HERCULES HILLTOWN DEVELOPMENT PROJECT

MELLO-ROOS CFD AUTHORIZATION

SANTA CLARA VALLEY HOUSING GROUP

SITE PLAN
T otal Project: 597 units
Phase 1: 206 townhomes
Phase 2: 124 townhomes
Phase 3: 70 townhomes
Phase 4: 197 apartments/condominiums
WHY ARE WE REQUESTING A MELLO-ROOS?
 We are here this evening to formally request City Council approval for the formation of a Mello-Roos Community Facilities District for the Hilltown Development Project. The project cannot move forward without this financing mechanism.
 As you are all aware, the Hilltown site faces significant development issues related to grading. There are approximately $86.5 million dollars of public improvement costs and impact fees that render the project financially unfeasible without utilizing this commonly used public improvement funding mechanism.  We are requesting that the City Council approve use of a Mello-Roos Community Facilities District on this long- awaited marque project for the City of Hercules. Use of a Mello-Roos will be the catalyst for moving the Hilltown Project forward in 2022.

ASSUMPTIONS FOR SCENARIOS #1-3
* The Bond Interest Rate is an assumption and subject to change to reflect the market at the time of the Bond sale.

ASSUMPTIONS

Sales Price $650,000 $750,000
Expected Residential Units 200 200
Current Total Tax Rate 1.34% $8,710 $10,050

Bond Interest Rate* 4.50%
Capitalized Interest 12 Months
Annual % Increase in Special Tax 2.00%

SCENARIO #1

SCENARIO #2

SCENARIO #3 (RECOMMENDED OPTION)

CONCLUSION
 We request that the City Council approve Scenario #3. This Scenario provides a significant financial contribution toward the public improvements while keeping the Mello-Roos cost for future homeowners at a sustainable level.  The recommended Scenario #3 Mello-Roos would provide approximately $28 million for construction costs for the public improvements. Santa Clara Valley Housing Group will provide the remaining $58.5 million (approximately 70% of the total costs).  We respectfully request that the City Council approve the creation of a Mello-Roos Community Facilities District for the Hilltown Development Project with a maximum tax of 2.00% so that we may commence the project.