REPORT TO THE CITY COUNCIL
DATE: Regular Meeting of February 14, 2023
TO: Mayor Walker-Griffin and Members of the City Council SUBMITTED BY: Dante Hall, City Manager
SUBJECT: Progress Update on the Parks Master Plan
RECOMMENDATION ACTION:
Receive an update from staff and the City’s consultant, MIG, on the progress of the Parks Master Plan.
BACKGROUND:
In September of 2022, the City entered into an agreement with MIG to complete a Parks Master Plan and Americans with Disabilities Act (ADA) Assessment for Park Facilities. Once complete, the Parks Master Plan and ADA Assessment will provide the information needed for the City to take a proactive approach over the next decade in addressing aging park facilities, responding to the need for inclusive parks, and anticipating the future recreation needs of the community. This information will support informed discussion and decision-making related to park needs and opportunities and allow the City to strategically allocate resources and leverage grant opportunities to ensure the needs of the community are met in the future.
MIG’s scope of work include the following phases:
Phase 1: State of the Park System
Phase 2: ADA Assessment
Phase 3: Park Needs and Opportunities
Phase 4: Recommendations and Prioritization
Phase 5: Plan Development
The project team is currently working through Phase 3 - Park Needs and Opportunities. This Phase will include a robust public participation and outreach effort. Attached to this staff report is a summary document that provides more detail on activities completed and activities planned.
FISCAL IMPACT:
There is no fiscal impact associated with this item.
ATTACHMENTS:
Parks and Recreation Facilities Master Plan Progress Summary Parks and Recreation Facilities Master Plan Presentation