Wheelchair
Ramps FY25
450 - Street
System
Im
provements
05340 Project complete. This project has no General
Fund or Measure C impact.
Capital Improvement Program (CIP) Progress Report
FY26 Quarter 3 & 4 Completed Projects (January 1, 2026 to June 30, 2026)
ATTACHMENT III
Projects Fund Project
Number Activities General Fund/Measure C
Impact
Speed Management Plan
460 -
Transportation
Improvement
06943 Completed. Plan appr oved by City Council.
Originally, this project was
partially funded by Fund 460 -
Transportation Improvement
- Transportation System
Corridor which does include
transfers from the General
Fund and Measure C. In
order to minimize the impact
on General Fund, staff
received City Council
approval to remove the
entire General Fund
contribution of $264,000 for
the required matching
portion of the project and
replace with an appropriation
from Fund 213, Measure BB
(Pedestrian& Bicycle).
ATTACHMENT III