Jurisdiction Ord.
Type
Council
Adopted
Date
CEC
Approval
Date
Single Family and Low-rise
Multifamily Requirement
High-rise Multifamily
Requirement
Nonresidential
Requirement
Cost-effectiveness
Study Municipal Code Link Ordinance
Alameda PV 6/1/2021 8/11/2021 N/A
New: PV system to fill solar
zone (>15% of roof area) as
defined in Sec. 110.10
New: PV system to fill solar
zone (>15% of roof area) as
defined in Sec. 110.10
2019 LR Res NC /
2019 Non Res NC Section 140.0 Ord. No.
EE 12/21/2020 5/12/2021
New: SF mixed-fuel ≥ 10 EDR
margin / SF all-electric ≥ 4.7
efficiency EDR margin / MF
mixed fuel ≥ 10.3 EDR margin /
MF all-electric ≥ 0 EDR
Add/Alts: prescriptive
measures
New: MF mixed fuel ≥ 10.3
EDR margin / MF all-electric ≥
0 EDR
Add/Alts: prescriptive
measures
New: mixed fuel office ≥ 20%
compliance margin / all-
electric office ≥ 10%
compliance margin / mixed
fuel retail ≥ 16% compliance
margin / all-electric retail ≥
16% compliance margin
Add/Alts: prescriptive
measures
PV 12/21/2020 5/12/2021 N/A
New: PV system to fill solar
zone (>15% of roof area) as
defined in Sec. 110.10
New: PV system to fill solar
zone (>15% of roof area) as
defined in Sec. 110.10
EE 12/3/2019 2/20/2020
New: All-electric OR
Mixed Fuel, Total EDR margin >
10 AND electric-ready
New HRR/Hotel: All-electric
OR Mixed-Fuel and >10%
compliance margin
New: All-electric OR
Mixed-Fuel: 10% compliance
margin AND electric-ready
Exception: Labs, industrial,
manufacturing occupancies
19.36.040
PV 12/3/2019 2/20/2020 N/A
New: PV system to fill solar
zone (>15% of roof area) as
defined in Sec. 110.10
New: PV system to fill solar
zone (>15% of roof area) as
defined in Sec. 110.10
19.36.100.3
Brisbane PV 12/12/2019 2/20/2020 N/A
(see All-electric sheet)
New: PV of 3 kW min. for <
10,000 sq. ft. and 5 kW min.
for
> 10,000 sq. ft OR
Solar thermal
New: PV of 3 kW min. for <
10,000 sq. ft. and 5 kW min.
for
> 10,000 sq. ft OR
Solar thermal
2019 LR Res NC /
2019 Non Res NC 15.81.050 Ord. No. 643
2019 Code Cycle - Locally Adopted Energy Ordinances
Berkeley Ord. No 7,678-N.S.2019 LR Res NC /
2019 Non Res NC
Albany 2019 LR Res NC /
2019 Non Res NC 12-6.1.b.4 (p) Resolution No.
2020-127
2021-10-01
1 Jurisdiction Ord.
Type
Council
Adopted
Date
CEC
Approval
Date
Single Family and Low-rise
Multifamily Requirement
High-rise Multifamily
Requirement
Nonresidential
Requirement
Cost-effectiveness
Study Municipal Code Link Ordinance
2019 Code Cycle - Locally Adopted Energy Ordinances
Burlingame PV 8/17/2020 10/14/2020 N/A
(see All-electric sheet)
New: PV of 3 kW min. for <
10,000 sq. ft. and 5 kW min.
for > 10,000 sq. ft.
Alternative: Solar thermal
> 40 sq.ft. collector area
New: PV of 3 kW min. for <
10,000 sq. ft. and 5 kW min.
for > 10,000 sq. ft.
Alternative: Solar thermal
> 40 sq.ft. collector area
2019 LR Res NC /
2019 Non Res NC 110.0 Ordinances 1979 ,
1980, 1981
EE 3/12/2019 8/14/2019
New: HPWH OR solar thermal
Adds/Alts: > $60k: Presc.
measures
New: HPWH OR increased
solar fraction
New: Electric water heating
OR solar thermal > 0.4 SF
Carlsbad Energy
Conservation
Ordinance CE Study
18.30.190 Ord. No. CS-348
PV 3/12/2019 8/14/2019 N/A New/Alt: 15 kW per 10,000
s.f.; min 5kW for < 10,000 s.f.
New/Alt: PV that offsets 80%;
15 kW per 10,000 s.f.; min
5kW for < 10,000 s.f.
2016 NR New
Construction 18.30.130 Ord. No. CS-347
Chula Vista EE 12/1/2020 1/25/2021
Add/Alts:
performance/precsriptive
efficiency reqs. for pre-2006
buildings (CZ specific)
N/A N/A 2019 Existing LR Chapter 15.26.040 Ord. No. 2020- 3495
Daly City PV 5/10/2021 7/15/2021 N/A
(see All-electric sheet)
New: PV system to fill solar
zone (>15% of roof area) as
defined in Sec. 110.10
New: PV system to fill solar
zone (>15% of roof area) as
defined in Sec. 110.10
2019 LR Res NC /
2019 Non Res NC Section 15.60.030 Ord. No. 1448
Davis EE 10/8/2019 1/22/2020
New SF: All-electric OR Mixed
Fuel, EDR margin of 9.5; New
LR MF: Mixed fuel, EDR margin
of 10; electric-ready
N/A N/A 2019 LR Res New
Construction 8.01.092 Ord. No. 2565
East Palo Alto PV 10/20/2020 12/9/2020 N/A
(see All-electric sheet)
New: PV system to fill solar
zone (>15% of roof area) as
defined in Sec. 110.10
New: PV system to fill solar
zone (>15% of roof area) as
defined in Sec. 110.10
2019 LR Res NC /
2019 Non Res NC Ord. No. 07-2020
Emeryville PV 9/13/2021 N/A
(see All-electric sheet)
New: PV system to fill solar
zone (>15% of roof area) as
defined in Sec. 110.10
New Hotel/Motel: PV system
to fill solar zone (>15% of roof
area) as defined in Sec. 110.11
2020 LR Res NC /
2019 Non Res NC Section 8-10.03 Ord. No. 21-006
Carlsbad
2021-10-01
2 Jurisdiction Ord.
Type
Council
Adopted
Date
CEC
Approval
Date
Single Family and Low-rise
Multifamily Requirement
High-rise Multifamily
Requirement
Nonresidential
Requirement
Cost-effectiveness
Study Municipal Code Link Ordinance
2019 Code Cycle - Locally Adopted Energy Ordinances
PV First Reading
9/22/2022 N/A
New: PV of 5 kW min. for <
10,000 sq. ft. and 15 kWdc
per 10,000 sq. ft. for > 10,000
sq. ft. OR TDV valuation
method (includes additions
that increase roof by 1,000 sq.
ft and alterations with permit
value over $1,000,000 that
affects 75% of floor area
New: PV of 5 kW min. for <
10,000 sq. ft. and 15 kWdc
per 10,000 sq. ft. for > 10,000
sq. ft. OR TDV valuation
method (includes additions
that increase roof by 1,000 sq.
ft and alterations with permit
value over $1,000,000 that
affects 75% of floor area
2019 LR Res NC /
2019 Non Res NC Section 120.10 Ord. 2021-13
EE First Reading
9/22/2023
Additions/Alterations of pre-
1978 buildings >$50k: duct
sealing OR cool roof
Additions/Alterations of post-
1978 buildings >$50k: LED
lighting package OR insulated
hot water pipes OR upgraded
water fixtures;
Exception for buildings that
score >7 on DOE Home Energy
Score
Additions/Alterations of pre-
1978 >$50k: R-38 attic
insulation
Additions/Alterations of 1978-
1990 buildings >$50k: duct
sealing OR cool roof
Additions/Alterations of 1991-
present buildings: LED lighting
package OR water heating
package;
Exception for buildings that
score >7 on DOE Home
Energy Score
Additions/Alterations of 1,000
sq. ft. >$200k: Inclusion of
outdoor lighting- one
prescriptive measure / Steel
Framing- prescriptive
measure
2019 Existing LR Section 23.12.080 Ord. 2021-13
EE 3/17/2020 6/10/2020 N/A
(see All-electric sheet)
New: All-electric OR 10%
compliance margin
New: All-electric OR 10%
compliance margin (15% for
Office/Retail)
PV 3/17/2020 6/10/2020 N/A
(see All-electric sheet)
New: PV system to fill solar
zone (>15% of roof area) as
defined in Sec. 110.10
New: PV system to fill solar
zone (>15% of roof area) as
defined in Sec. 110.10
Los Angeles
County EE 11/26/2019 4/8/2020
New and Re-roof: Low-slope
Aged Refl. > 0.65, TE > 0.85,
SRI > 78
Steep-slope: Aged Refl. > 0.25,
TE > 0.85, SRI > 20
New and Re-roof: Low-slope
Aged Refl. > 0.65, TE > 0.75,
SRI > 78
Steep-slope: Aged Refl. > 0.25,
TE > 0.75, SRI > 20
New and Re-roof: Low-slope
Aged Refl. > 0.68, TE > 0.85,
SRI > 82
Steep-slope: Aged Refl. > 0.28,
TE > 0.85, SRI > 27
2016 Cool Roofs Title 31 Ord No. 2019-0061
Hayward 2019 LR Res NC /
2019 Non Res NC Ord. No. 20-059-1.02
Encinitas
2021-10-01
3 Jurisdiction Ord.
Type
Council
Adopted
Date
CEC
Approval
Date
Single Family and Low-rise
Multifamily Requirement
High-rise Multifamily
Requirement
Nonresidential
Requirement
Cost-effectiveness
Study Municipal Code Link Ordinance
2019 Code Cycle - Locally Adopted Energy Ordinances
Marin County EE 10/8/2019 12/11/2019
New: All-electric OR
Limited Mixed-Fuel prewire for
induction, EE EDR Margin > 3
OR
Mixed-Fuel, pre-wire for
induction, EE EDR Margin > 3
and Total EDR Margin > 10
New: All-electric OR
Limited Mixed-Fuel: 5%
compliance margin, prewired
for induction OR
Mixed-Fuel: 10% compliance
margin, pre-wired for
induction
New: All-electric OR
Limited Mixed-Fuel: 5%
compliance margin, prewired
for induction OR Mixed-Fuel:
10% compliance margin, pre-
wired for induction
2019 LR Res NC /
2019 Non Res NC 19.04.130 Ord. No. 3712
Menlo Park PV 9/24/2019 12/11/2019 N/A
(see All-electric sheet)
New: PV of 3 kW min. for <
10,000 sq. ft. and 5 kW min.
for > 10,000 sq. ft. (some
exceptions)
New: PV of 3 kW min. for <
10,000 sq. ft. and 5 kW min.
for > 10,000 sq. ft. (some
exceptions)
2019 LR Res NC /
2019 Non Res NC 12.16.110.10 Ord. No. 1057
Millbrae PV 11/10/2020 1/25/2021 N/A
(see All-electric sheet) New: PV on 50% of roof area New: PV on 50% of roof area 2020 LR Res NC / 2019 Non Res NC 9.50 Ord. No. 2020-
Mill Valley EE 11/18/2019 4/8/2020
New: All-electric OR
Limited Mixed-Fuel: prewire for
induction, with EE EDR Margin
> 3 OR
Mixed-Fuel, pre-wire for
induction, EE EDR Margin > 3
and Total EDR Margin > 10
New: All-electric OR
Limited Mixed-Fuel: 5%
compliance margin, prewired
for induction OR
Mixed-Fuel: 10% compliance
margin, pre-wired for
induction
N/A 2019 LR Res NC /
2019 Non Res NC Chapter 14.48 Ord. No. 1313
EE 12/3/2019 2/20/2020
New: All-electric OR
Elec. Space and Water Heat:
Eff. EDR Margin of 2 for SF and
1 for MF
Mixed-Fuel: Total EDR Margin
of 10 for SF and 11 for MF;
AND electric-ready
New HR MF/ Hotel: All-
electric OR > 6% compliance
magin AND electric-ready
New: All-electric OR Office &
Retail: >14% compliance
margin; Industrial/
Manufacturing + 0%; All other
NR occupancies > 6%
compliance margin; AND
electric-ready
PV 12/3/2019 2/20/2020 N/A N/A
New: PV of 3 kW min. for <
10,000 sq. ft. and 5 kW min.
for > 10,000 sq. ft.
Ord. No. 65 1482019 LR Res NC /
2019 Non Res NCMilpitas Title 2, Chapter 11, Section 2
2021-10-01
4 Jurisdiction Ord.
Type
Council
Adopted
Date
CEC
Approval
Date
Single Family and Low-rise
Multifamily Requirement
High-rise Multifamily
Requirement
Nonresidential
Requirement
Cost-effectiveness
Study Municipal Code Link Ordinance
2019 Code Cycle - Locally Adopted Energy Ordinances
Mountain
View PV 11/12/2019 2/20/2020 N/A
(see All-electric sheet) New: PV on 50% of roof area New: PV on 50% of roof area 2019 LR Res NC / 2019 Non Res NC
Chapter 8, Article 1, Division 3, Section 8.20 Ord. No. 17.19 Pacifica PV 11/25/2019 4/8/2020 N/A
(see All-electric sheet)
New: PV of 3 kW min. for
< 10,000 sq. ft. and 5 kW min.
for > 10,000 sq. ft.
New: PV of 3 kW min. for
< 10,000 sq. ft. and 5 kW min.
for > 10,000 sq. ft.
2019 LR Res NC /
2019 Non Res NC Section 8.6.08 Ord. No. 852-CS
EE 12/2/2019 2/20/2020 N/A
(see All-electric sheet)
New: All-electric OR > 5%
compiance margin AND
electric-ready
New: All-electric OR Office &
Retail: >12% compliance
margin; Industrial/
Manufacturing + 0%; All other
NR occupancies > 5%
compliance margin; AND
electric-ready
PV 12/2/2019 2/20/2020 N/A
New: PV system to fill solar
zone (>15% of roof area) as
defined in Sec. 110.10
New: PV system to fill solar
zone (>15% of roof area) as
defined in Sec. 110.10
EE 2/1/2021 5/12/2021 Add/Alts: > $25k Prescriptive
EE reqs. N/A N/A
2019 Cost
Effectiveness Study for
Existing LR Residential
Building Upgrades
Section 8.02.020
PV 2/1/2021 5/12/2021 Add/Alts: Additional level or
roof area increased by >30% N/A N/A
2019 Cost-
Effectiveness Study:
Low-Rise Residential
Addendum
Section 8.02.070
Redwood City PV 9/21/2020 12/9/2020 N/A
(see All-electric sheet)
New: PV of 3 kW min. for <
10,000 sq. ft. and 5 kW min.
for > 10,000 sq. ft.
Alternative: Solar thermal
> 40 sq.ft. collector area
(some exceptions)
New: PV of 3 kW min. for <
10,000 sq. ft. and 5 kW min.
for > 10,000 sq. ft.
Alternative: Solar thermal
> 40 sq.ft. collector area
(some exceptions)
2019 LR Res NC /
2019 Non Res NC Section 9.255 Ord. No.
2019 LR Res NC /
2019 Non Res NC Ord. No. 5485
Piedmont Ord. No. 750NS
Palo Alto 16.17.040 et. seq.
2021-10-01
5 Jurisdiction Ord.
Type
Council
Adopted
Date
CEC
Approval
Date
Single Family and Low-rise
Multifamily Requirement
High-rise Multifamily
Requirement
Nonresidential
Requirement
Cost-effectiveness
Study Municipal Code Link Ordinance
2019 Code Cycle - Locally Adopted Energy Ordinances
Richmond PV 3/3/2020 6/10/2020 N/A
(see All-electric sheet)
New: PV of 3 kW min. for <
10,000 sq. ft. and 5 kW min.
for > 10,000 sq. ft.
Alternative: Solar thermal
> 40 sq.ft. collector area
New: PV of 3 kW min. for <
10,000 sq. ft. and 5 kW min.
for > 10,000 sq. ft.
Alternative: Solar thermal
> 40 sq.ft. collector area
2019 LR Res NC /
2019 Non Res NC Chapter 6.02.100 Ord No. 06-20 NS
San Anselmo EE 4/14/2020 9/9/2020
New: All-electric OR
Limited Mixed-Fuel prewire for
induction, EE EDR Margin > 3
OR
Mixed-Fuel, pre-wire for
induction, EE EDR Margin > 3
and Total EDR Margin > 10
New: All-electric OR
Limited Mixed-Fuel: 5%
compliance margin, prewired
for induction OR
Mixed-Fuel: 10% compliance
margin, pre-wired for
induction
New: All-electric OR
Limited Mixed-Fuel: 5%
compliance margin, prewired
for induction OR Mixed-Fuel:
10% compliance margin, pre-
wired for induction
2019 LR Res NC /
2019 Non Res NC Section 9-19.040 Ord. No. 1145
San Carlos PV 1/25/2021 5/12/2021 N/A
(see All-electric sheet)
New: PV of 2 W/sq. ft for
buildings < 10 habitable
stories
New: PV of 2 W/sq. ft for
buildings < 3 habitable stories
, healthcare facilities excepted
2019 LR Res NC /
2019 Non Res NC Section 9.255 Ord. No. 1570
San Francisco EE 1/7/2020 4/8/2020 New: All-electric OR Mixed Fuel- Total EDR Score < 14
New HRR/Hotel: All-electric
OR Mixed-Fuel and >10%
compliance margin
2019 LR Res NC /
2019 Non Res NC
Section 4.201.3
Section 5.201.3 Ord. No 003-20
San Jose EE 10/1/2019 12/11/2019 N/A
(see All-electric sheet)
New HR MF/ Hotel: All-
electric OR > 6% compliance
margin and electric-ready
New: All-electric OR Office &
Retail: >14% compliance
margin; Industrial/
Manufacturing + 0%; All other
NR occupancies > 6%
compliance margin; and
electric-ready
2019 LR Res NC /
2019 Non Res NC 24.12.100 Ord. No. 30311
2021-10-01
6 Jurisdiction Ord.
Type
Council
Adopted
Date
CEC
Approval
Date
Single Family and Low-rise
Multifamily Requirement
High-rise Multifamily
Requirement
Nonresidential
Requirement
Cost-effectiveness
Study Municipal Code Link Ordinance
2019 Code Cycle - Locally Adopted Energy Ordinances
EE 7/7/2020 8/11/2020
New SF: All-electric OR Mixed
Fuel, EDR margin of 9; New LR
MF: Mixed fuel, EDR margin of
9.5 AND electric-ready
New: All-electric OR
Hotel/HRR > 9% compliance
margin; AND electric-ready
New: All-electric OR
Office/Retail 15% compliance
margin, Others 5%
compliance margin AND
electric ready
Chapter 15.50 Ord. No. 1684
PV 7/7/2020 8/11/2020 N/A
New: PV system to fill solar
zone (>15% of roof area) as
defined in Sec. 110.10
New: PV system to fill solar
zone (>15% of roof area) as
defined in Sec. 110.10
Chapter 15.04.110 Ord. No. 1684
EE
(see All-electric sheet)
New SF and Duplexes: All-
electric OR
min Eff. EDR reduction of 2.5
N/A
(see All-electric sheet)
New Office Buildings: All-
electric OR Mixed-Fuel + 10%
compliance margin
2019 LR Res NC /
2019 Non Res NC 23.23.040 Ord. No. 2019-9
PV Prewire PV system for
expansion to all-electric design
New: PV: ≥ 3 kW. Alternative:
Solar thermal ≥ 40 sq ft
collector area
New: <10,000 s.f.: min. 3 kW
PV; 10,000+ s.f.: 5 kW PV
Alternative: Solar thermal ≥
40 s.f. collector area
2019 LR Res NC /
2019 Non Res NC 23.24.030 Ord. No. 2019-9
EE 10/5/2020 12/9/2020
(see All-electric sheet)
New 100% Affordable LR MF:
All-electric OR
at least .5 EDR less than
Standard Design OR
Prescriptive measures
New 100% Affordable HR MF:
All-electric OR
>5% compliance margin OR
Prescriptive measures
(see All-electric sheet) 2020 LR Res NC /
2019 Non Res NC 23.24.020 Ord. No. 2020-17
San Rafael EE 11/18/2019 4/8/2020
New: CALGreen Tier 1: Mixed
fuel, EDR ≥ 10, All-elec EDR ≥
14 New: CALGreen Tier 1 (5%
compliance margin)
New: CALGreen Tier 1 (10%
compliance margin)
2019 LR Res NC /
2019 Non Res NC Chapter 12.100 Ord. No. 1974
EE
New: All-electric OR
Mixed-Fuel with CalGreen Tier
1 New HRR/Hotel: All-electric
OR Mixed-Fuel and >5%
compliance margin
New: All-electric OR Mixed-
Fuel and >10% compliance
margin
2019 LR Res NC /
2019 Non Res NC 8.36.020 Ord. No. 2617
PV Major Additions: PV system 1.5
watts per sq. ft.
New and Major Additions: 2
watts per sq. ft.
New and Major Additions: 2
watts per sq. ft.
2019 LR Res NC: PV +
Additions Addendum 8.106.055 Ord. No. 2617
12/11/2019
Santa Monica 9/24/2019 12/11/2019
San Mateo
(City)
9/3/2019
2019 LR Res NC /
2019 Non Res NC
San Luis
Obispo
2021-10-01
7 Jurisdiction Ord.
Type
Council
Adopted
Date
CEC
Approval
Date
Single Family and Low-rise
Multifamily Requirement
High-rise Multifamily
Requirement
Nonresidential
Requirement
Cost-effectiveness
Study Municipal Code Link Ordinance
2019 Code Cycle - Locally Adopted Energy Ordinances
Sunnyvale PV 12/1/2020 1/25/2021 N/A
(see All-electric sheet)
New: PV of 3 kW min. for <
10,000 sq. ft. and 5 kW min.
for > 10,000 sq. ft.
Alternative: Solar thermal
> 40 sq.ft. collector area
New: PV of 3 kW min. for <
10,000 sq. ft. and 5 kW min.
for > 10,000 sq. ft.
Alternative: Solar thermal
> 40 sq.ft. collector area
2019 LR Res NC /
2019 Non Res NC Section 16.42.090 Ord. No. 3168-20
West
Hollywood
EE, Cool
Roofs 8/19/2019 12/11/2019
New or Alteration > 10,000 sq.
ft.: PV to offset 15% of usage
OR solar thermal with min. .5
solar fraction OR vegetative
roof covering min. 30%
New or Alteration > 10,000
sq. ft.: PV to offset 15% of
usage OR solar thermal with
min. .5 solar fraction OR
vegetative roof covering min.
30%
New or Alteration > 10,000
sq. ft.: PV to offset 15% of
usage OR solar thermal with
min. .5 solar fraction OR
vegetative roof covering min.
30%
2019 NR+ Retrofits
PV / 2019 Non Res
NC
19.20.060 Ord. No. 19-1072
All rights reserved, except that this document may be used, copied, and distributed without modification This report was prepared for the California Statewide Codes & Standards Program. The program is funded by California utility customers and administered by Pacific Gas and Electric Company, San Diego Gas & Electric Company (SDG&E®), Southern California Gas Company, and Southern California Edison Company under the auspices of the California Public Utilities Commission and in support of the California Energy Commission. © 2020 Pacific Gas and Electric Company, San Diego Gas and Electric Company, Southern California Gas Company and Southern California Edison. 2021-10-01
8 Jurisdiction Ord.
Type
Council
Adopted
Date
CEC
Approval
Date
Municipal Code Link Ordinance
Single Family and Low-rise
Multifamily High-rise Multifamily Nonresidential
Alameda All-
Electric 6/1/2021 8/11/2021 New: All-electric (excluding ADUs) New: All-electric
New: Exception for non-
electric space heating and
process systems in Fire, High-
Hazard, Laboratory
occupancies; public/employee
cafeteria; pre-wire for electric
13-11.3 Ord. No.
Berkeley All-
Electric 7/16/2019 N/A New: All-electric New: All-electric New: All-electric Chapter 12.80 Ord. No. 7,672-N.S Brisbane All-
Electric 12/12/2019 2/20/2020
New: Exception for
cooktops/fireplaces; pre-wire
for electric New: All-electric
New: Except Life science
occupancies and gas specific for
profit kitchen
15.83.060 Ord. No. 643
Burlingame All-
Electric 8/17/2020 10/14/2020
New: Exception for
indoor/outdoor cooking
appliances and fireplaces; pre-
wire for electric. Adds/Alts: >
50% valuation when HVAC
included
New: All-electric
New: Exception for-profit kitchen
cooking equipment; pre-wire for
electric
110.0 Ordinances 1979 ,
1980, 1981
Campbell All-
Electric 2/18/2020 1/25/2021
New: All-electric space/water
heating. Natural gas OK for
other uses; pre-wire for electric
N/A N/A 18.18.020 Ord. No 2,260
Cupertino All-
Electric 1/21/2020 4/8/2020 New: All-electric (excluding ADUs) New: All-electric
New: Exception for Fire, High-
Hazard, Laboratory, and "Essential
Facilities" occupancies; pre-wire
for electric
16.54.100 et. seq. Ord. No. 19-2193
Daly City All-
Electric 5/10/2021 7/15/2021 New: All-electric (excluding dwelling units) New: All-electric
New: Exception for Fire, High-
Hazard, Laboratory occupancies
and for-profit kitchen cooking
equipment
Section 15.160.020 Ord. No. 1448
East Palo Alto All-
Electric 10/20/2020 12/9/2020
New: Exception for ADUs; and
cooktops/fireplaces; pre-wire
for electric
New: Exceptions
cooktops/fireplaces, gas water-
heating for affordable housing;
pre-wire for electric
New: Exception for Life Science
buildings, Emergency operations,
and for-profit cooking; pre-wire
for electric
Chapter 15.25 Ord. No 07-2020
2019 Code Cycle - Locally Adopted All-Electric Only Ordinances Scope
2021-10-01
9 Jurisdiction Ord.
Type
Council
Adopted
Date
CEC
Approval
Date
Municipal Code Link Ordinance
Single Family and Low-rise
Multifamily High-rise Multifamily Nonresidential
2019 Code Cycle - Locally Adopted All-Electric Only Ordinances Scope
Emeryville All-
Electric 9/13/2021
New: All-electric (including
ADUs > 400 sq. ft.)
Adds/Alts: > 50% of foundation
or existing framing
N/A N/A Section 8-10.03 Ord. No. 21-006
Encinitas All-
Electric
First Reading
9/22/2022 New: All-electric New: All-electric
New: Exception for Essential
facilities and for-profit kitchens
with business-related reason to
cook with flame
Section 23.12.080 Ord. 2021-13
Fairfax All-
Electric 9/1/2021 New: All-electric New: All-electric
New: Exception for public interest
projects and for-profit cooking
equipment
Chapter 15.05 Ord. No.
Hayward All-
Electric 3/17/2020 6/10/2020 New: All-electric (including ADUs > 400 sq. ft.)
New: All-electric OR 10%
compliance margin
New: All-electric OR 10%
compliance margin (15% for
Office/Retail)
9-1.02 Ord. No. 20-05
Healdsburg All-
Electric 12/16/2019 2/20/2020
New: Exception for cooktops,
fireplaces, pool/spa; pre-wire
for electric
New: Exception for cooktops,
fireplaces, pool/spa; pre-wire
for electric
New: Exception for cooktops,
fireplaces, pool/spa, Essential
Services, technical processes; pre-
wire for electric
15.04.08 Ord. No. 1196
Los Altos Hills All-
Electric 2/20/2020 12/9/2020
New: All-electric space/water
heating (including ADUs).
Natural gas OK for other uses;
pre-wire for electric
N/A N/A 8.1.6.02 Ord. No. 589
Los Altos All-
Electric 11/10/2020 1/25/2021
New: Exception for
cooktops/fireplaces; pre-wire
for electric
New: All-electric for
developments > 10 units
New: Exception for Scientific
Laboratory/ Public buildings and
for-profit cooking; prewire for
electric
Chapter 12.22 Ord. No. 2020-
470A-C
2021-10-01
10 Jurisdiction Ord.
Type
Council
Adopted
Date
CEC
Approval
Date
Municipal Code Link Ordinance
Single Family and Low-rise
Multifamily High-rise Multifamily Nonresidential
2019 Code Cycle - Locally Adopted All-Electric Only Ordinances Scope
Los Gatos All-
Electric 12/17/2019 2/20/2020
New: All-electric (including
ADUs); pre-wire for battery
storage
N/A N/A Chapter 6, Article 7, Section 6.70.010 Ord. No. 2299 Menlo Park All-
Electric 9/24/2019 12/11/2019
New: All-electric space/water
heating and clothes dryers.
Natural gas OK for
cooktops/fireplaces; pre-wire
for electric
New: All-electric New: All-electric 12.16.010 Ord. No. 1057 Millbrae All-
Electric 11/10/2020 1/25/2021
New: All-electric space/water
heating and clothes dryers.
Natural gas OK for
cooktops/fireplaces; pre-wire
for electric
New: All-electric
New: Exception for Life Science/
Public buildings. For-profit
cooking may appeal for exception;
prewire for electric
9.50 Ord. No. 2020-
Morgan Hill All-
Electric 10/23/2019 N/A New: All-electric New: All-electric New: All-electric 15.63 Ord. No. 2306 N.S.
Mountain
View
All-
Electric 10/22/2019 2/20/2020
New SF and Duplexes:
Exception for
cooktops/fireplaces; pre-wire
for electric.
New LR MF: Exception for-
profit kitchen cooking
equipment
New: exception for F, H, and L
occupancies and for-profit
kitchen cooking equipment
New: Exception for Fire, High-
Hazard, Laboratory occupancies
and for-profit kitchen cooking
equipment
Chapter 8, Division 3, Section 8.20 Ord. No. 17.19
Oakland All-
Electric 12/1/2020 New: All-electric New: All-electric New: All-electric Ord. No. 2021-10-01
11 Jurisdiction Ord.
Type
Council
Adopted
Date
CEC
Approval
Date
Municipal Code Link Ordinance
Single Family and Low-rise
Multifamily High-rise Multifamily Nonresidential
2019 Code Cycle - Locally Adopted All-Electric Only Ordinances Scope
Ojai All-
Electric 11/10/2020
New: Exception for ADUs,
pool/spa, for-profit kitchen
cooking equipment
New: All-electric New: Exception for-profit kitchen
cooking equipment Section 9-1.1002 Ord. No.
Pacifica All-
Electric 11/25/2019 4/8/2020
New: Exception for ADUs; and
cooktops/fireplaces; pre-wire
for electric.
New LR MF: Exception for-
profit kitchen cooking
equipment
New: Exception for
cooktops/fireplaces; pre-wire
for electric
New: Exception for Fire and Police
occupancies and for-profit kitchen
cooking equipment
Section 8.6 Ord. No. 852-CS
Palo Alto All-
Electric 12/2/2019 2/20/2020 New: All-electric
New: All-electric OR > 5%
compiance margin; electric-
ready
New: All-electric OR Office &
Retail: >12% compliance margin;
Industrial/ Manufacturing + 0%;
All other NR occupancies > 5%
compliance margin; pre-wire for
electric
16.17.040 et. seq. Ord. No. 5485
Petaluma All-
Electric
5/17/2021 New: All-electric
Add/Alts: > 50% exterior wall
perimeter/ floor area
New: All-electric
Add/Alts: > 50% exterior wall
perimeter/ floor area
New: All-electric
Add/Alts: > 50% exterior wall
perimeter/ floor area. Exception
for Essential Services
17.09 Ord. No.
Piedmont All-
Electric 2/1/2021 5/12/2021 New: All-electric N/A N/A 8.02.070 Ord. No. 750NS 2021-10-01
12 Jurisdiction Ord.
Type
Council
Adopted
Date
CEC
Approval
Date
Municipal Code Link Ordinance
Single Family and Low-rise
Multifamily High-rise Multifamily Nonresidential
2019 Code Cycle - Locally Adopted All-Electric Only Ordinances Scope
Redwood City All-
Electric 9/21/2020 12/9/2020 New: All-electric (excluding ADUs)
New: exception for Fire, High-
Hazard, and Laboratory
occupancies and for-profit
kitchen cooking equipment;
additional exceptions
New: exception for Fire, High-
Hazard, and Laboratory
occupancies and for-profit kitchen
cooking equipment; additional
exceptions
Section 9.249 Ord. No.
Richmond All-
Electric 3/3/2020 6/10/2020
New: All-electric space/water
heating and clothes dryers.
Natural gas OK for
cooktops/fireplaces; pre-wire
for electric
Replace/Upgrade Equipment:
all-electric
New: All-electric
New: Exception for Fire/Police,
Life Sciences, For-profit kitchen
cooking equipment; pre-wire for
electric
Chapter 6.02.100 Ord No. 06-20 NS
Sacramento All-
Electric 6/1/2021
New Buildings ≤ 3 Stories: All-
electric
EFFECTIVE 2023
New Buildings ≥ 4 Stories: All-
Electric
EFFECTIVE 2026
New Buildings ≤ 3 Stories: All-
electric
EFFECTIVE 2023
New Buildings ≥ 4 Stories: All-
Electric
EFFECTIVE 2027
New Buildings ≤ 3 Stories: All-
electric
EFFECTIVE 2023
New Buildings ≥ 4 Stories: All-
Electric
EFFECTIVE 2028
Chapter 15.30.030 Ord. No.
San Carlos All-
Electric 1/25/2021 5/12/2021
New: Exception for
cooktops/fireplaces; pre-wire
for electric
Adds/Alts: > 50% of structure
New: exception Laboratory
occupancies and for-profit
kitchen cooking equipment
upon review; additional
exceptions
New: exception Laboratory
occupancies and for-profit kitchen
cooking equipment upon review;
additional exceptions
Section 110.0 Ord. No. 1570
2021-10-01
13 Jurisdiction Ord.
Type
Council
Adopted
Date
CEC
Approval
Date
Municipal Code Link Ordinance
Single Family and Low-rise
Multifamily High-rise Multifamily Nonresidential
2019 Code Cycle - Locally Adopted All-Electric Only Ordinances Scope
San Francisco All-
Electric 11/17/2020 New: All-electric New: All-electric New: All-electric Section 106A Ord. No. 9/17/72019 N/A New: All-electric N/A N/A Chapter 17.845 Ord No. 30330 12/1/2020 N/A New New
New: Exception for hospitals and
facilities with a Distributed Energy
Resource
Chapter 17.845 Ord. No. 30502
San Mateo
City
All-
Electric 10/5/2020 12/9/2020
New: All-electric (including
ADU's) N/A New Office Buildings: All-electric Section 23.24 Ord. No. 2020-17 San Mateo
County
All-
Electric 2/25/2020 9/9/2020 New: All-electric New: All-electric New: Exception for Laboratories,
Emergency operations, and for-
profit cooking (requires approval)
Section 9200 Ord No. 4824
Santa Barbara All-
Electric 7/27/2021 New: All-electric New: All-electric
New: Exception for public interest
projects, Laboratories, clean
rooms, and for-profit cooking
equipment
Section 22.100.040 Ord. No.
Santa Cruz All-
Electric 4/14/2020 N/A New: All-electric (including
ADUs > 750 sq. ft.) New: All-electric
New: Exception for industrial heat
processes and for-profit kitchen
cooking equipment
Chapter 6.100 Ord. No. 2020-06
Santa Rosa All-
Electric 11/12/2019 2/20/2020 New: All-electric N/A N/A Chapter 18-33.040 Ord. No. 2019-019 Saratoga All-
Electric 12/4/2019 4/8/2020
New: All-electric space/water
heating. Natural gas OK for
cooktops/fireplaces/clothes
dryer; pre-wire for electric
New: All-electric space/water
heating; pre-wire for electric
New: All-electric space/water
heating. Except public agency
owned emergency centers; pre-
wire for electric
Chapter 16.51.015 Ord. No. 366
San Jose All-
Electric
2021-10-01
14 Jurisdiction Ord.
Type
Council
Adopted
Date
CEC
Approval
Date
Municipal Code Link Ordinance
Single Family and Low-rise
Multifamily High-rise Multifamily Nonresidential
2019 Code Cycle - Locally Adopted All-Electric Only Ordinances Scope
South San
Francisco
All-
Electric 6/9/2021 New: All-electric Adds/Alts: >
50% of structure New: All-electric N/A Chapter 15.22 Ord. No.
Sunnyvale All-
Electric 12/1/2020 1/25/2021 New: All-electric New: All-electric New: Exception for Fire, High-
Hazard, Laboratory occupancies
and for-profit kitchen cooking
equipment; prewire for electric
Chapter 16.42 Ord. No. 3168-20
This report was prepared for the California Statewide Codes & Standards Program. The program is funded by California utility customers and administered by Pacific Gas and Electric Company, San Diego Gas & Electric Company (SDG&E®), Southern California Gas Company, and Southern California Edison Company under the auspices of the California Public Utilities Commission and in support of the California Energy Commission.
© 2020 Pacific Gas and Electric Company, San Diego Gas and Electric Company, Southern California Gas Company and Southern California Edison.
All rights reserved, except that this document may be used, copied, and distributed without modification 2021-10-01
15 Jurisdiction Ord.
Type
Council
Adopted Date Exceptions Ordinance
Single Family, Duplexes,
and Townhouses Multifamily Nonresidential - Office Nonresidential - Other Albany EV 12/20/2020 N/A New MF: 20% of spaces
equipped with EVCS N/A N/A Resolution 2020-
127
Brisbane EV 12/12/2019
New: Level 2 EV-Ready space
per unit + Level 1 EV-Ready
circuit (Level 2 if only 1 space
exists)
New: Level 2 EV-Ready space
per unit / min. 50% required
guest spaces EVCS spaces
New Office: >10 spaces- 15%
equipped with Level 2 EVCS + 10
% Level 1 EV-Ready +
25% Level 1 EV-Capable
New Other NR: >10 spaces- 15%
equipped with Level 2 EVCS +
10 % Level 1 EV-Ready
Ord. 643
Burlingame EV 8/17/2020
New: Level 2 EV-Ready space
per unit + Level 1 EV-Ready
circuit (Level 2 if only 1 space
exists)
New: 10% of units with Level 2
EV-Ready space ; remaining
units with Level 1 EV-Ready
New Office: >10 spaces- 10%
equipped with Level 2 EVCS +
10 % Level 1 EV-Ready
New Other NR: >10 spaces- 6%
equipped with Level 2 EVCS +
5 % Level 1 EV-Ready
ADU/JADU without parking
facilities
Ord.
1979/1980/1981
Carlsbad EV 3/12/2019
New: Level 2 EV-Ready space
per unit Add/Alts: >$60k OR
panel upgrade
New: 10% of units with Level 2
EV-Capable space AND 50% of
those spaces installed with EVSE
Add/Alts: >$200k
ADU/JADU without parking
facilities / utility service
cost > $400
Ord. CS-349
Contra Costa
County EV N/A New: 5% of spaces EVSE
equipped
New: EVSE charging at each space
required by TABLE 5.106.5.3.3
New: EVSE charging at each space
required by TABLE 5.106.5.3.4
Amendment to 74-
4.006 CGBSC
Colma EV 2/24/2021
New: Level 2 EV-Ready space
per unit + Level 1 EV-Ready
circuit (Level 2 if only 1 space
exists)
New: 15% of units with Level 2
EV-Ready space N/A N/A Ord.
Cupertino EV 1/21/2020
New: Level 2 EV-Ready space
per unit + Level 1 EV-Ready
circuit (Level 2 if only 1 space
exists)
New: < 20 units: Level 2 EV-
Ready space per unit ;
remaining spaces Level 1 EV-
Ready /
> 20 units: 25% of spaces Level
2 EV-Ready
New Office: >10 spaces- 20%
equipped with Level 2 EVCS + 10
% Level 1 EV-Ready + 30% Level 1
EV-Capable
New Other NR: >10 spaces- 6%
equipped with Level 2 EVCS +
5 % Level 1 EV-Ready
ADU/JADU without parking
facilities Ord. 19-2193
Daly City EV 5/10/2021
New: Level 2 EV-Ready space
per unit + Level 1 EV-Ready
circuit (Level 2 if only 1 space
exists)
New: < 20 units: Level 2 EV-
Ready space per unit/
> 20 units: 75% of spaces Level
1 EV-Ready ; remaining units
Level 2 EV-Ready
New: 10% of spaces to be Level 2
EVCS + 10% spaces Level 2 EV-
Ready + 30% Level 2 EV-Capable
New Other NR: 6% equipped with
Level 2 EVCS + 5 % Level 1 EV-
Ready;
>100 spaces- 80kW fast charger
per 100
Ord. 1449
Davis EV 4/23/2019 New: Level 2 EV-Ready space
per unit
New: < 20 units: Level 1
charging at 5% of spaces / >20
units: Level 2 charging at 1% of
spaces (min. 1)
Add/Alts: Panel upgrade must
include capacity for 20% Level 2
EV-Capable
N/A Ord. 2554
2019 Code Cycle - Locally Adopted Electric Vehicle Ordinances Scope
New: 10% of units with Level 2 EV-Capable space AND 50% of those spaces installed with EVSE
2021-10-01
16 Jurisdiction Ord.
Type
Council
Adopted Date Exceptions Ordinance
Single Family, Duplexes,
and Townhouses Multifamily Nonresidential - Office Nonresidential - Other 2019 Code Cycle - Locally Adopted Electric Vehicle Ordinances Scope
East Palo Alto EV 10/20/2020
New: Level 2 EV-Ready space
per unit + Level 1 EV-Ready
circuit (Level 2 if only 1 space
exists)
New: 10% of units with Level 2
charging + 90% of units with
Level 1 charging. Outlets may
be shared between two units.
New: Office: >10 spaces- 10%
equipped with Level 2 EVCS + 10%
Level 1 EV-Ready + 30 % EV-
Capable
New Other NR: >10 spaces- 6%
equipped with Level 2 EVCS +
5 % Level 1 EV-Ready
ADU/JADU without parking
facilities + MF: utility
service cost > $4500
Ord. 07-2020
Encinitas EV 11/13/2019 New: Level 2 EV-Ready space
per unit
New: EVSE charging at 15% of
spaces
ADU/JADU without parking
facilities / utility service
cost > $400 per unit
Ord. 2019-22
Fremont EV 4/20/2021 New: Level 2 EV-Ready space
per unit
New: EV-Ready spaces
calculated based on total spaces N/A N/A Utility service cost > $400 per unit Ordinance 05-2021
Los Altos EV 10/27/2020
New: Level 2 EV-Ready spaces
for each unit (Two Level 2 if
multiple spaces exist)
New: < 20 units: Level 2 EV-
Ready space per unit/ > 20
units: 25% of spaces Level 2 EV-
Ready + remaining spaces Level
1 EV-Ready
New: Office: >10 spaces- 10%
equipped with Level 2 EVCS + 30
% Level 2 EV-Ready Capable +
10% Level 1 EV-Ready
New: Other NR: >10 spaces- 6%
equipped with Level 2 EVCS + 5%
Level 1 EV-Ready
ADU/JADU without parking
facilities Ord. 2020-471
Marin County EV 10/8/2019
New: Level 2 EV-Ready space
per unit
Add/Alts: Panel upgrade must
include Level 2-Ready circuit
New: Level 2 EV-Ready space
per dwelling unit
Add/Alts: Panel upgrade must
include capacity for 20% Level 2
EV-Capable spaces
ADU/JADU without parking
facilities Ord. 3712
Millbrae EV 11/10/2020
New: Level 2 EV-Ready space
per unit + Level 1 EV-Ready
circuit (Level 2 if only 1 space
exists)
New: < 20 units: Level 2 EV-
Ready space per unit /
> 20 units: 25% of spaces Level
2 EV-Ready + remaining spaces
Level 1 EV-Ready / Affordable
MF: 10% spaces Level 2
New Office: >10 spaces- 10%
equipped with Level 2 EVCS +
additional 10 % LeMF: utility
service cost > $4500vel 1 EV-
Ready + additional 30% EV-
Capable
New Other NR: >10 spaces- 6%
equipped with Level 2 EVCS +
additional 5 % Level 1 EV-Ready
ADU/JADU without parking
facilities + MF: utility
service cost > $4500
Ord. No. 2020-20
Mill Valley EV 11/18/2019
New: Level 2 EV-Ready per unit
Add/Alts: Panel upgrade must
include Level 2-Ready circuit
New: One Level 2 EV-Ready
space per dwelling unit
ADU/JADU without parking
facilities Ord. 1313
New: 10% of spaces to be Level 2 EV-Ready + remaining spaces EV- Capable OR 20% spaces Level 2 EV-Ready + EVCS in 5% spaces (min. 2)
Add/Alts: Panel upgrade must include capacity for 20% Level 2 EV- Capable
Add/Alts: Panel upgrade must include capacity for 20% Level 2 EV- Capable
New NR + Hotel/Motel: EVSE charging at 8% of spaces
Add/Alts: > 10k sq. ft.
2021-10-01
17 Jurisdiction Ord.
Type
Council
Adopted Date Exceptions Ordinance
Single Family, Duplexes,
and Townhouses Multifamily Nonresidential - Office Nonresidential - Other 2019 Code Cycle - Locally Adopted Electric Vehicle Ordinances Scope
Milpitas EV 12/3/2019
New: Level 1 EV-Ready circuit
+ Level 2 EV-Ready circuit per
unit
New: < 20 units: Level 2
charging at 15% of spaces +
Level 1 EV-Capable at 35% of
spaces / >20 units: Level 2
charging at 20% of spaces +
Level 1 EV-Capable at 35% of
spaces
New Office: 5% equipped with
Level 2 EVCS + 10 % Level 1 EV-
Ready + 20% Level 2 EV-Capable
New Other NR: >10 spaces- 4%
equipped with Level 2 EVCS + 3 %
Level 1 EV-Ready;
>100 spaces- 80kW fast charger
per 100
MF Affordable Housing
Projects Ord. 65 148
Mountain View EV 11/12/2019
New: Level 1 EV-Ready circuit
+ Level 2 EV-Ready circuit per
unit
New: Level 2 charging at 15% of
spaces + remaining spaces EV-
Ready + Level 3 EVCS for every
100 spaces
Ord. 17.19
Oceanside EV 8/19/2020 N/A Ord. No.
Redwood City EV 9/21/2020
New: Level 2 EV-Ready space
per unit + Level 1 EV-Ready
circuit (Level 2 if only 1 space
exists)
New: <20 units- Level 2 EV-
Ready space per unit ;
remaining spaces Level 1 EV-
Ready / >20 units- 25% of
spaces Level 2 EV-Ready
New Office: >10 spaces- 10%
equipped with Level 2 EVCS +
additional 10 % Level 1 EV-Ready
+ additional 30% EV-Capable
New Other NR: >10 spaces- 6%
equipped with Level 2 EVCS +
additional 5 % Level 1 EV-Ready
ADU/JADU without parking
facilities Ord. No.
Sacramento EV 4/20/2021 N/A New MF: 20% of spaces Level 2 EV-Ready Ord.
San Anselmo EV 4/14/2020
New: Level 2 EV-Ready per unit
Add/Alts: Panel upgrade must
include Level 2-Ready circuit
New: Level 2 EV-Ready space
per dwelling unit
Add/Alts: Panel upgrade must
include capacity for 20% Level 2
EV-Capable spaces
ADU/JADU without parking
facilities Ord. 1145
New: 10% of spaces to be Level 2 EV-Ready + remaining spaces EV- Capable OR 20% spaces Level 2 EV-Ready + EVCS in 5% spaces (min. 2)
Add/Alts: Panel upgrade must include capacity for 20% Level 2 EV- Capable
New Mixed Use: Level 2 charging at 15% of spaces + remaining spaces EV-Ready + Level 3 EVCS for every 100 spaces
New Commercial/Hotel/Motel : < 10 spaces- Level 2 EVCS + EV-Ready remaining spaces / >10 spaces - 15% equipped with Level 2 EVCS + EV- Ready remaining spaces / >100 spaces - Level 3 DC EVCS
New: 20% of spaces Level 2 EV-Ready
New Hotel/Motel: 20% of spaces Level 2 EV-Ready
New MF and NR: 15% of spaces reserved for ZEV (> 5 parking spaces) and Level 2 charging at 50% of those reserved spaces
2021-10-01
18 Jurisdiction Ord.
Type
Council
Adopted Date Exceptions Ordinance
Single Family, Duplexes,
and Townhouses Multifamily Nonresidential - Office Nonresidential - Other 2019 Code Cycle - Locally Adopted Electric Vehicle Ordinances Scope
San Carlos EV 1/25/2021
New: Level 2 EV-Ready space
per unit + Level 1 EV-Ready
space (Level 2 if only 1 space
exists)
New: 10% of units with Level 2
EV-Ready space ; remaining
units with Level 1 EV-Ready /MF
exception: utility service cost >
$4500
New Office: >10 spaces- 10%
equipped with Level 2 EVCS +
additional 10 % Level 1 EV-Ready
+ additional 30% EV-Capable
New Other NR: ≥10 spaces- 6%
equipped with Level 2 EVCS +
additional 5 % Level 1 EV-Ready
ADU/JADU without parking
facilities / utility service
cost > $400 per unit
Ord.
San Jose EV 10/1/2019 New: Level 2 EV-Ready space
per unit
New: EVSE charging at 10% of
spaces + 20% of spaces EV-
Ready + 70% EV-Capable
ADU/JADU without parking
facilities + Detached
garages
Ord. 30311
San Mateo
County EV 2/25/2020
New: Level 2 EV-Ready space
per unit + Level 1 EV-Ready
circuit (Level 2 if only 1 space
exists)
New: 10% of units with Level 2
EV-Ready space + 40% of units
Level 1 EV-Ready spaces
New Office: >10 spaces- 10%
equipped with Level 2 EVCS + 10
% Level 1 EV-Ready + 30% Level 1
EV-Capable
New Other NR: >10 spaces; 6%
equipped with Level 2 EVCS + 5
% Level 1 EV-Ready
ADU/JADU without parking
facilities + MF: utility
service cost > $4500
Ord. 4824
Santa Monica EV 4/28/2020 New: Level 2 EV-Ready space
per unit
New: EVSE charging at 10% of
spaces + 20% of spaces EV-
Ready + 70% EV-Capable
New Office: EVSE charging at 10%
of spaces + 20% EV-Ready + 30%
EV-Capable
New Hotel/Motel: EVSE charging
at 10% of spaces + 30% EV-
Capable
New Other NR: EVSE charging at
10% of spaces + 30% EV-Capable
ADU/JADU without parking
facilities / utility service
cost > $400 per unit
Ord. 2634
South San
Francisco EV 6/9/2021
New: Level 2 EV-Ready space
per unit + Level 1 EV-Ready
circuit (Level 2 if only 1 space
exists)
New: < 20 units: Level 2 EV-
Ready space per unit /
> 20 units: 25% of spaces Level
2 EV-Ready + remaining spaces
Level 1 EV-Ready / Affordable
MF: 10% spaces Level 2 +
remaining Level 1
N/A N/A ADU/JADU without parking
facilities Ord. No.
Sunnyvale EV 12/1/2020
New: Level 2 EV-Ready + Level
1 EV-Ready space per unit
(Level 2 if only 1 space exists)
New: < 20 units: Level 2 EV-
Ready space per unit /
> 20 units: 25% of spaces Level
2 EV-Ready + remaining spaces
Level 1 EV-Ready / Affordable
MF: 10% spaces Level 2
New Office: >10 spaces- 10%
equipped with Level 2 EVCS +
additional 10 % Level 1 EV-Ready
+ additional 30% EV-Capable
New Other NR: >10 spaces- 6%
equipped with Level 2 EVCS +
additional 5 % Level 1 EV-Ready /
>100 spaces - Level 3 DC EVCS
ADU/JADU without parking
facilities Ord. No. 3168-20
New: EVSE charging at 10% of spaces + 40% EV-Capable
New Hotel/Motel: EVSE charging at 10% of spaces + 50% EV-Capable 2021-10-01
19 Jurisdiction Ord.
Type
Council
Adopted Date Exceptions Ordinance
Single Family, Duplexes,
and Townhouses Multifamily Nonresidential - Office Nonresidential - Other 2019 Code Cycle - Locally Adopted Electric Vehicle Ordinances Scope
This report was prepared for the California Statewide Codes & Standards Program. The program is funded by California utility customers and administered by Pacific Gas and Electric Company, San Diego Gas & Electric Company (SDG&E®), Southern California Gas Company, and Southern California Edison Company under the auspices of the California Public Utilities Commission and in support of the California Energy Commission. © 2020 Pacific Gas and Electric Company, San Diego Gas and Electric Company, Southern California Gas Company and Southern California Edison.
All rights reserved, except that this document may be used, copied, and distributed without modification 2021-10-01
20