DATE: April 14, 2022
TO: Planning Commission
FROM: Rachel Molina, Assistant City Manager
BY: Ryan Leonard, AICP, Senior Planner
SUBJECT: CUP19-00010, TPM22-00002 & DA22-00001 (Covington Group, Inc. ; APNs:
3064-351-03, 3064-361-01, 3064-391-01, 3064-401-02)
RECO

MMENDED ACTION
It i
s recommended that the Planning Commission adopt Resolution No. PC -2022-03, recommending that the City Council make the environmental determination pursuant to the California Environmental Quality Act (CEQA) by certifying the Final Environmental Impact Report (FEIR) and adopting a statement of overriding considerations and adopt R esolution Nos. PC- 2022-04 and PC-2022-05, recommending that the City Council approve CUP19-00010, TPM22- 00002 and DA22-00001.

BACKG
ROUND
Pr
oposal: A Conditional Use Permit (CUP) has been filed to construct a 3,745,429 square foot distribution center and industrial park on 194.8 gross acres. The project, identified as “Hesperia Commerce Center II” will consist of the construction of three industrial/warehouse buildings with associated office spaces, surface parking and loading areas. The northwesternmost building (referred to as Building 1) is proposed to be 1,567,317 square feet ; the southernmost building (referred to as Building 2) is proposed to be 2,065,987 square feet and would potentially be divided between two spaces within the same building; and the northeastern most building (referred to as Building 3) would be 112,125 square feet.

A t
entative parcel map has also been filed to rearrange the four existing parcels into four new parcels that generally follow the alignment of the future buildings. In addition, a Development Agreement (DA) is proposed that would allow the CUP to be effective for 12 years initially, with a provision allowing an automatic 8-year extension. In return, the City is requiring the Developer to construct certain off -site water and sewer infrastructure within the first 3 years from when the Development Agreement is executed (described in more detail below ). The applicant is also required to provide a one-time agreed upon community benefit contribution to the City.

Locati
on: On the north side of Phelan Road, west of Highway 395, south of Yucca Terrace Drive and east of the transmission line utility corridor.

Cur
rent General, Plan, Zoning and Land Uses: The site is within the Commercial Industrial Business Park (CIBP) Zone of the Main Street and Freeway Corridor Specific Plan (Specific Plan).

The surrounding land is designated as noted on Attachment 2. The 194.8- acre site is vacant.

Land uses to the north, on the opposite side of Yucca Terrace Drive, primarily consist of vacant land and scattered sites with unpermitted storage of trucks. The land uses to the east consist of vacant land followed by Highway 395. The land uses to the south consist of vacant land and large

Page 3 ends

Attachment 10
lot rural residences. The utility corridor and City boundary run parallel to the western boundary of the site and a number of rural residences are located on the opposite side of the transmission lines (Attachment 3).

ISSUES/ANALYSIS
CUP19-00010: The Hesperia Commerce Center II project consists of approximately 3,745,429 square feet of gross building area on approximately 194.8 gross acres. The northwesternmost building (referred to as Building 1) is proposed to be 1,567,317 square feet, the southernmost building (referred to as Building 2) is proposed to be 2,065,987 square feet, which would potentially be divided between two spaces within the same building, and the northeastern most building (referred to as Building 3) would be 112,125 square feet. Office space within Building 1 and Building 2 would total up to 20,000 square feet within each building. The office space within Building 3 would total up to 9,000 square feet. Depending on the number of future tenants, office areas could be distributed among four individual office spaces within the corners of each building or may be concentrated within one office in each building. Regardless of how the office spaces are distributed within each individual building, the square footages described above are the maximum amount of office area that would be allowed since it generates a higher parking demand than traditional warehouse area.

The proposed development complies with all site development regulations, including the minimum building requirements, landscaping, and number of parking spaces. The parking regulations require a minimum of 1,771 parking spaces, based upon the requirements listed in Table 1 . As proposed the project complies with the minimum number of parking spaces.

TABLE 1-PARKING REQUIREMENTS
BUILDING 1

Proposed
Building Square
Footage
Parking Formula Spaces
Required
Spaces
Provided
Warehouse 1,547,317 SF 20 spaces + 0.40/1,000 sq. ft. of building over 10,000 sq. ft
635

Office 20,000 SF 5 spaces per 1,000 sq. ft. gross
floor area
100
TOTAL 1,567,317 SF 735 748

BUILDING 2
Warehouse 2,045,987 SF 20 spaces + 0.40/1,000 sq. ft. of building over 10,000 sq. ft
834
Office 20,000 SF 5 spaces per 1,000 sq. ft. gross
floor area
100
TOTAL 2,065,987 SF 934 950

BUILDING 3
Warehouse 103,125 SF 20 spaces + 0.40/1,000 sq. ft. of
building over 10,000 sq. ft
57 Office 9,000 SF 5 spaces per 1,000 sq. ft. gross
floor area
45 TOTAL 112,125 SF 102

102

PROJECT
TOTAL
3,745,429 SF 1,771 1,800

Page 4 ends

The conventional parking spaces would be provided along the eastern and western sides of each building. Truck docks are proposed to be located on the north and south sides of Buildings 1 and 2, and on the south side of Building 3. Building 1 would provide 253 loading docks, Building 2 would provide 346 loading docks, and Building 3 would provide 14 loading docks. In addition, the project also provides 1,591 truck/trailer parking spaces . The truc k/trailer parking would be provided on the south side of Building 2, in between Buildings 1 and 2, and on the north side Building 1. A gated entry is proposed for each building; the gated areas would not be shared between the buildings. An 8-foot tall wrought iron fence is planned between Buildings 1 and 2 and would separate the row of contiguous truck/trailer parking spaces.

On the south side of the project site, Building 2 is proposed to be setback 245 feet from Phelan Road. Within the 245-foot setback, the front of the building would consist of truck loading docks followed by a single row of approximately 250 oversized parking stalls for truck s/trailers. The truck/trailer parking stalls would be setback 60 feet from Phelan Road. On the north side of the site, Building 1 is proposed to be setback 428 feet from Yucca Terrace Drive. Within the 428-foot setback, the front of the building would consist of truck loading docks, followed by 3 rows of approximately 400 oversized parking stalls for trucks/trailers. The truck/trailer parking stalls would be setback approximately 60 feet from the right-of-way. As proposed, an 8-foot high wrought iron fence would be constructed at the property line and a 60 foot wide landscape planter would be installed in front of both truck parking areas. The Specific Plan requires loading and truck parking areas to be screened. Therefore, as a condition of approval staff is requiring both truck parking areas that are adjacent to the right -of-way to be fully screened by a minimum 8- foot high decorative block wall.

Primary access to the site will be provided from a new public roadway (Caliente Road) that will be constructed by the project. Caliente Road is planned as a 70-foot wide Industrial Collector that will provide reciprocal access with the adjacent properties to the east and will form a connection between Yucca Terrace Drive to the north and Phelan Road to the south. The intersection of Caliente Road and Phelan Road will be fully signalized. A second primary access will be provided at the intersection of Yucca Terrace Drive and Highway 395. This intersection will be fully signalized and will allow full turning movements and controlled access onto Highway 395 .

Ultimately 9 driveway approaches will provide access from the perimeter streets to the project site; 7 driveway approaches will be provided off Caliente Road; one driveway approach will be provided off Phelan Road at the western end of the site that will provide right -in and right -out access to the site; and one driveway approach will be located off of Yucca Terrace drive at the western end of the site (Attachment 6).

The project would be responsible for the construction of curb, gutter and sidewalk along the project frontage of Yucca Terrace Drive, Phelan Road, the future public street (Caliente Road) and a portion of Highway 395. In addition, the project would be responsible for paving Yucca Terrace Drive, which is currently a n unimproved roadway, from the western boundary of the project to Highway 395. The project will also be responsible for the construction of Caliente Road that will connect Phelan Road to the south with Yucca Terrace Drive to the north. Finally, the project will be responsible for constructing the required traffic signals at the Phelan Road and Caliente Road intersection, and the Yucca Terrace Drive and Highway 395 intersection.

The architecture of the proposed warehouse buildings complies with the architectural requirements of the Specific Plan (Attachments 4 & 5). The large concrete tilt-up buildings within the project exhibit a clean, corporate look, exhibiting several exterior building colors and multiple expansion joints. The buildings have been designed to incorporate a prominent glass entry way

Page 5 ends

at the corners of each building. In addition, the sides of the building which are adjacent to the right-of-way feature prominent tower elements , copper accent panels, sand blasted concrete accent walls and decorative windows. The buildings also feature painted bands, reveals, and decorative panels on all four sides of the building. Building height will be approximately 48 feet.

The project also satisfies the minimum landscaping requirements. The minimum required landscape coverage is 10% of the developed site; the project provides 991,830,700 square feet (11.7%) of total landscape coverage, a majority of which will be located in front of the site and viewable from the right-of-way.

Water and Sewer. Sanitary sewer service to the project will be provided by a new sewer system that will be constructed as a part of the project (Attachment 7). The new sewer system will include a lift station located within the right of way of Yucca Terrace Drive (west of the Oro Grande Wash) and force main and gravity sewers (sizes to be determined) beginning at the intersection of Cataba Road and Acacia Road. From there the sewer system will extend north along Cataba Road to Yucca Terrace Drive, ultimately extending approximately 1,100 feet across the Oro Grande Wash, and then continuing west along Yucca Terrace Drive and crossing under Highway 395 to Caliente Road. From there the sewer system will extend south along Caliente Road to Phelan Road.

The project will also construct a new 16-inch water line to provide adequate water service for the project (Attachment 7). This new 16-inch transmission water line will begin at the intersection of Highway 395 and Sultana Street and traverse west along Sultana Street crossing the Oro Grande Wash to Los Banos Avenue. From there it will traverse north along Las Banos Avenue to Phelan Road, then east along Phelan Road to Caliente Road. From there it will traverse north to Yucca Terrace Drive.

Both the new 16-inch water pipeline and sewer system will be installed using the jack and bore method so as not disturb the Oro Grande Wash. A pit will be constructed at each end of the Wash and the new pipe will be bored through from one pit to the other without disturbing the ground surface.

Drainage. Stormwater collected by the project’s stormwater system would drain into two below - grade, open, earthen infiltration basins within the northeastern portion of the project site, and one below grade infiltration basin in the middle of the project site between Buildings 1 and 2. The infiltration/basin system would be designed to infiltrate and retain all of the stormwater generated by the 2-year through 100-year, 24-hour storm event.

Development Agreement. Construction of the 3,745,429 square foot project will likely take several years. The Development Code only provides an initial three- year effective period.

Consequently, the developer has negotiated a Development Agreement (DA) to allow the CUP to be effective for 12 years initially, with a provision allowing an automatic 8-year extension. In return, the City is requiring the Developer to construct the off-site water and sewer infrastructure within the first 3 years from when the Development Agreement is executed. In addition, the applicant is required to provide a one-time agreed upon community benefit contribution. The developer is also required to annex into the City-wide industrial community facilities district (CFD) within the first 6 months from when the DA is approved.

The Development Agreement will allow the reimbursement for the cost of the offsite infrastructure (i.e. construction of the offsite water and sewer facilities ). As future development occurs in the

Page 6 ends

area, development projects that directly connect to and benefit from the offsite water and sewer infrastructure will be conditioned to pay their fair share fee obligation to the developer. The requirement to construct all of the off -site infrastructure within the first 3 years from when the Development Agreement is executed will ultimately benefit the surrounding area and will provide the required infrastructure for other development projects to move forward. The Development Agreement allows the reimbursement provisions for a maximum of 10 years from when the Development Agreement is executed.

TPM22-00002 (Parcel Map No. 20257): A tentative parcel map has also been filed to rearrange the four existing parcels into four new parcels that generally follow the alignment of the future buildings. Recordation of the parcel map will allow separate ownership of the buildings. A n irrevocable reciprocal access and shared parking agreement is required as a condition of approval, ensuring that all businesses within the project will have adequate access and parking.

ENVIRONMENTAL ANALYSIS

Given the size and regional importance of this project, CEQA requires that the environmental impact of the project be analyzed. An initial study was prepared, which determined that the project may have a significant impact on the environment. As a result, an Environmental Impact Report (EIR) was required. A Notice of Preparation (NOP) was distributed for public review for a period of 30 days from November 21, 2019 thru December 20, 2019 and the Draft EIR was distributed for a 45 -day public period from September 16 , 2020 thru October 31, 2020. The public review period was subsequently extended until November 16, 2020 The environmental document was circulated to local, state and federal agencies and organizations as well as surrounding property owners. Eight comment letters were received during the Initial Study/NOP comment period; seven comment letters were received during the Draft EIR comment period; and two letters were received on the Draft EIR after the comment period was closed. The letters, as well as the responses to them are included in the Final EIR. The Draft and Final EIR are available for review on the City website and have been provided to the Commission under separate cover.

The Draft EIR identified potentially significant impacts of the project and discussed numerous mitigation measures proposed to address potential impacts of the project. Mitigation measures presented in the Draft EIR have been included in the Mitigation Monitoring Reporting Program, which is attached as Attachment 8 and also incorporated by reference in the conditions of approval (Attachments 9 & 10 ). The mitigation measures for the project will reduce potentially significant impacts to Aesthetics , Biological Resources, Cultural Resources, Hazards and Hazardous Materials, and Tribal Cultural Resources. However, the EIR concluded that in spite of mitigation measures, the project could result in significant and unavoidable impacts to Air Quality, Greenhouse Gas Emissions , Noise and Transportation. Consequently, pursuant to CEQA guidelines, a statement of overriding considerations must be made in order to approve the project.

The following is a summary of the significant and unavoidable impacts as a result of the project:

Air Quality: The Project site is located within the Main Street and Freeway Corridor Specific Plan and is designated for Commercial/Industrial Business Park (CIBP) uses. The CIBP designation is intended to provide for service commercial, light industrial, light manufacturing, and industrial support uses. The Project proposes land uses that are consistent with development anticipated under the site’s existing General Plan designation. The Project would therefore conform to local land use plans.

Page 7 ends

However, the long-term project operation will create vehicular emissions that would exceed the Mojave Desert Air Quality Management District’s (MDAQMD) daily emission thresholds . The project’s impacts related to volatile organic compounds (VOC), nitric oxide (NOx) and particulate matter (PM10) emissions will individually and cumulatively result in significant and unavoidable air quality impacts. In addition, the project would result in cumulatively considerable impacts related to the potential to conflict with the MDAQMD’s thresholds, result in a cumulatively considerable net increase of criteria pollutants (VOC, NOx, and PM10), and expose sensitive receptors to substantial pollutant concentrations (VOC, NOx, and PM10). Additionally, it should be noted that the majority of the Project’s NOX and PM10 emissions are derived from vehicle usage. Although mitigation measures would reduce operational emissions from on-road vehicles to the extent feasible, due to the size and type of the project, it is not feasible to implement mitigation measures to reduce the operational mobile source emissions. Therefore, the project’s impacts related to the potential to conflict with or obstruct implementation of the MDAQMD’s regional thresholds and the project operational VOC, NOx, and PM10 emissions would remain significant. In addition, the project would result in cumulatively considerable impacts related to the potential to conflict with the MDAQMD regional thresholds, result in a cumulatively considerable net increase of criteria pollutants (VOC, NOx, and PM10), and expose sensitive receptors to substantial pollutant concentrations (VOC, NOx, and PM10). The EIR concludes that there are significant unavoidable impacts to air quality and a finding of overriding considerations is included in the resolution certifying the EIR.

Greenhouse Gas Emissions: Long-term operations of the Project would result in greenhouse gas emissions through mobile sources and on- site equipment, area sources (landscape maintenance equipment); energy use (natural gas and generation of electricity consumed by the Project); generation of electricity associated with wastewater treatment and with water supply, treatment, and distribution; and solid waste disposal. Annual greenhouse gas emissions from these sources were estimated in the EIR.

With applicable regulatory requirements and project design features, the Project would result in approximately 55,599 MT CO2e per year, which would exceed the GHG threshold of 3,000 MT CO2e per year. Therefore, the Project would generate GHG emissions, either directly or indirectly, that may have a significant impact on the environment, and this would represent a cumulatively potentially significant impact. Mitigation measures would be required that would reduce p roject- generated construction and operational GHG emissions. The EIR determined that the effectiveness of the required mitigation measures cannot be accurately quantified. Therefore, project-generated greenhouse gas emissions would still exceed the applied threshold of 3,000 MT CO2e per year. T he EIR concludes that there are significant unavoidable impacts upon greenhouse gas emissions and a finding of overriding considerations is included in the resolution certifying the EIR for this project.

Noise: The EIR determined that the project would result in significant off -site operational traffic noise impacts along Main Street between U.S. Highway 395 and Cataba Road. Based on the infeasibility of potential mitigation to adequately reduce off-site project traffic noise levels to less- than-significant levels, and because there are no assurances that noise-reducing measures could be adequately implemented, no reasonably feasible and implementable mitigation measures have been identified. Thus, impacts related to the p roject’s off -site operational traffic noise impacts would remain significant and unavoidable and a finding of overriding considerations is included in the resolution certifying the EIR for this project.

Page 8 ends

Traffic/Circulation: Beginning on July 1, 2020, vehicle miles traveled (VMT) is used to determine the significance of transportation impacts. The San Bernardino Transportation Analysis Model (SBTAM) is an accepted program to estimate VMT as it considers interaction between different land uses based on socio-economic data such as population, households, and employment. The EIR determined that the project would exceed the current thresholds for VMT, resulting in a project-specific VMT impact that is significant and unavoidable. Mitigation Measures are proposed in the EIR to reduce impacts. However, the effectiveness of some of the mitigation strategies that have potential to reduce the p roject VMT are dependent on unknown building tenant(s). In addition, the EIR determined that the project may increase a hazardous condition due to queuing impacts at various intersections that the City does not have jurisdiction over, therefore, these improvements cannot be assumed to be in place prior to project’s occupancy. The EIR determined that the project’s impact to increase hazardous conditions (i.e. queuing) would be significant and unavoidable.

Mitigation measures are proposed to reduce potential transportation impacts, however, since implementation of the roadway improvements cannot be guaranteed by project opening or project build-out, mitigation and improvements are rendered infeasible. The significance determinations are based on a conservative worst -case scenario whereby it is assumed that mitigation for all significant impacts outside the control of the City are infeasible and therefore, the impacts are significant and unavoidable. A finding of overriding considerations is included in the resolution certifying the EIR for this project.

Overriding Considerations: Pursuant to CEQA, the City must balance the benefits of the project against any significant and unavoidable environmental impacts that cannot be mitigated to less than significant. If the benefits of the Project outweigh these environmental impacts, those impacts are considered “acceptable.” Since the impact upon Air Quality, Greenhouse Gas Emissions, Noise and Transportation are considered significant and unavoidable, findings for a Statement of Overriding Considerations must be made. T he project’s benefits include strengthening the local economy by providing new employment opportunities for local residents and generating tax revenues to maintain adequate infrastructure facilities. Further, the project will help satisfy the City's deficiency of high quality local jobs, as most residents must currently travel outside the City to obtain higher paying jobs . The proposed project would use the locational characteristics (specifically, the project’s proximity to the 15 freeway and Highway 395) to provide needed flexible industrial space to businesses wishing to invest in the City, as well as to provide approximately 3,134 permanent jobs both directly and indirectly in the region. The project’s social and economic benefits render these significant and unavoidable impacts acceptable.

Conclusion: In summary, because the project is consistent with the City’s General Plan, most of the project’s impacts, whether less than significant, mitigable, or significant and unavoidable were known and acknowledged by the City when the General Plan EIR was adopted in 2010.

Prior to acting on the project, the Planning Commission must recommend that the City Council make the environmental determination, certifying that the Final EIR is complete; that it has been prepared in compliance with CEQA; that it reflects the City’s independent judgment; and that all impacts from carrying out the project have been identified and disclosed to the public. Resolution PC-2022-03 has been prepared to document this determination. Once that has occurred, the Planning Commission can consider t he conditional use permit and the tentative parcel map. If recommended for approval, the mitigation monitoring and reporting program will be administered with the project approval.

FISCAL IMPACT

Page 9 ends

None. The development will be subject to payment of development impact fees and will be required to annex into the City Industrial CFD to pay for the ongoing maintenance of public infrastructure and services.

ALTERNATIVE(S)

1. Provide alternative direction to staff.

ATTACHMENT(S)

1. Site plan

2. General Plan / Zoning Map

3. Aerial photo

4. Color rendering

5. View Analysis

6. Traffic and Circulation Improvements

7. Off-site Water and Sewer Alignments

8. Resolution No. PC-2022-03 (Environmental findings to recommend adoption of the EIR including the Findings of Fact, Statement of Overriding Considerations and MMRP)

9. Resolution No. PC-2022-04, with list of conditions (CUP19-00010)

10. Resolution No. PC-2022-05, with list of conditions (TPM22-00002/PM-20257)

11. Draft EIR (provided under separate cover)

12. Final EIR (provided under separate cover)

13. Development Agreeement (provided under separate cover)

Page 10 ends

APPLICANT(S):

COVINGTON GROUP, INC.

FILE NO(S):

CUP19-00010, TPM22-00002 & DA22-00001
LOCATION:

ON THE NORTH SIDE OF PHELAN ROAD, WEST O F
HIGHWAY 395, SOUTH O F YUCCA TERRACE DRIV E AND
EAST OF THE TRANSMISSION LINE UTILITY CORRIDOR.

APNs:
3064-351-03, 3064-361-01, 3064-391-01,
3064-401-02
PROPOSAL:

CONSIDERATION OF A CONDITIONAL USE PERMIT TO CONSTRUCT A 3,745,429 MILLION

SQUARE FOOT DISTRIBU TION CENTER AND INDU STRIAL PARK IN CONJUNCTION WITH A

TENTATIVE PARCEL MAP TO REORGANIZE THE FOUR EXISTING PARCELS INT O FOUR NEW PARCELS AND A DEVELO PMENT AGREEMENT ON 194.8 GROSS ACRES. THE PROPOSAL

INCLUDES AN ENVIRONM ENTAL IM PACT REPORT PREPARED IN COMPLIANCE WITH THE

CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA)
N

SITE PLAN
ATTACHMENT 1

Page 11 ends

APPLICANT(S):

COVINGTON GROUP, INC.

FILE NO(S):

CUP19-00010, TPM22-00002 & DA22-00001
LOCATION:

ON THE NORTH SIDE OF PHELAN ROAD, WEST OF
HIGHWAY 395, SOUTH O F YUCCA TERRACE DRIV E AND
EAST OF THE TRANSMISSION LINE UTILITY CORRIDOR.

APNs:
3064-351-03, 3064-361-01, 3064-391-01,
3064-401-02
PROPOSAL:

CONSIDERATION OF A CONDITIONAL USE PERMIT TO CONSTRUCT A 3,745,429 MILLION

SQUARE FOOT DISTRIBU TION CENTER AND INDU STRIAL PARK IN CONJUNCTION WITH A

TENTATIVE PARCEL MAP TO REORGANIZE THE FOUR EXISTING PARCELS INT O FOUR NEW PARCELS AND A DEVELO PMENT AGREEMENT ON 194.8 GROSS ACRES. THE PROPOSAL

INCLUDES AN ENVIRONM ENTAL IM PACT REPORT PREPARED IN COMPLIANCE WITH THE

CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA)
N

GENERAL PLAN AND ZONING MAP
ATTACHMENT 2
SITE

Page 12 ends

APPLICANT(S):

COVINGTON GROUP, INC.

FILE NO(S):

CUP19-00010, TPM22-00002 & DA22-00001
LOCATION:

ON THE NORTH SIDE OF PHELAN ROAD, WEST OF
HIGHWAY 395, SOUTH O F YUCCA TERRACE DRIV E AND
EAST OF THE TRANSMISSION LINE UTILITY CORRIDOR.

APNs:
3064-351-03, 3064-361-01, 3064-391-01,
3064-401-02
PROPOSAL:

CONSIDERATION OF A CONDITIONAL USE PERMIT TO CONSTRUCT A 3,745,429 MILLION

SQUARE FOOT DISTRIBU TION CENTER AND INDU STRIAL PARK IN CONJUNCTION WITH A

TENTATIVE PARCEL MAP TO REORGANIZE THE FOUR EXISTING PARCELS INT O FOUR NEW PARCELS AND A DEVELO PMENT AGREEMENT ON 194.8 GROSS ACRES. THE PROPOSAL

INCLUDES AN ENVIRONM ENTAL IM PACT REPORT PREPARED IN COMPLIANCE WITH THE

CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA)
N

AERIAL PHOTO
ATTACHMENT 3
SITE

Page 13 ends

APPLICANT(S):

COVINGTON GROUP, INC.

FILE NO(S):

CUP19-00010, TPM22-00002 & DA22-00001
LOCATION:

ON THE NORTH SIDE OF PHELAN ROAD, WEST OF
HIGHWAY 395, SOUTH O F YUCCA TERRACE DRIV E AND
EAST OF THE TRANSMISSION LINE UTILITY CORRIDOR.

APNs:
3064-351-03, 3064-361-01, 3064-391-01,
3064-401-02
PROPOSAL:

CONSIDERATION OF A CONDITIONAL USE PERMIT TO CONSTRUCT A 3,745,429 MILLION

SQUARE FOOT DISTRIBU TION CENTER AND INDU STRIAL PARK IN CONJUNCTION WITH A

TENTATIVE PARCEL MAP TO REORGANIZE THE FOUR EXISTING PARCELS INT O FOUR NEW PARCELS AND A DEVELO PMENT AGREEMENT ON 194.8 GROSS ACRES. THE PROPOSAL

INCLUDES AN ENVIRONM ENTAL IM PACT REPORT PREPARED IN COMPLIANCE WITH THE

CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA)
N

COLOR RENDERING
ATTACHMENT 4

Page 14 ends

APPLICANT(S):

COVINGTON GROUP, INC.

FILE NO(S):

CUP19-00010, TPM22-00002 & DA22-00001
LOCATION:

ON THE NORTH SIDE OF PHELAN ROAD, WEST OF
HIGHWAY 395, SOUTH O F YUCCA TERRACE DRIV E AND
EAST OF THE TRANSMISSION LINE UTILITY CORRIDOR.

APNs:
3064-351-03, 3064-361-01, 3064-391-01,
3064-401-02
PROPOSAL:

CONSIDERATION OF A CONDITIONAL USE PERMIT TO CONSTRUCT A 3,745,429 MILLION

SQUARE FOOT DISTRIBU TION CENTER AND INDU STRIAL PARK IN CONJUNCTION WITH A

TENTATIVE PARCEL MAP TO REORGANIZE THE FOUR EXISTING PARCELS INT O FOUR NEW PARCELS AND A DEVELO PMENT AGREEMENT ON 194.8 GROSS ACRES. THE PROPOSAL

INCLUDES AN ENVIRONM ENTAL IM PACT REPORT PREPARED IN COMPLIANCE WITH THE

CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA)
N

LINE OF SIGHT
ATTACHMENT 5

Page 15 ends

APPLICANT(S):

COVINGTON GROUP, INC.

FILE NO(S):

CUP19-00010, TPM22-00002 & DA22-00001
LOCATION:

ON THE NORTH SIDE OF PHELAN ROAD, WEST OF
HIGHWAY 395, SOUTH O F YUCCA TERRACE DRIV E AND
EAST OF THE TRANSMISSION LINE UTILITY CORRIDOR.

APNs:
3064-351-03, 3064-361-01, 3064-391-01,
3064-401-02
PROPOSAL:

CONSIDERATION OF A CONDITIONAL USE PERMIT TO CONSTRUCT A 3,745,429 MILLION

SQUARE FOOT DISTRIBU TION CENTER AND INDU STRIAL PARK IN CONJUNCTION WITH A

TENTATIVE PARCEL MAP TO REORGANIZE THE FOUR EXISTING PARCELS INT O FOUR NEW PARCELS AND A DEVELO PMENT AGREEMENT ON 194.8 GROSS ACRES. THE PROPOSAL

INCLUDES AN ENVIRONM ENTAL IM PACT REPORT PREPARED IN COMPLIANCE WITH THE

CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA)
N

TRAFFIC AND CIRCULATION IMPROVEMENTS
ATTACHMENT 6

Page 16 ends

APPLICANT(S):

COVINGTON GROUP, INC.

FILE NO(S):

CUP19-00010, TPM22-00002 & DA22-00001
LOCATION:

ON THE NORTH SIDE OF PHELAN ROAD, WEST O F
HIGHWAY 395, SOUTH O F YUCCA TERRACE DRIV E AND
EAST OF THE TRANSMISSION LINE UTILITY CORRIDOR.

APNs:
3064-351-03, 3064-361-01, 3064-391-01,
3064-401-02
PROPOSAL:

CONSIDERATION OF A CONDITIONAL USE PERMIT TO CONSTRUCT A 3,745,429 MILLION

SQUARE FOOT DISTRIBU TION CENTER AND INDU STRIAL PARK IN CONJUNCTION WITH A

TENTATIVE PARCEL MAP TO REORGANIZE THE FOUR EXISTING PARCELS INT O FOUR NEW PARCELS AND A DEVELO PMENT AGREEMENT ON 194.8 GROSS ACRES. THE PROPOSAL

INCLUDES AN ENVIRONM ENTAL IM PACT REPORT PREPARED IN COMPLIANCE WITH THE

CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA)
N

OFF-SITE WATER AND SEWER ALIGNMENTS
ATTACHMENT 7

Page 17 ends

RESOLUTION NO. PC-2022-03

A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF

HESPERIA, CALIFORNIA, RECOMMENDING THAT THE CITY COUNCIL

ADOPT ENVIRONMENTAL FINDINGS PURSUANT TO T HE CALIFORNIA

ENVIRONMENTAL QUALITY ACT, CERTIFY THE FINAL ENVIRONMENTAL IMPACT REPORT (SCH # 2019110418), ADOPT T HE STATEMENT OF

OVERRIDING CONSIDERATIONS, AND ADOPT A MITIGATION

MONITORING AND REPORTING PROGRAM

WHEREAS, the Hesperia C ommerce Center II project would consist of the construction of a 3,745,429 square foot distribution center and industrial park on 194.8 gross acres. The project includes the construction of three industrial/warehouse buildings with associated office spaces, surface parking and loading areas. The northwesternmost building (referred to as Building 1) is proposed to be 1,567,317 square feet ; the southernmost building (referred to as Building 2) is proposed to be 2,065,987 square feet; and the northeastern most building (referred to as Building 3) would be 112,125 square feet . A tentative parcel map has also been filed to rearrange the four exi sting parcels into four new parcels that generally follow the alignment of the future buildings. In addition, a Development Agreement (DA) is proposed that would among other things, allow the CUP to be effective for 12 years initially, with a provision to allow an automatic 8-year extension.

WHEREAS, the Project would be accessible to US Highway 395 and ultimately Interstate 15 and would promote the City's economic development by creating approximately 3,134 jobs for the citizens of Hesperia and surrounding communities, wou ld increase the City's tax base, would fulfill the growing demand for distribution and light industrial uses in the region, and would develop the land to the highest and best allowable use that is compatible with the City's General Plan, and Main Street and Freeway Corridor Specific Plan; and

WHEREAS, pursuant to the California Environmental Quality Act ("CEQA") (Public Resources Code $ 21000 et. seq,) and the State CEQA Guidelines (14 CCR $ 15000 et. seq.), the City of Hesperia is the lead agency for the Project as the public agency with general gover nmental powers; and

WHEREAS, the City of Hesperia, as lead agency, prepared an initial study, from which it was determined that an Environmental Impact Report ("EIR') should be prepared pursuant to CEQA in order to analyze all adverse environmental impacts of the Project; and

WHEREAS, a Notice of Preparation ( NOP") and the Initial Study identifying the scope of environmental issues were distributed to numerous state, federal, and local agencies and organizations from November 21, 2019 thru December 20, 2019 , for a period of 30 days, pursuant to State CEQA Guidelines sections 15082(a), 15103, and 15375. Eight comment letters were received during the Initial Study/NOP comment period and were incorporated into the Draft EIR ("DEIR"); and

WHEREAS, a public scoping meeting for the EIR was held at Hes peria City Hall on December 12, 2019; and

ATTACHMENT 8

Page 18 ends

W
HEREAS, the City completed the DEIR and circulated it with the Notice of Availability ('NOA") to affected public agencies and interested members of the public for a 45 -day public period from September 16, 2020 thru October 31, 2020 . The public review period was subsequently extended until November 16, 2020; and

WHEREAS, on April 14, 2022, the Planning Commission of the City of Hesperia conducted a duly noticed public hearing, at which time all interested parties were provided the opportunity to give testimony for or against the issue; and

WHEREAS, as contained herein, the City has endeavored in good faith to set forth the basis for its decision on the project; and

WHEREAS, the EIR for the project reflects the City’s independent judgment. The City has exercised independent judgment in accordance with Public Resources Code Section 21082.1(c)(3) in directing the consultant in the preparation of the EIR. The City has independently reviewed and analyzed the EIR and accompanying studies and finds that the report reflects the independent judgment of the City for the purposes of making decisions on the merits of the project; and

WHEREAS, all the requirements of CEQA, the State CEQA Guidelines, and the City's Local CEQA Guidelines have been satisfied in the EIR, which is sufficiently detailed so that all of the significant environmental effects of the project have been adequately evaluated; and

WHEREAS, the EIR prepared in connection with the project sufficiently analyzes both the feasible mitigation measures necessary to avoid or substantially lessen the p roject's environmental impacts and a range of feasible alternatives capable of eliminating or reducing these effects in accordance with CEQA, the State CEQA Guidelines, and the City's Local CEQA Guidelines.

WHEREAS, all legal prerequisites to the adoption of this Resolution have occurred.

NOW THEREFORE, BE IT RESOLVED BY THE CITY OF HESPERIA PLANNING COMMISSION AS FOLLOWS:

Section 1. The Planning Commission hereby specifically finds that all of the facts set forth in this Resolution are true and correct.

Section 2. Based upon substantial evidence presented to the Planning Commission during the above-referenced April 14, 2022, hearing, including public testimony and written and oral staff reports, this Commission specifically finds as follows:

a) The Planning Commission has independently reviewed, analyzed and considered the Final EIR and all written documentation and public comments prior to making recommendations on the proposed project; and

b) The Final EIR was prepared and completed in compliance with the provisions of CEQA, the State CEQA Guidelines, and the City's Local CEQA Guidelines; and

Page 19 ends

c) The
information and analysis contained in the Final EIR reflects the City’s independent judgment as to the environmental consequences of the proposed Project; and

d) The documents and other materials, including without limitation, staff reports, memoranda, maps, letters, and minutes of all relevant meetings, which constitute the administrative record of proceedings upon which the Planning Commission's decision is based are located at the City of Hesperia, Planning Division, 9700 Seventh Avenue, Hesperia, C A 92345. The custodian of the records is the Planning Division.

Section 3. That on the basis of the evidence contained in the administrative record of the Final EIR, the Planning Commission finds based on the information submitted, following the conclusion of the public comment period on the Draft EIR, and following the consultant's responses thereto, there is no significant new information concerning the p roject's environmental effects, feasible mitigation measures, or feasible project alternatives; therefore there is no need or requirement to recirculate the EIR for additional public comment

Section 4. That the Planning Commission of the City of Hesperia hereby recommends that the City Council certify the Final EIR.

Section 5. Exhibit A (Findings of Facts and Statement of Overriding Considerations) and Exhibit B (Mitigation Monitoring and Reporting Program) of this Resolution provide findings required under Section 15091 of the State CEQA Guidelines for significant effects of the Project. Exhibit A of this Resolution provides the findings required under Section 15093 of the State CEQA Guidelines relating to the acceptable adverse impacts of the project due to overriding considerations. The City has balanced the economic, legal, social, technological, and other benefits of the project against the unavoidable environmental risks that may result, and finds that the specific economic, legal, social, technological, and other benefits outweigh the unavoidable adverse environmental effects. Therefore, the Planning Commission hereby recommends that the City Council adopt the Findings of Facts and Statement of Overriding Considerations attached hereto as Exhibit A.

Section 6. Pursuant to Public Resources Code Section 21081.6, the Planning Commission hereby recommends approval of the Mitigation Monitoring and Reporting Program attached as Exhibit B to this Resolution and recommends the Council require the Project to comply with the mitigation measures contained therein. The Planning Commission finds that these mitigation measures are fully enforceable on the Project and shall be binding upon the City and affected parties.

Section 7. The Secretary shall certify to the adoption of this Resolution.

Page 20 ends

ADOP
TED AND APPROVED this 14th day of April 2022.

_____________________________________
Roger Abreo, Chair, Planning Commission AT
TEST:
_________
______________________________
Maricruz Montes, Secretary, Planning Commission

Page 21 ends

EXHIBIT A- FINDINGS OF FACT AND STATEMENT OF OVERRIDING CONSIDERATION

Page 22 ends

Findings of Fact and Statement of Overriding Considerations Hesperia Commerce Center II EIR
SCH No. 2019110418
Prepared for:

City of Hesperia, Planning Department
9700 Seventh Avenue
Hesperia, California 92645

Prepared by:

38 North Marengo Avenue
Pasadena, California 91101

MARCH 2022

Page 23 ends

Printed on 30% post-consumer recycled material.

Page 24 ends

12122
i March 2022
Table of Contents
SECTION PAGE NO.
1 INTRODUCTION ................................ ................................ ................................ ................................ ............. 1

1.1 Purpose ................................................................................................................................................... 1

1.1.1 Record of Proceedings ............................................................................................................. 2

1.1.2 Custodian and Location of Records ......................................................................................... 3 2 CEQA FINDINGS OF INDEPENDENT JUDGEMENT ................................ ................................ ......................... 5

2.1 Independent Review and Analysis ......................................................................................................... 5

2.2 Impacts Determined to Be Significant and Unavoidable ..................................................................... 5

2.2.1 Air Quality .................................................................................................................................. 6

2.2.2 Greenhouse Gas Emissions .................................................................................................. 15

2.2.3 Noise ....................................................................................................................................... 18

2.2.4 Transportation ........................................................................................................................ 21

2.3 Impacts Determined to Be Less Than Significant with Mitigation .................................................... 25

2.3.1 Aesthetics ............................................................................................................................... 26

2.3.2 Air Quality ............................................................................................................................... 32

2.3.3 Biological Resources ............................................................................................................. 33

2.3.4 Cultural Resources ................................................................................................................ 47

2.3.5 Geology and Soils .................................................................................................................. 52

2.3.6 Hazards and Hazardous Materials ....................................................................................... 53

2.3.7 Tribal Cultural Resources ...................................................................................................... 58

2.4 Impacts Determined to Be Less Than Significant ............................................................................. 59

2.4.1 Aesthetics ............................................................................................................................... 60

2.4.2 Agriculture and Forestry Resources ...................................................................................... 61

2.4.3 Air Quality ............................................................................................................................... 62

2.4.4 Biological Resources ............................................................................................................. 64

2.4.5 Energy ..................................................................................................................................... 66

2.4.6 Geology and Soils .................................................................................................................. 68

2.4.7 Greenhouse Gas Emissions .................................................................................................. 71

2.4.8 Hazards and Hazardous Materials ....................................................................................... 72

2.4.9 Hydrology and Water Quality ................................................................................................. 73

2.4.10 Land Use ................................................................................................................................ 82

2.4.11 Mineral Resources ................................................................................................................. 84

2.4.12 Noise ....................................................................................................................................... 84

2.4.13 Population and Housing ........................................................................................................ 88

2.4.14 Public Services ....................................................................................................................... 89

2.4.15 Recreation .............................................................................................................................. 92

2.4.16 Transportation ........................................................................................................................ 92

Page 25 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
ii March 2022

2.4.17 Utilities and Service Systems ................................................................................................ 95

2.4.18 Wildfire ................................................................................................................................. 102 3 FINDINGS ON PROJECT ALTERNATIVES ................................ ................................ ................................ .... 109

3.1 Alternatives Considered and Eliminated During the Scoping/Project Planning Process .............. 109

3.2 Alternatives Selected for Further Analysis ....................................................................................... 111

3.2.1 Alternative 1: No Project/No Development Alternative ..................................................... 111

3.2.2 Alternative 2: No Project/Other Development Project Alternative ....................................... 113

3.2.3 Alternative 3: Reduced Development Intensity Alternative ............................................... 114

3.2.4 Environmentally Superior Alternative ................................................................................. 118 4 GENERAL CEQA FINDINGS ................................ ................................ ................................ ........................ 119

4.1 Findings Regarding Recirculation ..................................................................................................... 119

4.2 Legal Effects of Findings ................................................................................................................... 120 5 STATEMENT OF OVERRIDING CONSIDERATIONS ................................ ................................ ...................... 121 6 CONCLUSION ................................ ................................ ................................ ................................ ............. 125 7 REFERENCES CITED ................................ ................................ ................................ ................................ .. 127

Page 26 ends

12122
1 March 2022
1 Introduction
This statement of Findings of Fact (Findings) addresses the environmental effects associated with the proposed Hesperia Commerce Center II Project (project), as described in the Environmental Impact Report (EIR). These Findings are made pursuant to the California Environmental Quality Act (CEQA) (California Public Resources Code, Section 21000 et seq.), specifically California Public Resourc es Code, Sections 21081, 21081.5, and 21081.6, and the CEQA Guidelines (14 CCR 15000 et seq.), specifically Sections 15091 and 15093. The EIR examines the full range of potential effects of construction and operation of the project and identifies standard mitigation practices that could be employed to reduce, minimize, or avoid those potential effects.

1.1 Purpose
California Public Resources Code, Section 21081, and CEQA Guidelines Section 15091 require that the lead agency, in this case the City of Hesperia (City), prepare written findings for identified significant effects, accompanied by a brief explanation of the rationale for each finding. Specifically, CEQA Guidelines Section 15091 states, in part, that:
a) No public agency shall approve or carry out a project for which an EIR has been certified which identifies one or more significant environmental effects of the project unless the public agency makes one or more written findings for each of those significant effects, accompanied by a brief explanation of the rationale for each finding. The possible findings are:
1) Changes or alterations have been required in, or incorporated into, the project which avoid or substantially lessen the significant environmental effect as identified in the final EIR. 2) Such changes or alterations are within the responsibility and jurisdiction of another public agency and not the agency making the finding. Such changes have been adopted by such other agency or can and should be adopted by such other agency. 3) Specific economic, legal, social, technological, or other considerations, including provision of employment opportunities for h ighly trained workers, make infeasible the mitigation measures or project alternatives identified in the final EIR.

In accordance with California Public Resource Code, Section 21081, and CEQA Guidelines Section 15093, whenever significant effects cannot be mitigated to below a level of significance, the decision ‐making agency is required to balance, as applicable, the benefits of the project against its unavoidable environmental risks when determining whether to approve the project. If the benefits of a pro ject outweigh the unavoidable adverse environmental effects, the adverse effects may be considered “acceptable.” In that case, the decision -making agency may prepare and adopt a Statement of Overriding Considerations (SOC), pursuant to the CEQA Guidelines.

Section 15093 of the CEQA Guidelines state that:
a) CEQA requires the decision-making agency to balance, as applicable, the economic, legal, social, technological, or other benefits of a proposed project against its unavoidable environmental risks when determining whether to approve the project. If the specific economic, legal, social, technological, or other benefits of a proposed project outweigh the unavoidable adverse environmental effects, the adverse environmental effects may be considered "acceptable." b) When the lead agency approves a project which will result in the occurrence of significant effects which are identified in the final EIR but are not avoided or substantially lessened, the

Page 27 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
2 March 2022
agency shall state in writing the specific reasons to support its action based on the Final EIR and/or other information in the record. The statement of overriding considerations shall be supported by substantial evidence in the record.
c) If an agency makes a statement of overriding considerations, the statement should be included in the record of the project approval and should be mentioned in the notice of determination. This statement does not substitute for, and shall be in addition to, findings required pursuant to Section 15091.

The Final EIR identified potentially significant effects that could result from the project. The City finds that the inclusion of certain mitigation measures as part of the approval of the project will reduce most, but not all, of those effects to less -than‐significant levels. Those impacts that are not reduced to less ‐than‐significant levels are identified and overridden due to specific project benefits (see Section 5, Statement of Overriding Considerations).

As required by CEQA, the City, in adopting these Findings, also adopts a Mitigation Monitoring and Reporting Program (MMRP) for the project. The City finds that the MMRP, which is incorporated by reference and made a part of these Findings, meets the requi rements of California Public Resources Code, Section 21081.6, by providing for the implementation and monitoring of measures intended to mitigate potentially significant effects of the project.

In accordance with the CEQA Statutes and Guidelines, the City adopts these Findings for the project. Pursuant to California Public Resources Code, Section 21082.1(c)(3), the City also finds that th ese Findings reflect the City’s independent judgment as the lead agency for the project.

1.1.1 Record of Proceedings
For the purposes of CEQA and the Findings herein set forth the record of proceedings for the project and consists of those items listed in CEQA Section 21167.6(e), along with other miscellaneous items contained within the City’s files that are relevant to th e consideration of the project. The record of proceedings for the City’s decision on the project consists of the following documents, at a minimum and without limitation, which are incorporated by reference and made part of the record supporting these Findings:
• The Notice of Preparation, Notice of Availability, and all other public notices issued by the City in conjunction with the project
• The Draft EIR for the project and all technical appendices and documents relied upon or incorporated by reference • All written comments submitted by agencies, organizations, or members of the public during the public review comment period on the Draft EIR and the City’s responses to those comments • The Final EIR for the project
• The MMRP for the project
• All reports, studies, memoranda, maps, staff reports, or other planning documents relating to the project prepared by the City or consultants to the City with respect to the City’s compliance with the requirements of CEQA and with respect to the City’s action on the project • All documents submitted to the City by other public agencies or members of the public in connection with the Draft EIR
• Any minutes and/or verbatim transcripts of all information sessions, public meetings, and public hearings held by the City in connection with the project

Page 28 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
3 March 2022
• Any documentary or other evidence submitted to the City at such information sessions, public meetings, and public hearings
• All resolutions adopted by the City regarding the project, and all staff reports, analyses, and summarie s related to the adoption of those resolutions
• Matters of common knowledge to the City, including, but not limited to federal, state, and local laws and regulations • Any documents expressly cited in these Findings, in addition to those cited above; and any other materials required for the record of proceedings by CEQA Section 21167.6(e)

1.1.2 Custodian and Location of Records
The documents and other materials that constitute the Record of Proceedings for the City’s actions related to the project are located at the City of Hesperia, Planning D epartment, 9700 Seventh Avenue , Hesperia, California 92645. The City is the custodian of the Record of Proceedings for the project.

Page 29 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
4 March 2022

INTENTIONALLY LEFT BLANK

Page 30 ends

12122
5 March 2022
2 CEQA Findings of
Independent Judgement

2.1 Independent Review and Analysis
Under CEQA, the lead agency must (1) independently review and analyze the EIR; (2) circulate draft documents that reflect its independent judgment; (3) as part of the certification of an EIR, find that the report or declaration reflects the independent judgment of the lead agency; and (4) submit copies of the documents to the State Clearinghouse if there is state agency involvement or if the project is of s tatewide, regional, or area-wide significance (California Public Resources Code, Section 21082.1[c]).

This Findings reflects City’s independent judgment. The City has exercised independent judgment in accordance with CEQA Section 21082.1(c)(3) in retaining its own environmental consultant in the preparation of the EIR, as well as reviewing, analyzing and revising material prepared by the consultant.

Having received, reviewed, and considered the information in the Final EIR, as well as any and all other information in the record, the City hereby makes findings pursuant to and in accordance with CEQA Sections 21081, 21081.5, and 21081.6.

2.2 Impacts Determined to Be Significant
and Unavoidable
This section identifies the significant unavoidable impacts that require a statement of overriding considerations to be issued by the City, pursuant to Section 15093 of the CEQA Guidelines, if the project is approved. Based on the analysis contained in the EIR, the following impacts have been determined to fall within the “significant unavoidable impacts” category:
• Air Quality
o Applicable air quality plan
o Cumulatively considerable net increase of criteria pollutants • Long-term operational impacts
• Health effects of criteria air pollutants
o Expose sensitive receptors to substantial pollutant concentrations • Criteria air pollutant emissions and associated pollutant concentrations o Cumulative air quality impacts
• Greenhouse Gas Emissions
o Generation of greenhouse gas emissions
o Cumulative greenhouse gas impacts
• Noise
o Increase in noise levels
o Cumulative noise impacts

Page 31 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
6 March 2022
• Transportation
o Conflict with CEQA Guidelines Section 15064.3(b)
o Design hazards
• Queuing analysis
o Cumulative transportation impacts
Other impacts addressed under cumulatively considerable net increase of criteria pollutants (construction) are addressed in Section 2.3, Impacts Determined to Be Less Than Significant with Mitigation, and other impacts under expose sensitive receptors to substantial pollutant concentrations (local carbon monoxide concentrations, toxic air contaminant exposure, and valley fever ) and other emissions (such as those leading to odors) are addressed in Section 2.4, Impacts Determined to Be Less Than Significant. In addition, other impacts not addressed under increase in noise levels (short-term construction impacts and on-site operational noise) are addressed in Section

2.4. Other impacts not addressed under conflicts with design hazards (hazardous design features and incompatible uses) are addressed in Section 2.4.

2.2.1 Air Quality

2.2.1.1 Potentially Significant Impacts to Air Quality
Applicable Air Quality Plan
The Federal Particulate Matter Attainment Plan and Ozone Attainment Plan f or the Mojave Desert set forth a comprehensive set of programs that will lead the MDAB into compliance with federal and state air quality standards.

The control measures and related emission reduction estimates within the Federal Particulate Matter Attainm ent Plan and Ozone Attainment Plan are based upon emissions projections for a future development scenario derived from land use, population, and employment characteristics defined in consultation with local governments. A project is non -conforming with an air quality plan if it conflicts with or delays implementation of any applicable attainment or maintenance plan. A project is conforming if it complies with all applicable MDAQMD rules and regulations, complies with all proposed control measures that are not yet adopted from the applicable plan(s), and is consistent with the growth forecasts in the applicable plan(s) (or is directly included in the applicable plan). Zoning changes, specific plans, general plan amendments and similar land use plan changes wh ich do not increase dwelling unit density, do not increase vehicle trips, and do not increase vehicle miles traveled are also deemed to comply with the applicable air quality plan (MDAQMD 2016).

The Project would be required to comply with all applicable MDAQMD Rules and Regulations, including, but not limited to Rules 401 (Visibile Emissions), 402 (Nuisance), and 403 (Fugitive Dust). The Project site is located within the Main Street and Freeway Corridor Specific Plan and is designated for Commercial/Industrial Business Park (CIBP) uses. The CIBP designation is intended to provide for service commercial, light industrial, light manufacturing, and industrial support uses. The Project Applicant proposes land uses that are consistent with development anticipated under the site’s existing General Plan designation. The Project would therefore conform to local land use plans.

As discussed below, Project construction -source emissions would not exceed applicable MDAQMD regional thresholds after implementation of Mit igation Measure (MM) AQ -1. However, Project operational -source air pollutant emissions would result in exceedances of regional thresholds for emissions of VOC, NOx, and PM10, even after implementation of MM -AQ-4 through MM -AQ-6. As such, VOC, NO x, and PM 10 emissions are considered

Page 32 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
7 March 2022
significant and unavoidable and the Project would have the potential to increase the frequency or severity of a violation in the federal or state ambient air quality for on-going Project operations.

Based on the preceding considerations, the Project would conform to local land use plans and would comply with all applicable all MDAQMD Rules and Regulations. However, Project operational -source emissions have the potential to increase the frequency or severity of a violation in the f ederal or state ambient air quality standards.

On this basis, the Project is considered to potentially conflict with the Federal Particulate Matter Attainment Plan and Ozone Attainment Plan for the MDAB. Therefore, impacts associated with the conflicting w ith the MDAQMD would be significant and unavoidable.

Cumulatively Considerable Net Increase of Criteria Pollutants Construction and operation of the Project would result in emissions of criteria air pollutants from mobile, area, and/or stationary sources, which may cause exceedances of federal and state ambient air quality standards or contribute to existing nonattainment of ambient air quality standards. The following discussion identifies potential short-term construction and long-term operational impacts that would result from implementation of the Project.

Air pollution is largely a cumulative impact. The nonattainment status of regional pollutants is a result of past and present development, and the MDAQMD develops and implements plans for future attainment of ambient air quality standards. Although the area of the MDAB where the Project is located is currently designated a nonattainment area for federal and state O 3 standards and federal and state PM 10 standards, the MDAB has experienced a substantial reduction in maximum 8-hour concentrations of O3 over the past 30 years, as well as reductions in PM10 over time, as described in the respective MDAQMD O3 and PM10 attainment plans. CEQA thresholds are established at levels that the air basin can accommodate without affecting the attainment date for the AAQS. Based on these considerations, project-level thresholds of significance for criteria pollutants are relevant in the determination of whether a project’s individual emissions would have a cumulatively significant impact on air quality.

Long-Term Operational Impacts
Operation of the Project would generate VOC, NOx, CO, SOx, PM10, and PM2.5 emissions from mobile sources, including passenger vehicle and truck trips; area sources, including the use of consumer products, architectural coatings for repainting, and landscape maintenance equipment; energy sources, including combustion of fuels used for space and water heating; and on-site equipment. CalEEMod utilizes summer and winter EMFAC2017 emission factors in order to derive vehicle emissions associated with on-road vehicle activities, which vary by season.

The Project would exceed the numerical thresholds of significance established by the MDAQMD for emissions of VOC, NOX, and PM10. This impact would be potentially significant without mitigation.

Mitigation measures are required to minimize operational-related air quality impacts (MM-AQ-4 through MM-AQ-6).

For VOC emissions, the majority are derived from consumer products, including cleaning supplies, aerosols, and other consumer products. As such, the Project Applicant cannot meaningfully control the use of consumer products by future buildi ng users via mitigation; nonetheless, MM -AQ-6, requiring a low -VOC/green cleaning product educational program, would be implemented in effort to reduce VOC emissions from consumer products.

Additionally, the majority of the Project’s NOX and PM10 emissions are derived from vehicle usage, which n either the Project Applicant nor the City can substantively or materially affect reductions in Project mobile source emissions beyond what is already required. Nonetheless, MM-AQ-4 and MM-AQ-5 would be implemented to reduce mobile-source emissions of VOC, NOX, and PM10. While MM-AQ-4 through MM-AQ-6 would reduce Project-generated operational criteria air pollutant emissions, the associated emission reductions cannot be accurately quantified at

Page 33 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
8 March 2022
this time; therefore, em issions of VOC, NO X, and PM 10 would still exceed the MDAQMD thresholds with implementation of mitigation. Furthermore, no feasible mitigation measures or project design features beyond those already identified exist that would reduce these emissions to levels that are less than significant. Therefore, even with the incorporation of mitigation, long -term impacts associated with a cumulatively considerable net increase of criteria pollutants for which the Project region is non-attainment would be significant and unavoidable.

Health Effects of Criteria Air Pollutants
Construction of the Project would result in emissions that would not exceed the MDAQMD thresholds for criteria air pollutants, including VOC, after implementation of MM -AQ-1. Operation of the Project, however, would result in emissions that would exceed the MDAQMD thresholds for criteria air pollutants including VOC, NOx, and PM10, even after implementation of MM-AQ-4 through MM-AQ-6.

Under the heading Pollutants and Effects, health effects associated with O 3 include respiratory symptoms, worsening of lung disease leading to premature death, and damage to lung tissue (CARB 2019 a). VOCs and NO x are precursors to O3, for which the MDAB is designated as nonattainment with respect to the NAAQS and CAAQS.

The contribution of VOCs and NO x to regional ambient O3 concentrations is the result of complex photochemistry.

The increases in O3 concentrations in the MDAB due to O3 precursor emissions tend to be found downwind of the source location because of the time required for the photochemical reactions to occur. Further, the potential for exacerbating excessive O 3 concentrations would also depend on the time of year that the VOC emissions would occur, because exceedances of the O 3 NAAQS and CAAQ S tend to occur between April and October when solar radiation is highest. Due to the lack of quantitative methods to assess this complex photochemistry, the holistic effect of a single project’s emissions of O 3 precursors is speculative. That being said, because the Project would exceed the MDAQMD VOC and NO x thresholds during Project operations, the Project could contribute to health effects associated with O3.

Health effects associated with NOx and NO2 include lung irritation and enhanced allergic responses (CARB 2019b).

Although Project-related NOx emissions would exceed the MDAQMD construction mass daily thresholds, because the MDAB is a designated attainment area for NO 2 (and NO 2 is a constituent of NO x) and the existing NO 2 concentrations in the area are well below the NAAQS and CAAQS standards, 1 it is not anticipated that the Project would cause an exceedance of the NAAQS and CAAQS for NO2 or result in potential health effects associated with NO2 and NO x. Nonetheless, because the Project would excee d the MDAQMD NO x threshold during Project operations, the Project could contribute to health effects associated with NOx and NO2.

Health effects associated with CO include chest pain in patients with heart disease, headache, light -headedness, and reduced mental alertness (CARB 2019 c). CO tends to be a localized impact associated with congested intersections. The potential for CO hotspots is discussed under the subsequent impact criterion below and determined to be less than significant. Thus, the Project’s CO emissions would not contribute to significant health effects associated with CO.

Health effects associated with PM10 include premature death and hospitalization, primarily for worsening of respiratory disease (CARB 2017). Operation of the Project would exceed the MDAQMD threshold for PM10. As such, the Project would potentially contribute to exceedances of the NAAQS and CAAQS for particulate matter and obstruct the MDAB from

1 Ambient concentrations of NO2 at the Victorville monitoring station have not exceeded the NAAQS or CAAQS between 2016 and 2018.

Page 34 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
9 March 2022
coming into attainment for these pollutants. Because the Project has the potential to contribute substantial particulate matter during operation, the Project could result in associated health effects.

The California Supreme Court’s Sierra Club v. County of Fresno (2018) 6 Cal. 5th 502 decision (referred to herein as the Friant Ranch decision) (issued on December 24, 2018), addresses the need to correlate mass emission values for criteria air pollutants to specific health consequences, and contains the following direction from the California Supreme Court: “The Environmental Impact Report (EIR) must provide an adequate analysis to inform the public how its bare numbers translate to create potential adverse impacts or it must explain what the agency does know and why, given existing scientific constraints, it cannot translate potential health impacts further” (Italics original). Currently, MDAQMD, CARB, and EPA have not approved a quantitative method to reliably, meaningfully, and consistently translate the mass emissi on estimates for the criteria air pollutants resulting from the Project to specific health effects. In addition, there are numerous scientific and technological complexities associated with correlating criteria air pollutant emissions from an individual project to specific health effects or potential additional nonattainment days.

In connection with the judicial proceedings culminating in issuance of the Friant Ranch decision, the SCAQMD and the San Joaquin Valley Air Pollution Control District (SJVAPCD) filed amicus briefs attesting to the extreme difficulty of correlating an individual project’s criteria air pollutant emissions to specific health impacts. Both the SJVAPCD and the SCAQMD have among the most sophisticated air quality modeling and health impact evaluation capabilities of the air districts in the state. The key, relevant points from the SCAQMD and SJVAPCD briefs is summarized herein.

In requiring a health impact type of analysis for criteria air pollutants, it is important to understand how O3 and PM is formed, dispersed and regulated. The formation of O3 and PM in the atmosphere, as secondary pollutants,2 involves complex chemical and physical interactions of multiple pollutants from natural and anthropogenic sources. The O3 reaction is self-perpetuating (or catalytic) in the presence of sunlight because NO 2 is photochemically reformed from nitric oxide (NO). In this way, O 3 is controlled by both NO x and VOC emissions (NRC 2005). The complexity of these interacting cycles of pollutants means that incremental decreases in one emission may not result in proportional decreases in O3 (NRC 2005). Although these reactions and interactions are well understood, variability in emission source operations and meteorology creates uncertainty in the modele d O 3 concentrations to which downwind populations may be exposed (NRC 2005). Once formed, O3 can be transported long distances by wind and due to atmospheric transport, contributions of precursors from the surrounding region can also be important (EPA 2008).

Because of the complexity of O3 formation, a specific tonnage amount of VOCs or NOX emitted in a particular area does not equate to a particular concentration of O 3 in that area (SJVAPCD 2015). PM can be divided into two categories: directly emitted PM and secondary PM. Secondary PM, like O3, is formed via complex chemical reactions in the atmosphere between precursor chemicals such as SOx and NOx (SJVAPCD 2015). Because of the complexity of secondary PM formation, including the potential to be transport ed long distances by wind, the tonnage of PM - forming precursor emissions in an area does not necessarily result in an equivalent concentration of secondary PM in that area (SJVAPCD 2015). This is especially true for individual projects, like the Project, where Project-generated criteria air pollutant emissions are not derived from a single "point source," but from construction equipment and mobile sources (passenger cars and trucks) driving to, from and around the Project site.

Another important technical nuance is that health effects from air pollutants are related to the concentration of the air pollutant that an individual is exposed to, not necessarily the individual mass quantity of emissions associated with an individual project. For example, health effects from O3 are correlated with increases in the ambient level of O3 in the air a person breathes (SCAQMD 2015). However, it takes a large amount of additional precursor emissions to cause a modeled increase in ambient O3 levels over an entire region (SCAQMD 2015). The lack of link between

2 Air pollutants formed through chemical reactions in the atmosphere are referred to as secondary pollutants.

Page 35 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
10 March 2022
the tonnage of precursor pollutants and the concentration of O 3 and PM2.5 formed is important because it is not necessarily the tonnage of precursor pollutants that causes human health effects; rather, it is the concentration of resulting O 3 that causes these effects (SJVAPCD 2015). Indeed, the ambient air quality standards, which are statutorily required to be set by EPA at levels that are requisite to protect the public health, are established as concentrations of O3 and PM2.5 and not as tonnages of their precursor pollutants (EPA 2018b). Because the ambient air quality standards are focused on achieving a particular concentration region -wide, the tools and plans for attaining the ambient air quality standards are regional in nature. For CEQA analyses, project-generated emissions are typically estimated in pounds per day or tons per year and compared to mass daily or annual emission thresholds. While CEQA thresholds are established at levels that the air basin can accommodate without affecting the attainment date for the AAQS, even if a project exceeds established CEQA significance thresholds, this does not mean that one can easily determine the concentration of O3 or PM that will be created at or near the project site on a particular day or month of the year, or what specific health impacts will occur (SJVAPCD 2015).

In regard to regional concentrations and air basin attainment, the SJVAPCD emphasized that attempting to identify a change in background pollutant concentrations that can be attributed to a single project, even one as large as the entire Friant Ranch Specific Plan, is a theoretical exercise. The SJVAPCD brief noted that it “would be extremely difficult to model the impact on NAAQS attainment that the emissions from the Friant Ranch project may have” (SJVAPCD 2015). The situation is further complicated by the fact that background concentrations of regional pollutants are not uniform either temporally or geographically throughout an air basin, but are constantly fluctuating based upon meteorology and other environmental factors. SJVAPCD noted that the currently available modeling tools are equipped to model the impact of all emission sources in the San Joaquin Valley Air Basin on attainment (SJVAPCD 2015). The SJVAPCD brief then indicated that, “Running the photochemical grid model used for predicting O3 attainment with the emissions solely from the Friant Ranch project (which equate to less than one-tenth of one percent of the total NOx and VOC in the Valley) is not likely to yield valid information given the relative scale involved” (SJVAPCD 2015).

SCAQMD and SJVAPCD have indicated that it is not feasible to quantify project -level health impacts based on existing modeling (SCAQMD 2015; SJVAPCD 2015). Even if a m etric could be calculated, it would not be reliable because the models are equipped to model the impact of all emission sources in an air basin on attainment and would likely not yield valid information or a measurable increase in O 3 concentrations sufficient to accurately quantify O3-related health impacts for an individual project.

Nonetheless, following the Supreme Court’s Friant Ranch decision, some EIRs where estimated criteria air pollutant emissions exceeded applicable air district thresholds have included a quantitative analysis of potential project-generated health effects using a combination of a regional photochemical grid model (PGM)3 and the EPA Benefits Mapping and Analysis Program (BenMAP or BenMAP–Community Edition [CE]).4 The publicly available health impact assessments (HIAs) typically present results in terms of an increase in health incidences and/or the increase in background health

3 The first step in the publicly available HIAs includes running a regional PGM, such as the Community Multiscale Air Quality (CMAQ) model or the Comprehensive Air Quality Model with extensions (CAMx) to estimate the increase in concentrations of O3 and PM2.5 as a result of project-generated emissions of criteria and precursor pollutants. Air districts use photochemical air quality models for regional air quality planning. These photochemical models are large -scale air quality models that simulate the changes of pollutant concentrations in the atmosph ere using a set of mathematical equations characterizing the chemical and physical processes in the atmosphere (EPA 2017).
4 After estimating the increase in concentrations of O3 and PM2.5, the second step in the five examples includes use of BenMAP or BenMAP-CE to estimate the resulting associated health effects. BenMAP estimates the number of health incidences resulting from changes in air pollution concentrations (EPA 2018a). The health impact function in BenMAP-CE incorporates four key sources of data: (i) modeled or monitored air quality changes, (ii) population, (iii) baseline incidence rates, and (iv) an effect estimate. A ll of the five example HIAs focused on O3 and PM2.5.

Page 36 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
11 March 2022
incidence for various health outcomes resulting from the project’s estimated increase in concentrations of O3 and PM2.5.5 To date, the five publicly available HIAs reviewed have concluded that the evaluated project’s health effects associated with the estimated project-generated increase in concentrations of O3 and PM2.5 represent a small increase in incidences and a very small percentage of the number of background incidences, indicating that these health impacts are negligible and potentially within the models’ margin of error. It is also important to note that while the results of the five available HIAs conclude that the project emissions do not result in a substantial increase in health incidences, the estimated emissions and assumed toxicity is also conservatively inputted into the HIA and thus, overestimate health incidences, particularly for PM2.5.

As explained in the SJVAPCD brief and noted previously, running the PGM used for predicting O3 attainment with the emissions solely from an individual project like the Friant Ranch project or the Project is not likely to yield valid information given the relative scale involved. The five examples reviewed support the SJVAPCD’s brief contention that consistent, reliable, and meaningful results may not be provided by methods applied at this time. Accordingly, additional work in the industry and more importantly, air district participation, is needed to develop a more meaningful analysis to correlate project- level mass criteria air pollutant emissions and health effects for decision makers and the public. Furthermore, at the time of writing, no HIA has concluded that health effects estimated using the PGM and BenMAP approach are substantial provided that the estimated project-generated incidences represent a very small percentage of the number of background incidences, potentially within the models’ margin of error.

In summary, operation of the Project could result in exceedances of the MDAQMD significance thresholds for VOC, NOx, and PM10, and the Project would potentially result in health effects associated with those pollutants. Because construction of the Project would not exceed any MDAQMD thresholds (after mitigation), and operation of the Project would not exceed the MDAQMD thresholds for CO, SOx or PM2.5, and because the MDAQMD thresholds are based on levels that the MDAB can accommodate without affecting the attainment date for the AAQS and the AAQS are established to protect public health and welfare, the Project is not anticipated to result in health effects associated with CO, SOx or PM2.5.

Notably, there are numerous scientific and techn ological complexities associated with correlating criteria air pollutant emissions from an individual project to specific health effects or potential additional nonattainment days, and methods available to quantitatively evaluate health effects may not be appropriate to apply to emissions associated with the Project, which cannot be estimated with a high -level of accuracy. Notwithstanding, because operation of the Project could result in exceedances of MDAQMD significance thresholds for VOC, NO x, and PM10, even after implementation of MM -AQ-4 through MM-AQ-6, the potential health effects associated with criteria air pollutants are conservatively considered significant and unavoidable.

Expose Sensitive Receptors to Substantial Pollutant Concentrations Criteria Air Pollutant Emissions and Associated Pollutant Concentrations As discussed above, because operation of the Project could result in exceedances of the MDAQMD significance thresholds for VOC, NO x, and PM 10, the Project would potentially result in health effects associated with those pollutants. Because construction of the Project would not exceed any MDAQMD thresholds (after implementation of MM-AQ-4 through MM-AQ-6), and operation of the Project would not exceed the MDAQMD thresholds for CO, SOx

5 The following CEQA documents included a quantitative HIA to address Friant Ranch: (1) California State University Dominguez Hills 2018 Campus Master Plan EIR (CSUDH 2019), (2) March Joint Powers Association K4 Warehouse and Cactus Channel Improvements EIR (March JPA 2019), (3) Mineta San Jose Airport Amendment to the Airport Mas ter Plan EIR (City of San Jose 2019), (4) City of Inglewood Basketball and Entertainment Center Project EIR (City of Inglewood 2019), and (5) San Diego Stat e University Mission Valley Campus Master Plan EIR (SDSU 2019).

Page 37 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
12 March 2022
or PM 2.5, and because the MDAQMD thresholds are based on levels that the MDAB can accommodate without affecting the attainment date for the AAQS and the AAQS are established to protect public health and welfare, the Project is not anticipated to result in health effects associated with CO, SOx or PM2.5.

Notably, there are numerous scientific and technological complexities associated with correlating criteria air pollutant emissions from an individual project to specific health effects or potential additional nonattainment days, and methods available to quantitatively evaluate health effects may not be appropriate to apply to emissions associated with the Project, which cannot be estimated with a high -level of accuracy. Notwithstanding, because operation of the Project could result in exceedances of MDAQMD significance thresholds for VOC, NO x, and PM10, even after implementation of MM -AQ-4 through MM-AQ-6, the potential health effects associated with criteria air pollutants are conservatively considered significant and unavoidable.

Cumulative Air Quality Impact
Air pollution is largely a cumulative impact. The nonattainment status of regional pollutants is a result of past and present development, and the MDAQMD develops and implements plans for future attainment of ambient air quality standards. Based on these considerations, project-level thresholds of significance for criteria pollutants are relevant in the determination of whether a project’s individual emissions would have a cumulatively significant impact on air quality. Individual projects that do not generate operational or construction emissions that exceed the MDAQMD’s recommended daily thresholds for project -specific impacts would also not cause a cumulatively considerable increase in emissions for those pollutants for which the MDAB is in nonattainment, and, therefore, would not be considered to have a significant, adverse air quality impact.

The area of the MDAB in which the Project is located is a nonattainment area for O 3 and PM10 under the NAAQS and/or CAAQS. The poor air quality in the MDAB is the result of cumulative emissions from motor vehicles, off-road equipment, commercial and industrial facilities, and other emission sources. Projects that emit these pollutants or their precursors (i .e., VOC and NO x for O 3) potentially contribute to poor air quality. Daily construction emissions associated with the Project would not exceed the MDAQMD significance thresholds after implementation of mitigation of MM-AQ-1. However, as presented in the pr eceding analysis, Project operational-source air pollutant emissions would result in exceedances of regional thresholds for emissions of VOC, NO X, and PM10. As previously stated, the majority of VOC emissions are derived from consumer products, the use of which the Project Applicant cannot meaningfully control for future building users via mitigation. On this basis, it is concluded that Project operational-source VOC emissions cannot be definitively reduced below applicable MDAQMD thresholds.

Additionally, it should be noted that the majority of the Project’s NOX and PM10 emissions are derived from vehicle usage. Although MM -AQ-4 through MM -AQ-6 would reduce operational emissions from on -road vehicles to the extent feasible, since neither the Project Applic ant nor the City of Hesperia have regulatory authority to control tailpipe emissions, no feasible MMs exist that would reduce these emissions to levels that are less-than-significant.

As such, Project operational-source VOC, NO X, and PM 10 emissions exceedances of applicable MDAQMD regional thresholds would be significant and unavoidable, and thus, cumulatively considerable.

2.2.1.2 Mitigation Measures
MM-AQ-1 The Project shall utilize “Super-Compliant” low VOC paints which have been reformulated to exceed the regulatory VOC limits put forth by MDAQMD’s Rule 1113. Super-Compliant low VOC paints shall be no more than 10 grams per liter (g/L) of VOC. Alternatively, the Project Applicant may utilize tilt- up concrete buildings that do not require the use of architectural coatings.

Page 38 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
13 March 2022
MM-AQ-2 The Project shall implement the following measures in order to reduce construction air pollutant emissions to the extent feasible:
• Ensure the cleanest possible construction practices and equipment are used. This includes eliminating the idling of diesel-powered equipment and providing the necessary infrastructure (e.g., electrical hookups) to support zero and near-zero emission equipment and tools. • Implement, and plan accordingly for, the necessary infrastructure to support the zero and near- zero emission technology, vehicles, and equipment that will be operating onsite during construction. Necessary infrastructure may include the physical (e.g. needed footprint), energy, and fueling infrastructure for construction equipment, onsi te vehicles and equipment, and medium-heavy and heavy-heavy duty trucks.

MM-AQ-3 The Project shall include the following language within construction contracts in order to reduce construction air pollutant emissions to the extent feasible:
• All off-road diesel-powered equipment used during construction shall be equipped with Tier 4 or cleaner engines. If the operator lacks Tier 4 equipment, and it is not available for lease or short-term rental within 50 miles of the project site, Tier 3 or cleaner off -road construction equipment may be utilized subject to City approval.
• Heavy-duty trucks entering the construction site during grading and building construction phases should be model year 2014 or later. All heavy -duty trucks should also meet CARB’s lowest optional low oxides of nitrogen (NOx) standard starting in the year 2022.6 • All construction equipment and fleets shall be in compliance with all current air quality regulations.

MM-AQ-4 The Project shall implement the following measures in order to reduce operational air pollutant emissions to the extent feasible:
• Only haul trucks meeting model year 2010 engine emission standards shall be used for the on-road transport of materials to and from the Project site. • Legible, durable, weather-proof signs shall be placed at truck access gates, loading docks, and truck parking areas that identify applicable California Air Resources Board (CARB) anti -idling regulations. At a minimum, each sign shall include: 1) instructions for truck drivers to shut off engines when not in use; 2) instructions for drivers of diesel trucks to restrict idling to no more than 5 minutes once the vehicle is stopped, the transmission is set to "neutral" or "park," and the parking brake is engaged; and 3) telephone numbers of the building facilities manager and the CARB to report violations. Prior to the issuance of an occupancy permit, the City of Hesperia shall conduct a site inspection to ensure that the signs are in place. • Prior to tenant occupancy, the Project Applicant or success or in interest shall provide documentation to the City of Hesperia demonstrating that occupants/tenants of the Project site have been provided documentation on funding opportunities, such as the Carl Moyer Program, that provide incentives for using cleaner-than-required engines and equipment.

6 In 2013, CARB adopted optional lo w-NOx emission standards for on -road heavy -duty engines. CARB encourages engine manufacturers to introduce technologies to reduce NOx emissions below the current mandatory on-road heavy-duty diesel engine emission standards for model year 2010 and later. C ARB’s optional low -NOx emission standard is available at:
https://ww2.arb.ca.gov/our-work/programs/optional-reduced-nox-standards.

Page 39 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
14 March 2022
• Automobile electric vehicle (EV) charging stations with Level 2 or faster chargers shall be provided. The number of EV charging stations shall equal at least 25% employee parking spots. • In addition, the buildings shall include electrical infrastructure sufficiently sized to accommodate the potential installation of additional auto and truck EV charging stations in the future. • Conduit shall be installed to tractor trailer parking areas in logical locations determined by the Project Applicant during construction document plan check, for the purpose of accommodating the future installation of EV truck charging stations at such time this technology becomes commercially available.
• The Project shall include rooftop solar panels for each proposed warehouse to the extent feasible, with a capacity that matches the maximum allowed for distributed solar connections to the grid.

The Project Applicant or successor in interest shall maintain, replace, and upgrade the solar panels per manufacturers recommendations through the life of the Project. Should the capacity for solar connections increase, additional solar panels shall be added to the Project.

MM-AQ-5 The Project shall include the following language within tenant lease agreements in order to reduce operational air pollutant emissions to the extent feasible:
• Require tenants to use the cleanest technologies available, and to provide the necessary infrastructure to support zero -emission vehicles, equipment, and appliances that would be operating on site. This requirement shall apply to equipment such as forklifts, handheld landscaping equipment, yard trucks, office appliances, etc. • Require future tenants to exclusively use zero-emission light and medium-duty delivery trucks and vans, when economically feasible.
• Tenants shall be in, and monitor compliance with, all current air quality regulations for on-road trucks including CARB’s Heavy -Duty (Tractor -Trailer) Greenhouse Gas Regulation 7, Periodic Smoke Inspection Program (PSIP)8, and the Statewide Truck and Bus Regulation9. • Cold storage operations shall be prohibited unless additional environmental review, including a Health Risk Assessment, is conducted and certified pursuant to the California Environmental Quality Act.

MM-AQ-6 Low-VOC/Green Cleaning Product Educational Program. Prior to the occupancy of any on -site development, the Applicant or its designee shall provide evidence to the City of Hesperia that the Applicant/phase developer has developed a Green Cleaning Product and Paint education program to be made available at rental offices, leasing spaces, and/or on websites.

7 In December 2008, CARB adopted a regulation to reduce greenhouse gas emissions by improving the fuel efficiency of heavy- duty tractors that pull 53-foot or longer box-type trailers. The regulation applies primarily to owners of 53-foot or longer box-type trailers, including both dry-van and refrigerated-van trailers, and owners of the heavy-duty tractors that pull them on California highways. CARB’s Heavy-Duty (Tractor-Trailer) Greenhouse Gas Regulation is available at: https://www.arb.ca.gov/ cc/hdghg/hdghg.htm.
8 The PSIP program requires that diesel and bus fleet owners conduct annual smoke opacity inspections of their vehicles and repair those with excessive smoke emissions to ensure compliance. CARB’s PSIP program is available at:
https://www.arb.ca.gov/enf/hdvip/hdvip.htm.
9 The regulation requires that newer heavier trucks and buses must meet particulate matter filter requirements beginning January 1, 2012. Lighter and older heavier trucks must be replaced starting January 1, 2015. By January 1, 2023, nearly all trucks and buses will need to have 2010 model year engines or equivalent. CARB’s Statewide Truck and Bus Regu lation is available at:
https://www.arb.ca.gov/msprog/onrdiesel/onrdiesel.htm.

Page 40 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
15 March 2022

2.2.1.3 Findings per CEQA Guidelines
The City finds that the above mitigation measures are feasible, are adopted, and will reduce the proposed project’s air quality impact. Construction emissions would be reduced to below the MDAQMD’s regional thresholds with implementation of MM-AQ-1. However, Project operational -source air pollut ant emissions would result in exceedances of regional thresholds for emissions of VOC, NO x, and PM10, even after implementation of MM -AQ-4 through MM-AQ-6. As such, VOC, NOx, and PM10 emissions are considered significant and unavoidable. In addition, the project would result in cumulatively considerable impacts related to the potential to conflict with the MDAQMD’s thresholds, result in a cumulatively considerable net increase of criteria pollutants ( VOC, NO x, and PM 10), and expose sensitive receptors to substantial pollutant concentrations (VOC, NOx, and PM10). Additionally, it should be noted that the majority of the Project’s NOX and PM10 emissions are derived from vehicle usage. Although MM-AQ- 4 through MM-AQ-6 would reduce operational emissions from on-road vehicles to the extent feasible, since neither the Project Applicant nor the City of Hesperia have regulatory authority to control tailpipe emissions, no feasible MMs exist that would reduce these emissions to levels that are less-than-significant. As such, Project operational- source VOC, NOX, and PM10 emissions exceedances of applicable MDAQMD regional thresholds would be significant and unavoidable, and thus, cumulatively considerable.

Pursuant to Section 21081(a)(3) of the Californ ia Public Resources Code, as described in the Statement of Overriding Considerations, the City has determined that specific economic, legal, social, technological, or other considerations make infeasible the alternatives identified in the EIR, and the iden tified air quality impacts are thereby acceptable because of specific overriding considerations (see Section 5).

2.2.1.4 Facts in Support of the Findings Related to Air Quality Based on the impact analysis, the proposed project would result in significant operational VOC, NO x, and PM 10 emission impacts. Implementation of MM-AQ-1 through MM-AQ-6 would reduce potential impacts from criteria air pollutants and project emissions. However, due to the size and type of the project, it is not feasible to implement mitigation measures to reduce the operational mobile source emissions. Various mitigation measures were considered, including land use strategies such as proximity to transi t station; however, these strategies and MM- AQ-4 through MM-AQ-6 cannot be quantified due to the uncertainty. Thus, the project’s impacts related to potential to conflict with or obstruct implementation of the MDAQMD’s regional thresholds and the project operational VOC, NOx, and PM10 emissions would remain significant. In addition, the project would result in cumulatively considerable impacts related to the potential to conflict with the MDAQMD regional thresholds , result in a cumulatively considerable net increase of criteria pollutants (VOC, NOx, and PM10), and expose sensitive receptors to substantial pollutant concentrations (VOC, NOx, and PM10).

2.2.2 Greenhouse Gas Emissions

2.2.2.1 Potentially Significant Impacts to Greenhouse Gas Emissions Generation of Greenhouse Gas Emissions
For construction phase Project emissions, GHGs are quantified and amortized over the life of the Project. MDAQMD follows the SCAQMD recommendation in calculating the total GHG emissions for construction activities by amortizing the emissions over the life of the Project by dividing it by a 30-year Project life then adding that number

Page 41 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
16 March 2022
to the annual operational phase GHG emissions. As such, construction emissions were amortized over a 30 -year period and added to the annual operational phase GHG emissions.

Total estimated GHG emissions generated during construction of the Project is approximately 3,885 MT CO2e. Estimated Project-generated construction emissions amortized over 30 years would be approximately 130 MT CO2e per year.

Long-term operations of the Project would result in GHG emissions through mobile sources and on-site equipment, area sources (landscape maintenance equipment); energy use (natural gas and generation of electricity consumed by the Project); generation of electricity associated with wastewater treatment and with water supply, treatment, and distribution; and solid waste disposal. Annual GHG emissions from these sources were estimated using CalEEMod.

To effectively analyze operational GHG emissions as sociated with the Project, two scenarios were modeled. The first scenario represents Project emissions under a without regulatory measures and PDFs (shown as “unmitigated” emissions in CalEEMod), which estimates Project emissions absent federal, state, and local measures and without Project features intended to reduce GHG emissions upon Project buildout. The second scenario (shown as “mitigated” emissions in CalEEMod) represents Project emissions with implementation of applicable federal, state, and local GHG reduction measures and Project features. Without accounting for applicable regulatory requirements and PDFs, the Project would result in approximately 63,906 MT CO2e per year.

The Project would be required to comply with all mandates imposed by the State of California and the MDAQMD. Those measures that are applicable to the Project and that would assist in the reduction of GHG emissions are as follows:
• Global Warming Solutions Act of 2006 (AB 32).
• Regional GHG Emissions Reduction Targets/Sustainable Communities Strategies (SB 375). • Pavley Fuel Efficiency Standards (AB 1493). Establishes fuel efficiency ratings for new vehicles. • Title 24 California Code of Regulations (California Building Code). Establishes energy efficiency requirements for new construction.
• Title 20 California Code of Regulations (Appliance Energy Efficiency Standards). Establishes energy efficiency requirements for appliances.
• Title 17 California Code of Regulations (Low Carbon Fuel Standard). Requires carbon content of fuel sold in California to be 10% less by 2020.
• California Water Conservation in Landscaping Act of 2006 (AB 1881). Requires local agencies to adopt the Department of Water Resources updated Water Efficient Landscape Ordinance or equivalent by January 1, 2010 to ensure efficient landscapes in new development and reduced water waste in existing landscapes. • Statewide Retail Provider Emissions Performance Standards (SB 1368). Requires energy generators to achieve performance standards for GHG emissions.
• Renewable Portfolio Standards (SB 1078). Requires electric corporations to increase the amount of energy obtained from eligible renewable energy resources to 20 % by 2010 and 33% by 2020. • SB 32. Requires the state to reduce statewide GHG emissions to 40% below 1990 level s by 2030, a reduction target that was first introduced in Executive Order B-30-15.

In addition to the above regulatory measures, the Project would implement PDFs and attributes promoting energy efficiency and sustainability, which are found below in Section 2.2.2.2, Project Design Features.

Page 42 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
17 March 2022
With applicable regulatory requirements and PDFs, the Project would result in approximately 55,599 MT CO2e per year, which would exceed the SCAQMD GHG threshold of 3,000 MT CO2e per year. Therefore, the Project would generate GHG emissions, either directly or indirectly, that may have a significant impact on the environment, and this would represent a cumulatively potentially significant impact. Mitigation measures would be required that would reduce Project-generated construction and operational GHG emissions. As presented in Section 2.2.1, Air Quality, implementation of mitigation measures MM -AQ-2 and MM -AQ-3 would also reduce construction -related GHG emissions and mitigation measures MM -AQ-4 and MM -AQ-5 would also re duce operation -related GHG emissions. In addition, mitigation measures MM -GHG-1, requiring water conservation measures. and MM -GHG-2, implementing solid waste reduction strategies, would be implemented to reduce GHG emissions generated during operation of the Project. However, the effectiveness of the required mitigation measures cannot be accurately quantified at this time. Therefore, Project -generated GHG emissions would still exceed the applied threshold of 3,000 MT CO2e per year and impact would be significant and unavoidable.

Cumulative GHG Impacts
GHG emissions impacts are inherently cumulative in nature. The Project would result in GHG emissions in exceedance of the SCAQMD significance threshold. The Project would result in potentially significant impacts with regard to GHG emissions Implementation of MM -AQ-2 through MM -AQ-5 and MM -GHG-1 and MM -GHG-2 would reduce the Project’s GHG impacts; however, impacts would remain significant and unavoidable.

2.2.2.2 Project Design Features
Energy-saving and sust ainable design features and operational programs would be incorporated into facilities developed pursuant to the currently Project. The Project also incorporates and expresses the following project design features (PDFs) and attributes promoting energy eff iciency and sustainability. Because these features/attributes are integral to the Project, and/or are regulatory requirements, they are not considered to be mitigation measures.
• The Project will design building shells and building components, such as windows; roof systems: electrical and lighting systems: and heating, ventilating, and air conditioning systems to meet 2019 Title 24 Standards which expects 30% less energy for non-residential buildings. • To reduce water demands and associated energy use, subseq uent development proposals within the Project site would be required to implement a Water Conservation Strategy and demonstrate a minimum 20% reduction in indoor and outdoor water usage when compared to baseline water demand (total expected water demand without implementation of the Water Conservation Strategy).10 • In order to reduce the amount of waste disposed at landfills, the Project would implement a 75% waste diversion.

2.2.2.3 Mitigation Measures
MM-GHG-1 Water Conservation. Prior to the issuance of building permits for the Project, the Project applicant shall provide building plans that include the following water conservation measures:
• Install low-water use appliances and fixtures

10 Reduction of 20% indoor and outdoor water usage is consistent with the current CALGreen Code performance standards for residential and non-residential land uses. Per CALGreen, the reduction shall be based on the maximum allowable water use per plumbing fixture and fittings as required by the California Building Standards Code.

Page 43 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
18 March 2022
• Restrict the use of water for cleaning outd oor surfaces and prohibit systems that apply water to non-vegetated surfaces
• Implement water-sensitive urban design practices in new construction • Install rainwater collection systems where feasible.

MM-GHG-2 Solid Waste Reduction. Prior to the issuance of building permits for the Project, the Project applicant shall provide building plans that include the following solid waste reduction measures:
• Provide storage areas for recyclables and green waste in new construction, and food waste storage, if a pick-up service is available.
• Evaluate the potential for onsite composting.

2.2.2.4 Findings Per CEQA Guidelines
The City finds that the above mitigation measures are feasible, are adopted, and will reduce the proposed project’s greenhouse gas emissions impact. The Project would result in GHG emissions in exceedance of the SCAQMD significance threshold even with implementation of MM -AQ-2 through MM -AQ-5 and MM -GHG-1 and MM -GHG-2.

However, the effectiveness of the required mitigation measures cannot be accurately quantified at this time.

Therefore, these impacts must be considered significant and unavoidable even after implementation of all feasible mitigation measures. Pursuant to Section 21081(a)(3) of the California Public Resources Code, as described in the Statement of Overriding Considerations, the City has determined that specific economic, legal, social, technological, or other considerations make infeasible the alternatives identified in the EIR, and the identified greenhouse gas emission impacts are thereby acceptable because of specific overriding considerations (see Section 5).

2.2.2.5 Facts in Support of the Findings Related to Greenhouse Gas Emissions Based on the impact analysis, the proposed project would result in significant greenhouse gas emission impacts.

Implementation of MM-AQ-2 through MM-AQ-5 and MM-GHG-1 and MM-GHG-2 would reduce potential impacts from greenhouse gas emissions. However, the effectiveness of the required mitigation measures cannot be accurately quantified at this time, therefore, greenhouse gas emission project impacts would remain significant and unavoidable.

2.2.3 Noise

2.2.3.1 Potentially Significant Impacts to Noise
Increase in Ambient Noise Levels
Long-Term Operational Noise
Off-Site Operational Traffic Noise
The Project would generate traffic along roadways in the community surrounding the Project site. Many of the roadways evaluated in the Traffic Impact Analysis serve commercial and industrial areas, which are not considered noise-sensitive in relation to noise from roadway traffic. However, a total of 12 roadway segments evaluated in the TIA are aligned along existing noise -sensitive (i.e., residential) areas. Potential noise effects from vehicular traffic

Page 44 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
19 March 2022
were assessed using the Federal Highway Administrati on’s Traffic Noise Model version 2.5 (FHWA 2004).

Information used in the model included the site geometry, existing, existing plus Project, future without Project, and future with Project traffic volumes (provided in the Transportation Impact Analysis) and posted traffic speeds. Noise levels were modeled at a uniform distance from the roadway center-line along roadway segments with residences exiting along the right-of-way.

The City does not have a specific criterion for evaluating the significance of Pro ject-related increases in off -site traffic noise levels at residences or noise -sensitive areas. For the purposes of this analysis, traffic noise level increases are considered significant if they exceed ambient traffic noise levels by one dB or more, or ca use noise levels to exceed the 65 dBA CNEL noise threshold. An increase or decrease in noise level of three dBA is the minimum before any noticeable change in community response would be expected (Caltrans 1998).

The maximum noise level increase would below one (1) dB, and therefore insignificant, at every studied road segment except Main Street. Along Main Street, the Project would result in a maximum increase of 2.3 dB and 2 dB at the Mesa Linda Street and Cataba Road segments, respectively. While overall exterior noise exposure would remain within the City’s maximum exterior limits, the increase in traffic noise would be noticeable to residents along these segments.

To reduce the potentially significant Project traffic noise level increases on the tw o study area roadway segments for Existing plus Project, Opening Year Cumulative and Horizon Year Project conditions, potential noise mitigation measures were considered in the Noise Impact Analysis. Potential mitigation measures discussed in the report included rubberized asphalt hot mix pavement and off-site noise barriers for the existing non-conforming residential use adjacent to impacted roadway segments. However, while rubberized asphalt would provide some noise reduction, this mitigation is only effective for tire-on-pavement noise at higher speeds and would not reduce truck- related off-site traffic noise levels associated with truck engine and exhaust stacks.

The Noise Impact Analysis found that for off-site noise barriers at receiving noise-sensitive land uses experiencing Project-related traffic noise level increases would need to be high enough and long enough to block the line-of-sight from the noise source (at 11.5 feet high per Caltrans) to the receiver (at 5 feet high per FHWA guidance) in order to provide a 5 dBA reduction per FHWA guidance. Exterior noise mitigation in the form of noise barriers is not anticipated to provide the FHWA attainable reduction of 5 dBA required to reduce the off -site traffic noise level increases and would also require potential openings for driveway access to individual residential lots fronting the road. As such, off-site noise barriers would not be feasible and would not lower the off-site traffic noise levels below a level of significance.

In addition, implementation of both rubberized asphalt hot mix pavement and off-site noise barriers would need to occur within the public right-of-way and private property, respectively. Thus, the ability for the Project applicant to incorporate these measures could not be guaranteed, as there is no assurances that the respective property owners (e.g., the City and private residential property owners) would allow for these improvements on their respective properties. As such, there are no assurances that these measures could be adequately implemented.

Based on the infeasibility of potential mitigation to adequately reduce off -site Project traffic noise levels to less - than-significant levels, off -site Project -related traffic noise level increases at adjacent land uses would remai n significant. Therefore, long-term operational impacts associated with Project-related traffic noise increases would be significant and unavoidable.

Page 45 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
20 March 2022
Cumulative Noise Impacts
The cumulative context for traffic noise is the traffic volume increases on roadw ays within Hesperia as a result of buildout of the City’s 2010 General Plan and the anticipated increase in traffic volumes along these roadways. The Project traffic analysis considered the addition of traffic trips from cumulative projects as identified by the City.

Non-transportation noise sources (e.g., Project operation) and construction noise impacts are typically project - specific and highly localized (i.e., these do not generally affect the community noise level at distances beyond several hundred feet). Construction activities associated with proposed or future development within the area would contribute to cumulative noise levels, but in a geographically limited and temporary manner. As other development occurs in the area, noise from different types of uses (e.g., traffic, aircraft, and fixed noise sources) would continue to combine, albeit on a localized basis, to cause increases in overall background noise conditions within the area.

As a result, such sources do not significantly contribute to cu mulative noise impacts at distant locations and are not evaluated on a cumulative level.

The analysis of off -site Project-related traffic noise levels included an evaluation of traffic volumes and resulting roadway traffic noise levels from cumulative projects. The maximum noise level increase for the cumulative versus cumulative plus Project scenario would be less than 1 dB at every studied road segment except Main Street. Along Main Street, the Project would result in a maximum increase of 2.3 dB and 2 dB at the Mesa Linda Street and Cataba Road segments, respectively. While overall exterior noise exposure would remain within the City’s maximum exterior limits, the increase in traffic noise would be clearly noticeable to residents along these two segments.

To reduce the potentially significant Project traffic noise level increases on the two study area roadway segments for Existing plus Project, Opening Year Cumulative and Horizon Year Project conditions, potential noise mitigation measures were considered in the Noise Impact Analysis. Potential mitigation measures discussed in the report included rubberized asphalt hot mix pavement and off-site noise barriers for the existing non-conforming residential use adjacent to impacted roadway segments. However, as further discussed in the Noise Impact Analysis, while rubberized asphalt would provide some noise reduction, this mitigation is only effective for tire-on-pavement noise at higher speeds and would not reduce truck -related off-site traffic noise levels ass ociated with truck engine and exhaust stacks.

The Noise Impact Analysis found that for off-site noise barriers at receiving noise-sensitive land uses experiencing Project-related traffic noise level increases would need to be high enough and long enough to block the line-of-sight from the noise source (at 11.5 feet high per Caltrans) to the receiver (at 5 feet high per FHWA guidance) in order to provide a 5 dBA reduction per FHWA guidance. Exterior noise mitigation in the form of noise barriers is not anticipated to provide the FHWA attainable reduction of 5 dBA required to reduce the off -site traffic noise level increases and would also require potential openings for driveway access to individual residential lots fronting the road. As such, off-site noise barriers would not be feasible and would not lower the off-site traffic noise levels below a level of significance.

In addition, implementation of the both rubberized asphalt hot mix pavement and off-site noise barriers would need to occur within the public right-of-way and private property, respectively. Thus, the ability for the Project applicant to incorporate these measures could not be guaranteed, as there is no assurances that the respective property owners (e.g., the City and private residential pro perty owners) would allow for these improvements on their respective properties. As such, there are no assurances that these measures could be adequately implemented.

Based on the infeasibility of potential mitigation to adequately reduce off -site Project traffic noise levels to less - than-significant levels, off -site Project -related traffic noise level increases at adjacent land uses would remain

Page 46 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
21 March 2022
significant. Therefore, long-term operational impacts associated with Project-related traffic noise increases would be significant and unavoidable, and the Project would have cumulatively considerable impact related to noise.

2.2.3.2 Findings Per CEQA Guidelines
The Project would result in less -than-significant on-site operational impacts; however, the Project wou ld result in potentially significant off-site operational traffic noise impacts along Main Street between U.S. Highway 395 and Cataba Road. Based on the infeasibility of potential mitigation to adequately reduce off -site Project traffic noise levels to less-than-significant levels, and because there are no assurances that noise-reducing measures could be adequately implemented, no reasonably feasible and implementable mitigation measures have been identified. As such, off -site operational traffic noise impa cts would remain significant and unavoidable. Pursuant to Section 21081(a)(3) of the California Public Resources Code, as described in the Statement of Overriding Considerations, the City has determined that specific economic, legal, social, technological, or other considerations make infeasible the alternatives identified in the EIR, and the identified noise impacts are thereby acceptable because of specific overriding considerations (see Section 5).

2.2.3.3 Facts in Support of the Findings Related to Noise Based on the impact analysis, the proposed project would result in significant off-site operational traffic noise impacts along Main Street between U.S. Highway 395 and Cataba Road. Based on the infeasibility of potential mitigation to adequately reduce off-site Project traffic noise levels to less-than-significant levels, and because there are no assurances that noise -reducing measures could be adequately implemented, no reasonably feasible and implementable mitigation measures have been identified. Thus, impacts related to the Project’s off-site operational traffic noise impacts would remain significant and unavoidable.

2.2.4 Transportation

2.2.4.1 Potentially Significant Impacts to Transportation Conflict with CEQA Guidelines Section 15064.3 (b)
CEQA Guidelines Section 15064.3(b) focuses on newly adopted criteria (VMT) adopted pursuant to SB 743 for determining the significance of transportation impacts. Pursuant to SB 743, the focus of transportation analysis changes from vehicle delay to VMT. Th e related updates to the CEQA Guidelines required under SB 743 were approved on December 28, 2018. As stated in CEQA Guidelines Section 15064.3(c), the provisions of Section 15064.3 shall apply statewide on July 1, 2020.

The City of Hesperia has yet to ad opt its own VMT analysis guidelines and thresholds. City staff have recommended the VMT threshold of better than existing regional VMT until the City of Hesperia adopts its own guidelines and thresholds.

For the purposes of this EIR, the recommended VMT an alysis methodology and thresholds identified within the OPR’s Technical Advisory and SBCTA February 2020 guidelines have been used.

The San Bernardino Transportation Analysis Model (SBTAM) is a useful tool to estimate VMT as it considers interaction betwe en different land uses based on socio -economic data such as population, households, and

Page 47 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
22 March 2022
employment. The SBCTA Guidelines identifies SBTAM as the appropriate tool for conducting VMT analysis for land use projects in San Bernardino County.

Project VMT has be en calculated using the most current version of SBTAM. Adjustments in socioeconomic data (SED) (i.e., employment) have been made to a traffic analysis zone (TAZ) within the SBTAM model to reflect the Project’s proposed land uses (i.e., warehouse). As menti oned previously, the SBTAM model includes a truck component. Therefore, Project truck trips and truck related VMT are included in the Project’s per -employee VMT, and the Project’s VMT is a conservative estimate.

The employment estimates for the Project are consistent with the employment density factors identified in SCAG’s Employment Density Study (SCAG 2001).

Adjustments to employment factors for the Project TAZ were made to both the SBTAM base year model (2012) and the cumulative year model (2040). Proje ct VMT was then calculated for both the base year model (2012) and cumulative year model (2040) and linear interpolation was used to determine the Project’s baseline (2020) VMT.

The VMT is then normalized by dividing by the Project’s service population (SP ) (e.g., employees). The Project baseline (2020) VMT per SP is 39.25.

SBCTA provides VMT calculations for each of its member agencies and for the County of San Bernardino region.

Urban Crossroads has obtained this data from SBCTA which identifies that the existing San Bernardino County VMT per SP for is 32.66.

The comparison between Project-generated VMT per SP to the baseline (2016) regional (San Bernardino County) VMT per SP, which was derived from the SBTAM base year model by SBCTA and their consulta nt. As shown, the Project would exceed the current threshold of the baseline County of San Bernardino VMT per SP. The Project VMT impact is therefore significant and unavoidable.

Design Hazards
Queuing Analysis
A queuing analysis was performed for U.S. Highway 395 from Luna Road to Joshua Street to assess vehicle queues along the roadways. There are no intersection turning movements that currently experience periodic queuing issues during the peak hours based on the 95th percentile peak hour traffic flows.

A queuing analysis was performed for the off -ramps at the I -15 and Main Street interchange to assess vehicle queues for the off ramps that may potentially result in deficient peak hour operations at the ramp -to-arterial intersections and may potentially “ spill back” onto the I -15 mainline. There are no off -ramp movements that are currently experiencing queuing issues during the weekday AM or weekday PM peak 95th percentile traffic flows.

Existing plus Project
The following intersection is anticipated to experience periodic queuing issues during the peak hours based on the 95th percentile peak hour traffic flows with the addition of Project traffic under Existing plus Project traffic conditions:
• U.S. Highway 395/Phelan Road/Main Street (#12) Southbound Left – AM and PM peak hours

Page 48 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
23 March 2022
There are no off -ramp movements that are anticipated to experience queuing issues during the weekday AM or weekday PM peak 95th percentile traffic flows.

Opening Day plus Project
The following intersection turning movements are anticipated to experience periodic queuing issues during the peak hours based on the 95th percentile peak hour traffic flows for Opening Year Cumulative (2021) Without Project traffic conditions:
• U.S. Highway 395/Phelan Road/Main Street (#12) Southbound Left – AM and PM peak hours • U.S. Highway 395/Three Flags Road (#14) Northbound Left – AM and PM peak hours The following additional intersection turning movement is anticipated to experience queuing issues during the peak hours based on the 95th percentile peak hour traffic flows with the addition of Project traffic for Opening Year Cumulative (2021) With Project traffic conditions:
• U.S. Highway 395 and Phelan Road/Main Street (#12) Northbound Left – AM and PM peak hours There are no off-ramp movements that are anticipated to experience queuing issues during the weekday AM or weekday PM peak 95th percentile traffic flows under Opening Year Cumulative (2021) With Project traffic conditions.

Horizon Year (2040) plus Project
The following intersection turning movements are anticipated to experience periodic queuing issues during the peak hours based on the 95th percentile peak hour traffic flows for Horizon Year (2040) Without Project traffic conditions:
• U.S. Highway 395/Bear Valley Road (#9) Northbound Left – AM and PM peak hours • U.S. Highway 395/Bear Valley Road (#9) Southbound Left – AM and PM peak hours • U.S. Highway 395/Phelan Road/Main Street (#12) Northbound Left – PM peak hour only • U.S. Highway 395/Phelan Road/Main Street (#12) Southbound Left – AM and PM peak hours • U.S. Highway 395/Poplar Street (#13) Southbound Left – AM and PM peak hours • U.S. Highway 395/Three Flags Road (#14) Northbound Left – AM and PM peak hours • U.S. Highway 395/Joshua Street (#15) Southbound Left – AM and PM peak hours There are no additional intersection turning movements that are anticipated to experience queuing issues during the peak hours based on the 95th percentile peak hour traffic flows for Horizon Year (2040) With Project traffic conditions, in addition to the movements identified under Horizon Year (2040) Without Project traffic conditions.

There are no off -ramp movements that are anticipated to experience queuing issues during the weekday AM or weekday PM peak 95th percentile traffic flows with the addition of Pr oject traffic under Horizon Year (2040) With Project traffic conditions.

Improvement measures required to mitigate Project’s impact would include fair-share contribution to Intersections #9, #12, #13, #14, and #15. Since the City does not have jurisdiction over some of these facilities, these improvements cannot be assumed to be in place prior to Project’s occupancy. Therefore, Project’s impact to increase in hazardous conditions (i.e. queuing) would be significant and unavoidable.

Page 49 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
24 March 2022
Cumulative Transportation Impacts
A TIA was prepared to evaluate the Project’s effects on the LOS on transportation facilities in the Project area. The Project’s cumulative contribution to traffic-related impacts has been analyzed under Opening Year and Horizon Year analyses within the TIA and summarized under Threshold A. Some of the study area intersections would not comport with Policy CI -2.1, 2.2 and 2.3 under General Plan Goal: CI -2 Develop and implement a City -wide Congestion Management Plan of the City’s General Plan, as th ey would operate or are forecast to operate at unsatisfactory (LOS E or F) conditions during either the AM or PM peak hours. However, LOS has been addressed herein for informational purposed only and can no longer be used to determine significant transportation impacts under CEQA and SB 743.

As discussed above, the Project would exceed the current threshold of the baseline County of San Bernardino VMT per SP, resulting in a Project -specific VMT impact that is therefore significant and unavoidable. OPR’s Tec hnical Advisory states the following, “a project that falls below an efficiency-based threshold that is aligned with long-term goals and relevant plans has no cumulative impact distinct from the project impact. Accordingly, a finding of a less- than-significant project impact would imply a less than significant cumulative impact and vice versa. Therefore, the Project’s finding related to cumulative VMT impacts is considered potentially significant. MM -TRA-1 would be implemented. However, the effectiveness of some of the TDM strategies that have potential to reduce the Project VMT are dependent on yet unknown Project building tenant(s); and as noted above, VMT reductions from TDM strategies cannot be guaranteed in most cases. Therefore, Project’s cumulative impact with respect to VMT would be significant and unavoidable.

In addition, the Project may increase a hazardous condition due to queuing impacts at the intersections #9, #12, #13, #14, and #15 under the Horizon Year (2040) plus Project analysis scenario. Since the City does not have jurisdiction over some of these facilities, these improvements cannot be assumed to be in place prior to Project’s occupancy. Therefore, Project’s impact to increase in hazardous conditions (i.e. queuing) would be significant and unavoidable, and thus, the Project could contribute to a cumulatively considerable impact associated with queuing and hazardous design features.

2.2.4.2 Mitigation Measures
MM-TRA-1 The Project applicant shall submit a Transportation Demand Management (TDM) plan prepared by a qualified transportation consultant acceptable to the City of Hesperia to reduce Project’s vehicle miles traveled. The TDM plan shall be approved by the City prior to the issuance of the first occupancy permit. The TDM plan shall apply to Project tenants through tenant leases. The TDM plan shall discourage single -occupancy vehicle trips and encourage alternative modes of transportation such as carpooling, taking transit, walking, and biking. Examples of trip reduction measures may include, but are not limited to:
• Transit passes
• Car-sharing programs
• Telecommuting and alternative work schedules
• Ride sharing programs

Page 50 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
25 March 2022

2.2.4.3 Findings per CEQA Guidelines
The City finds that the above mitigation measure is feasible, is adopted, and will reduce some of the proposed project transportation impacts attributable to trips generated by the proposed project. The Project would exceed the current threshold of the baseline County of San Bernardino VMT per SP, resulting in a Project -specific VMT impact that is therefore significant and unavoidable. MM-TRA-1 would be implemented. However, the effectiveness of some of the TDM strategies that have potential to reduce the Project VMT are dependent on yet unknown Project building tenant(s).

In addition, the Project may increase a hazardous condition due to queuing impacts at various intersections that the City does not have jurisdiction over, therefore, these improvements cannot be assumed to be in place prior to Project’s occupancy. Therefore, the Project’s impact to increase in hazardous conditions (i.e. queuing) would be significant and unavoidable. Pursuant to Section 21081(a)(3) of the California Public Resources Code, as described in the Statement of Overriding Considerations, the City has determined that specific economic, legal, social, technological, or other considerations make infeasible the alternatives identified in the EIR, and the identified transportation impacts are thereby acceptable because of specific overriding considerations (see Section 5).

2.2.4.4 Facts in Support of the Findings Related to Transportation The Project would exceed the current threshold of the baseline County of San Bernardino VMT per SP, resulting in a Project -specific VMT impact that is therefore significant and unavoidable. MM -TRA-1 would be implemented.

However, the effectiveness of some of the TDM strategies that have potential to reduce the Project VMT are dependent on yet unknown Project building tenant(s).

Some intersection impacts remain significant and unavoidable because they are outside the City’ s control to implement mitigation. The Project may increase a hazardous condition due to queuing impacts at the intersections #9, #12, #13, #14, and #15 under the Horizon Year (2040) plus Project analysis scenario. Since the City does not have jurisdiction over some of these facilities, these improvements cannot be assumed to be in place prior to Project’s occupancy.

Mitigation measures are proposed to reduce potential transportation impacts, however, since implementation of the roadway improvements cannot be guaranteed by project opening or project build -out, mitigation and improvements are rendered infeasible. The significance determinations are based on a conservative worst -case scenario whereby it is assumed that mitigation for all significant impacts outside the control of the City are infeasible and therefore, the impacts are significant and unavoidable.

2.3 Impacts Determined to Be Less Than Significant
with Mitigation
This section identifies significant adverse impacts of the project that require f indings to be made under CEQA Section 21081(a) and CEQA Guidelines Section 15091(a)(1). Based on substantial evidence, the City finds that adoption of the mitigation measures set forth in this section will reduce the identified significant impacts to less than significant levels:
• Aesthetics
o Scenic vistas

Page 51 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
26 March 2022
o Regulations governing scenic quality
o Cumulative aesthetics impacts
• Air Quality
o Cumulatively considerable net increase of criteria pollutants • Short-term construction impacts
• Biological Resources
o Candidate, sensitive, or special-status species
o Adverse impact on riparian habitat/sensitive natural communities o Adverse effect on wetlands
o Conflict with biological resources protection policies and ordinances o Cumulative biological impacts
• Cultural Resources
o Historic resources
o Archaeological resources
o Disturbance of human remains
o Cumulative cultural impacts
• Geology and Soils
o Unique paleontological resource or site or unique geologic feature • Hazards and Hazardous Materials
o Routine transport, use, or disposal of hazardous materials o Release of hazardous materials and the potential for upset conditions o Cumulative hazards impacts
• Tribal Cultural Resources
o Register of Historical Resources
o California Public Resource Code, Section 5024.1
o Cumulative tribal cultural impacts
Other impacts addressed under cumulatively considerable net increase of criteria pollutants are addressed in Section 2.2, Impacts Determined to be Significant and Unavoidable. In addition, other impacts not addressed under special-status wildlife species are addressed in Section 2.4.4.

2.3.1 Aesthetics

2.3.1.1 Potentially Significant Impacts to Aesthetics
Scenic Vistas
The Project would involve the construction of three industrial/warehouse buildings, surface parking and loading areas. Buildings 1 and 3 would be in the northern portion of the Project site, and Building 2 would be in the southern portion of the Project site and would front Phelan Road.

Page 52 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
27 March 2022
The Project site is located on relatively flat land within a wide, valley floor. The City of Hesperia General Plan identifies natural scenic open space as a valuable scenic resource that contributes to the visual landscape and states that these areas should be preserved. Open space areas within the City include the Mojave River to the east, the San Bernardino and San Gabriel Mountain ranges and the surrounding Victor Valley to the south, and the neighboring undeveloped hillsides and the natural desert environment. Additionally, several washes and natural water courses traverse the City, and are identified in the City’s General Plan as providing physical and visual relief from surrounding urban development (City of Hesperia 20 10a).The City protects wash areas through the Main Street and Freeway Corridor Specific Plan Wash Protection Overlay. The nearest protected wash area to the Project site is the Oro Grande Wash, which is located approximately 0.25 -mile to the east of the Pr oject site beyond U.S.

Highway 395.

Photographs of the Project site and surrounding area were taken from public vantage points to document the existing visual environment and to identify locations from which to assess the potential for Project impacts on scenic vistas. Key view locations were selected to depict existing views toward the Project site available from public vantage points, and KOPs 1 and 2 were selected to depict existing conditions and visual simulations of the Project.

Visual simulations pro vide 3 -dimensional photo -realistic before and after images of the Project. The key view locations and KOPs were selected based on the variety of viewer groups in the area and existing views to natural scenic resources. Motorists constitute the largest view er group in the Project area, and thus, views are depicted from public roadways. Other land uses in the Project area include rural residential uses and commercial/light industrial uses. These land uses are located in close proximity to the key view locatio ns and KOPs, and would be afforded similar views as presented in the photographs.

Existing views toward and across the immediate and broader Project area consist of natural scenic elements such as the flat valley floor, sloping natural terrain within nearby washes, including the Oro Grande Wash and the smaller wash/drainage area adjacent to the Project site, a variety of natural vegetation, including scattered Joshua trees and Juniper, and distant ridgelines of the San Gabriel and San Bernardino Mountains that form a backdrop.

Additionally, there are several man -made elements located throughout the Project area that intervene between viewers and natural scenic elements. These intervening elements include roadways, roadway signage, rural residential buildings, light industrial uses (e.g., truck yards, warehouses, and scrapyards), and transmission lines.

As discussed in further detail below, implementation of the Project would result in the development of three warehouse buildings within an area that contains limited levels of development. While development of these structures would result in some levels of blockage of views of natural scenic elements, these views would still largely be afforded to viewers as they move through the Project area. Moreover, the p resence of existing man -made elements (i.e., transmission lines, signage, and light-industrial uses) within the existing viewshed precludes views of the Project site from being particularly significant. In addition, implementation of MM -AES-1 would require that Project buildings are designed such that building colors mimic the colors and tones found in the natural desert landscape to soften the contrast with the surrounding desert terrain, to the extent feasible. These factors and significance determinations are discussed in further detail below in the context of specific key observation points, which are representative of other views in and around the Project site.

Visual Simulations
KOP 1
KOP 1 provides an existing conditions image and a visual simulation of the Project from Phelan Road/Main Street, located approximately 0.15-mile southwest of the Project site. A residential development is located immediately

Page 53 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
28 March 2022
north of KOP 1, across Phelan Road atop elevated terrain on the western side of the wash/drainage a rea. Views afforded to eastbound motorists include natural scenic resources such as the gently to moderately sloping desert terrain covered with a variety of natural vegetation within a small wash/drainage area that flanks the western side of the Project s ite (within the Los Angeles Bureau of Power and Light Road corridor). A rise in the terrain encompassed by the eastern bank the wash/drainage area is visible and covered with grasses and scattered small to medium sized shrubs, and large Joshua and Juniper trees. The Project site portrays as a flat plateau elevated atop vegetation covered slopes. Multiple transmission lines are apparent in the immediate foreground and middle- ground and are located adjacent to the Project site’s western and southern boundarie s. Associated with these transmission lines are the tall lattice structures within the Los Angeles Bureau of Power and Light Road right-of-way and the smaller wooden t-pole structures along Phelan Road.

The Project would introduce wide, lower-profile warehouse buildings to the Project site. The approximately 48-foot-tall western and southern façades of Building 2 would be prominently visible from KOP 1. The southern façade of the building would be visible extending to the east, as the building fronts Phelan Road for approximately 3,000 feet. The building façades would include vertical and horizontal color variation that would break up the overall massing of the buildings and provide visual interest. While the warehouse buildings would be prominently visible and would alter the existing view, the Project would not substantially block or disrupt views of the natural features from KOP 1. The sloping terrain and existing desert vegetation within the wash/drainage area west of the Project site would remain intact.

Project buildings would not block views across the desert landscape from KOP 1, as under existing conditions, the elevated plateau impedes long distance views across the landscape from KOP 1. As motorists travel east on Phelan Road, the road slopes upward to meet the elevation of the Project site. Phelan Road is a major arterial, which is meant to accommodate large volumes of through-traffic traveling at higher speeds (City of Hesperia 2010a). Assuming drivers are traveling on Phelan Road at prevailing speeds (55 mph), Building 2 would front Phelan Road and screen immediate views across the landscape to the north for a brief period (approximately 38 seconds) and views would be quickly restored. Some Joshua trees that are visible from KOP 1 and additional trees within the Project site would be removed.

However, Joshua trees would be relocated according to the Joshua Tree Relocation Plan (see Section 2.3.2, Biological Resources). Thus, views from KOP 1 would not be substantially impacted such that views of scenic vistas or scenic resources would be substantially blocked or screened from view.

KOP 2
KOP 2 provides an existing conditions image and a visual simulation of the Project from the intersection of Bellflower Street and Yucca Terrace Drive, approximately 0.28-mile northwest of the Project site. KOP 2 is representative of views to toward the Project site from local roads within the rural residential and light industrial/commercial areas surrounding the Project site. Rural residential properties are located within close proximity of KOP 2. Scenic vistas and scenic resources visible from this location include the expansive desert terrain and natural vegetation (including Joshua trees) and the background ridgeline of the San Bernardino Mountains. Similar other views surrounding the Project site, existing transmission lines and tall lattice towers and t-poles are the primary built structures that intervene between viewers and scenic backdrops. While these features do not block views of the desert landscape or Sa n Bernardino Mountains, the disorganized repetition of the linear and angular features detract from the overall integrity of the viewshed. Additionally, several medium-duty and heavy-duty trucks are visible in the foreground and middle- ground, in an area immediately north of the Project site. These trucks are parked on one of many truck storage lots located throughout the Project area and throughout the U.S. Highway 395 corridor.

Upon Project implementation the Project would introduce warehouse buildings (o nly Buildings 1 and 2 would be visible from KOP 2) into the viewshed. The existing view of the foreground desert terrain and natural vegetation would remain intact, and Joshua trees removed from the Project site would be relocated according to the Joshua

Page 54 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
29 March 2022
Tree Relocation Plan (see Section 2.3.2). Project buildings would display a low, flat profile that would mimic the flat desert terrain. As shown in the visual simulation, Project buildings would display a variety of tan and brown colors with vertical and horizontal elements, which would disrupt the monotony of the building facades. However, the bright/light tan of the western façade of the buildings would be prominently visible and would contrast with the natural desert terrain. MM-AES-1 would require that Project buildings are designed such that building colors mimic the colors and tones found in the natural desert landscape to soften the contrast with the desert terrain, to the extent feasible.

Further, the Project would include landscaping that would incorporate natural vegetation and that would complement the desert landscape. With implementation of MM-AES-1 and through site specific landscaping, the visible contrast with the surrounding environment would be softened. Additionally, introduction of Project buildings on the Project site would shorten the available views across the flat desert landscape, and when viewed directly across the Project site, would block a portion of San Bernardino Mountains from view. However, given the low profile and limited extent of Project buildings, these views would only be partially blocked from view and would be fully restored to viewers as they travel around the Project area. Moreover, these views of the desert landscape and San Bernardino Mountains are already interrupted by existing transmission facilities and trucking-related use which detract from the overall integrity of the viewshed. Thus, placement of Project structures within the viewshed of this KOP, which is representative of other views in and around the Project site, would not result in a significant impact to scenic vistas, as the Project buildings would only result in minor blockage of views of desert landscape and the San Bernardino Mountains; views would be restored upon moving around the Project site; and existing intervening features within and surrounding the Project site detract from existing views through and beyond the Project site. Therefore, with incorporation of MM-AES- 1, impacts associated with scenic vistas would be less than significant.

Regulations Governing Scenic Quality
California Public Resources Code Section 21071 defines an “urbanized area” as “an incorporated city that meets either of the following criteria: (1) Has a population of at least 100,000 persons, or (2) Has a population of less than 100,000 persons if the population of that city and not more than two contiguous incorporated cities combined equals at least 100,000 persons.” T he City’s population in 2019 was approximately 95,750 people (U.S. Census 2019). However, the City is border ed by the City of Victorville to the north, City of Apple Valley to the east, unincorporated San Bernardino County land to the south, and the unincorporated community of Oak Hills to the west. The combined population of the City of Hesperia and any one of these adjacent Cities is over 100,000 persons. Thus, the Project site is considered to be within an urbanized area and following analysis considers whether the Project would conflict with applicable zoning or other regulations governing scenic quality. Nonetheless, the Project’s compatibility with the existing visual character and quality of the surrounding area as viewed from public vantage points has also been considered and discussed throughout this analysis.

The Project would result in the construction of three industrial/warehouse buildings on relatively flat, vacant land.

The Project would result in an increase in the intensity of use on currently undeveloped site, as the Project would support a variety of activities associated with the three industri al/warehouse buildings, including the ingressing and egressing of passenger vehicles and trucks, the loading and unloading of trucks with designated truck courts/loading areas, and the internal and external movement of materials around the Project site via forklifts, pallet jacks, and similar equipment. In an attempt to ensure that current and future development within the City is designed and constructed to conform to existing the visual character and quality, the City of Hesperia Development Code (Title 16 of the City’s Municipal Code) includes design standards related to building size, height, floor area ratio, and setbacks, as well as landscaping, signage, and other visual considerations. These design standards help adjacent land uses to be visually consistent with one another and their surroundings, and reduces the potential for conflicting visual elements. More specific to the Project site, the Main Street and Freeway Corridor Specific Plan sets forth development standards for the CIBP Zone and industrial development. The design specifications for the

Page 55 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
30 March 2022
Project would be reviewed by the City for compliance with all applicable provisions set forth by the City’s Development Code and the Specific Plan. As part of the City’s development review process, the Proj ect’s architectural plans would be reviewed by City staff and the Planning Commission to determine whether Project design conforms to the Development Code and Specific Plan, and promotes the visual character and quality of the surrounding area.

Due to the size and scale of industrial buildings, it is especially important to consider design to ensure compatibility with other parts of the community. Chapter 11 of the Specific Plan provides additional details regarding design standards and guidelines for indu strial development. In accordance with the Specific Plan design guidelines, all setback areas would be landscaped, and building orientation, siting and entrances would be designed to minimize conflicts with the surrounding visual environment. For instance, landscaping and vegetation would be used to provide visual screening, and building facades would feature a complementary neutral color palette and a variety of building materials.

With implementation of MM-AES-1, building colors shall be reviewed to incorporate the colors and tones that match or complement the natural desert environment such that color contrasts with the surrounding environment would be minimized. Buildings would include materials such as concrete, metal, aluminum entry framing, and glass, and building elevations would include vertical and horizontal elements that would break up the overall massing of the buildings and provide visual interest.

Project buildings and streetscape elements (e.g., lighting and paving materials) would be designe d to minimize conflicts between the Project and existing residential neighborhoods to the north, west, east and south by locating the most intensive components of the Project as far away from residences as possible. The existing natural and semi-natural land uses, such as Oro Grande Wash corridor and the adjacent wash/drainage area to the west of the Project site (within the Los Angeles Bureau of Power and Light Road transmission corridor), would serve as natural buffers between the Project site and surrounding residential areas.

The Project would be of similar bulk and scale as other industrial and commercial development located throughout the City and region, such as the existing manufacturing, distributing and commercial uses located approximately 1 mile east and south of the Project site, near I-15 and U.S. Highway 395. Further, the flat, low appearance of Project buildings would mimic the surrounding, relatively flat desert landscape.

The visual setting surrounding the Project site currently consists of primarily undeveloped desert landscape with scattered residential, commercial and light industrial uses, and panoramic views of the surrounding valley and mountains. The visual integrity of the site itself has been disrupted by the disturbed nature of the site, which is crossed by dirt trails and roads and scattered debris piles due to ongoing trespassing and illegal dumping on site, debris piles and exposed soils are visible near the road as well as scattered throughout the site). Overall, Project development would alter the existing rural character of the Project area. However, the proposed building elevations are consistent with the design standards and guidelines outlined in the Specific Plan.

The Main Street and Freeway Corridor Specific Plan encourag es architectural design to maximize views of the landscape and incorporate natural elements. Project landscaping would include a plant palette that complements and reflects the natural desert environment. Further, with incorporation of MM-AES-1, natural desert tones would be used in Project colors and materials to reduce contrast with the surrounding environment. The Project would eliminate the illegal uses currently occurring on site (trespassing and illegal dumping), and develop the vacant parcels with maintained development and landscaping. Therefore, compliance with the City’s Development Code and the Main Street Corridor Specific Plan design standards and guidelines, implementation of site specific landscaping, and with

Page 56 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
31 March 2022
implementation of MM-AES-1, the Project would not conflict applicable zoning or other regulations governing scenic quality and impacts related to visual character and quality would be less than significant.

Cumulative Aesthetics Impacts
The Project is located within the Main Street and Freeway Corridor Specific Plan area, and thus, would be designed and constructed according to the design guidelines and standards outlined in the Specific Plan for the CIBP Zone and industrial development. These guidelines and standards aim to protect the Specific Plan area’s high desert setting and panoramic mountain views. All related projects located within the Specific Plan area would be subject to these design guidelines and standards, which include rec ommendations for the architectural character of new buildings to maximize views of the landscape while taking inspiration from surrounding natural elements.

The development and design standards provide the framework for the desired aesthetic and visual en vironment.

Other development projects in the area will incorporate development standards, design guidelines, and other strategies outlined in the Specific Plan. In addition, with implementation of MM -AES-1, the Project’s proposed building colors shall be reviewed to incorporate the colors and tones that match or complement the natural desert environment such that color contrasts with the surrounding cumulative environment would be minimized. Thus, cumulative impacts related to the visual quality and charact er of the Project area would not be cumulatively considerable, assuming that related Projects would implement the same mandatory design standards set forth in the Specific Plan to which the Project must adhere.

Related development in the Specific Plan area and surrounding areas would introduce new sources of light in a setting that includes large areas of undeveloped land. However, Project lighting would comply with existing requirements (i.e., lighting would be directed downward, shielded, and focused on the Project site) to ensure lighting has a minimal effect on the overall night sky and reduce the potential for glare. Other projects located throughout the Specific Plan area would similarly be required to comply with these regulations. Therefore, complian ce with these regulations would ensure that lighting and glare impacts would be less than significant with mitigation incorporated.

2.3.1.2 Mitigation Measures
MM-AES-1: Project buildings and elements shall include colors and tones that mimic the natural desert environment. The Project applicant shall present to the City of Hesperia a materials board showing the proposed building color palette for review and approval prior to issuance of the first building permit. City staff shall review the color palette to ensure that the selected colors and tones largely conform to those colors and tones already found in the surrounding natural desert landscape. The color palette, along with the Project design as a whole, shall also be reviewed to assure conformance with the development standards of the Hesperia Municipal Code and the Main Street and Freeway Corridor Specific Plan in order to promote the visual character and quality of the surrounding area.

2.3.1.3 Findings Per CEQA Guidelines
Consistent with CEQA Guidelines Section 15126.4(a)(1), feasible measures that can minimize significant adverse impacts were developed for the potentially significant impacts described in Section 2.3.1.1. This feasible measure, MM-AES-1, is described in Section 2.3.1.2.

Page 57 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
32 March 2022
The City finds that this mitigation measure is feasible, is adopted, and will reduce the potential aesthetics impacts of the proposed project to less -than-significant levels. Accordingly, the City finds that, pursuant to CEQA Section 21081(a)(1) and CEQA Guideli nes Section 15091(a)(1), changes or alterations have been required in, or incorporated into, the proposed project that mitigate or avoid potentially significant aesthetics‐related impacts of the proposed project identified in the Final EIR.

2.3.1.4 Facts in Support of the Findings Related to Aesthetics The City finds that the mitigation measure is feasible, is adopted, and will reduce the proposed project’s aesthetics impact. Potential impacts to scenic vistas and cumulative aesthetics would be reduced to a less-than-significant level with implementation of MM-AES-1. Furthermore, the Project’s conflicts with regulations governing scenic quality would be reduced to less than significant with implementation of MM-AES-1.

2.3.2 Air Quality

2.3.2.1 Potentially Significant Impacts to Air Quality Resources Cumulatively Considerable Net Increase of Criteria Pollutants Short-Term Construction Impacts
Construction of the Project would result in the temporary addition of pollutants to the local airshed ca used by on- site sources (i.e., off -road construction equipment and soil disturbance) and off -site sources (i.e., on -road haul trucks, vendor trucks, and worker vehicle trips). Construction emissions can vary substantially from day to day, depending on the level of activity, the specific type of operation, and for dust, the prevailing weather conditions.

Therefore, such emission levels can only be approximately estimated with a corresponding uncertainty in precise ambient air quality impacts.

Criteria air po llutant emissions associated with temporary construction activity were quantified using CalEEMod.

CalEEMod calculates maximum daily emissions for summer and winter periods. Under the assumed scenarios, emissions resulting from the Project construction woul d exceed criteria pollutant thresholds established by the MDAQMD for VOC emissions. This impact would be potentially significant without mitigation.

MM-AQ-1 will be implemented to reduce the impacts, which requires that the Project shall utilize “Super-Compliant” low VOC paints which have been reformulated to exceed the regulatory VOC limits put forth by MDAQMD’s Rule 1113. Super-Compliant low VOC paints shall be no more than 10 grams per liter (g/L) of VOC. Alternatively, the Project Applicant may utilize tilt-up concrete buildings that do not require the use of architectural coatings. In addition, MM -AQ-2 and MM -AQ-3 would be implemented to further reduce Project -generated construction emissions, including VOC emissions, associated with equipment and vehicle exhaust. The effectiveness of MM-AQ-1 is quantified in the mitigated emissions estimate; however, the emission reductions associated with implementation of MM-AQ-2 cannot be accurately quantified at this time and the emission reductions associated with MM-AQ-3 are conservatively not assumed.

After implementation of MM-AQ-1, regional construction emissions would not exceed the applicable MDAQMD thresholds of significance for any criteria pollutant. Mitigation measures MM-AQ-2 and MM-AQ-3 would further reduce Project- generated construction emissions; however, the associated emission reductions are not estimated herein. Therefore,

Page 58 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
33 March 2022
with the incorporation of mitigation, short-term impacts associated with a cumulatively considerable net increase of any criteria pollutant for which the Project region is non-attainment would be less than significant.

2.3.2.2 Mitigation Measures
MM-AQ-1 through MM-AQ-3 can be found in Section 2.2.1.2, above.

2.3.2.3 Findings Per CEQA Guidelines
Consistent with CEQA Guidelines Section 15126.4(a)(1), feasible measures that can minimize significant adverse impacts were developed for the potentially significant impacts described in Section 2.3.2.1. These feasible measures, MM-AQ-1 through MM-AQ-3, are listed in Section 2.2.1.2.

The City finds that these mitigation measures are feasible, are adopted, and will reduce the potential air quality impacts of the proposed project to less than significant levels. Accordingly, the City finds that, pursuant to CEQA Section 21081(a)(1) and CEQA Guidelines Section 15091(a)(1), changes or alterations have been required in or incorporated into the proposed project that will mitigate or avoid potentially significant impacts on air quality.

2.3.2.4 Findings Per CEQA Guidelines
Implementation of MM-AQ-1 through MM-AQ-3 would reduce potentially significant impacts related to air quality as described in Section 2.3.2.1 to a less than significant level. There would be no significant, unavoidable impacts related to air quality as described in Section 2.3.2.1 after implementation of these mitigation measures.

2.3.3 Biological Resources

2.3.3.1 Potentially Significant Impacts to Biological Resources Candidate, Sensitive, or Special-Status Species
The following section evaluates the Project’s effects on plant and wildlife species identified as candidate, sensitive, or special status species in local or regional plans, policies, or regulations, or by the CDFW or USFWS.

Special-Status Plant Species
Direct Impacts
Desert native plants protected under the City of Hesperia’s Municipal Code and California Desert Native Plants Act Plants are described below. No non-listed special-status plant species were observed within the Project site or Off- Site Utilities Alignments (the Off-Site Sewer Alignment and the Off-Site Water Alignment) and none are expected to occur. Western Joshua tree, a candidate for state listing under CESA, was observed and would be directly impacted by the Project. Based on the site plan, implementation of the Project would result in direct impacts to 1,367 western Joshua tree individuals. All ground -disturbing activities, even areas temporarily impacted, are considered permanent impacts to western Joshua trees.

As required by MM-BIO-1, mitigation for direct impacts to 1,367 western Joshua trees will be fulfilled through conservation of Western Joshua tree through purchase of credits at a CDFW -approved mitigation bank or other

Page 59 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
34 March 2022
conservation mechanism approved by the City of Hesperia and CDFW. Additionally, as required by MM-BIO-2 and in accordance with Chapter 16.24 of the Hesperia Municipal Code, the preparation of a Joshua tree and desert native plants relocation plan is required to mitigate impacts to western Joshua trees as a result of the Project. As such, a Joshua Tree Preservation, Protection, and Relocation Plan, and California Desert Native Plant Relocation Plan was prepared to provide detailed specifications for the Project Applicant to meet the requirements of Chapter 16.24 of the Hesperia Municipal Code to protect, preserve, and mitigate impacts to Joshua trees.

Indirect Impacts
Construction-related indirect impacts may include inadvertent spillover impacts outside of the construction footprint, dust accumulation on individual western Joshua tre es, chemical spills, stormwater erosion and sedimentation, and increased wildfire risk.

Implementation of MM-BIO-3 gives the Project’s Designated Biologist the authority to stop work if construction is not compliant with this CEQA document. MM-BIO-4 requires that an experienced biologist oversee compliance with the protective measures, including limiting impacts to the Project impact footprint. MM-BIO-5 would provide construction personnel with training related to western Joshua trees that are present on and adjacent to the impact footprint. MM-BIO-6 provides for documentation that the education program was administered to applicable personnel. MM-BIO-7 requires that impacts occur within the fenced, staked, or flagged area that is clearly delineated within the Project impact footprint. The construction crew will be responsible for unauthorized impacts from construction activities to western Joshua trees that are outside the permitted Project footprint. Thus, implementation of MM-BIO-3 through MM-BIO-7 will enable the Project to avoid and minimize inadvertent spillover impacts outside of the approved impact footprint.

To reduce fugitive dust resulting from Project construction and to minimize adverse air quality impacts, the Project would employ dust mitigation measures in accordance with the Mojave Desert Air Quality Management District’s Rules 401 and 403.2, which limit the amount of fugitive dust generated during construction.

MM-BIO-8 would ensure that a prompt and effective response to any accidental chemical spills will be implemented and that repair and clean-up of any hazardous waste occurs. Thus, implementation of MM-BIO-8 would help to avoid and minimize impacts to western Joshua tree from any construction-related chemical spills.

A Stormwater Pollution Prevention Plan would be prepared and implemented to prevent all construction pollutants from contacting stormwater during construction activities, with the intent of keeping sediment and any other pollutants from moving off site and into receiving waters. Best management practice categories employed on site would include erosion control, sediment control, and non -stormwater good housekeeping. Preparation and implementation of a Stormwater Pollution Prevention Plan would help to avoid and minimize the p otential effects of stormwater erosion during construction.

Construction of the Project would introduce potential ignition sources to the Project site, including the use of heavy machinery and the potential for sparks during welding activities or other ho t work. However, the Project would be required to comply with City of Hesperia and state requirements for fire safety practices to reduce the possibility of fires during construction activities. Further, vegetation would be removed from the site prior to t he start of construction. Adherence to City of Hesperia and state regulatory standards during Project construction would reduce the risk of wildfire ignition and spread during construction activities. Therefore, short -term construction impacts involving wildland fires would not be substantial.

Page 60 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
35 March 2022
Potential long-term (post-construction) indirect impacts from operations and maintenance activities may include effects of herbicides, changes in water quality, increased wildfire risk, and accidental chemical spills.

MM-BIO-9 would limit herbicide use to instances where hand or mechanical efforts are infeasible and would only be applied when wind speeds are less than 7 miles per hour to prevent drift into off-site western Joshua trees.

Implementation of low-impact-development features and best management practices would, to the maximum extent practicable, reduce the discharge of pollutants into receiving waters, including inadvertent release of pollutants (e.g., hydraulic fluids and petroleum); the improper management of hazardous materials; trash and debris; and the improper management of portable restroom facilities (e.g., regular service) in accordance with all relevant local and state development standards. In addition, in accordance with CalGreen requirements (Cal ifornia Green Building Standards Code, CCR, Title 24, Part 11), Project source controls to improve water quality would be provided for outdoor material storage areas, outdoor trash storage/waste handling areas, and outdoor loading/unloading areas. Therefore, impacts to western Joshua trees due to changes in water quality would be avoided and minimized through implementation of low-impact-development features and best management practices.

Upon completion of Project construction, with adherence to the City of Hesperia’s Municipal Code and because of the low ignitability of the proposed structures and implementation of fire -resistant and irrigated landscaping, the Project would not facilitate wildfire spread or exacerbate wildfire risk. Further, given that surrounding off-site fuels consist of moderately spaced vegetation, wildfires in the immediate surrounding area are not common, and it is unlikely that the Project site would be exposed to the uncontrolled spread of a wildfire. It is not anticipated that the Project, due to slope, prevailing winds, and other factors, would exacerbate wildfire risks or the uncontrolled spread of a wildfire; thus, with adherence to the City of Hesperia’s Municipal Code, long -term indirect impacts to western Joshua tree associated with increased wildlife risk is not expected to occur.

Special-Status Wildlife
Burrowing Owl
Direct Impacts
Burrowing owl was not observed on the Project site or Off-Site Utilities Alignments; however, suitable habitat exists on site, and the species could eventually occupy the Project site or Off -Site Utilities Alignments prior to construction.

Pursuant to the California Fish and Game Code and the MBTA, a pre ‐construction survey in compliance with Staff Report on Burrowing Owl Mitigation, State of California Natural Resource Agency, Department of Fish and Game, May 7, 2012 (CDFW 2012) would be necessary to reevaluate the locations of potential burrowing owl burrows located within the Project limits so take of owls or active owl nests can be avo ided. Consistent with MM -BIO-3, a pre - construction survey for burrowing owl shall be conducted in areas supporting potentially suitable habitat and within 14 days prior to the start of construction activities. Additionally, a burrowing owl relocation plan has been prepared.

The Project would result in the loss of 192.5 acres of suitable habitat for burrowing owl. As required by MM-BIO-1, mitigation for direct impacts to western Joshua trees will be fulfilled through conservation of Western Joshua tree through purchase of credits at a CDFW-approved mitigation bank or other conservation mechanism approved by the City of Hesperia and CDFW. Conservation efforts for western Joshua tree associated with this mitigation will focus on the conservation of large, interconnected Joshua tree woodlands on lands where edge effects are limited, versus lands in urban settings that are subject to habitat fragmentation and edge effects, such as the Project site. Thus, mitigation for impacts to western Joshua tree will also mitigate for impacts to loss of suitable habitat for burrowing owl.

Page 61 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
36 March 2022
Indirect Impacts
Construction activities have the potential to result in indirect impacts to burrowing owls and their habitat. Those impacts could include dust, noise and vibration, trash and debris, increased human presence, vehicle collisions, chemical spills, and night-time lighting. These potential short-term or temporary indirect impacts to burrowing owls are considered significant absent mitigation.

MM-BIO-10 would require burrowing owl surveys and result in establishment of construction buffers around any burrowing owl dens found, thus limiting effects from most short-term indirect impacts, including noise and vibration, increased human presence, night-time lighting, and vehicle collisions. MM-BIO-11 would require night-time lighting during construction within 50 feet of habitat for special-status species to be shielded downward. MM-BIO-3, MM-BIO- 4, and MM-BIO-6 would require that all workers complete a Worker Environmental Awareness Program (WEAP) training and would require ongoing biological monitoring and compliance with all biological resource mitigation requirements.

MM-BI0-12 would require trash and debris to be removed regularly and would require animal -resistant trash receptacles to avoid attracting urban-related, predator species. MM-BIO-8 would ensure that a prompt and effective response to any accidental chemical spills will be implemented and that repair and clean-up of any hazardous waste occurs. To reduce fugitive dust resulting from project construction and to minimize adverse air quality impacts, the Project would employ dust mitigation measures in accordance with the Mojave Desert Air Quality Management District’s Rules 401 and 403.2, which limit the amount of fugitive dust generated during construction.

Potential long-term indirect impacts that could result from development within or adjacent to burrowing owl habitat include nighttime lighting and increased invasive plant species that may degrade habitat. MM-BIO-11 would require night-time lighting during operations within 50 feet of habitat for special -status species to be shielded downward.

MM-BIO-4 would result in restoration of temporary impact areas that would limit the introduction of non -native species in burrowing owl habitat and avoid long-term habitat degradation.

With the incorporation of mitigation, direct and indirect impacts to burrowing owl would be less than significant.

Loggerhead Shrike
The loggerhead shrike is a CDFW species of special concern during its nesting period. It can be found in lowlands and foothills throughout California. It prefers open habitats with scattered shrubs, trees, posts, fences, utility lines, or other perches. Highest density occurs in open-canopied valley foothill hardwood, valley foothill hardwood-conifer, valley foothill riparian, pinyon-juniper, juniper, desert riparian, and Joshua tree habitats. Loggerhead shrike was not observed during the biological surveys, but has a moderate potential to occur on the Project site and within the Off- Site Utilities Alignments. Extensive suitable nesting habitat, particularly near Joshua trees, is present within the Project site and Off-Site Utilities Alignments.

Direct Impacts
To avoid potential impacts to nesting loggerhead shrike, it is recommended that the vegetation removal activities be conducted outside the general bird nesting season (February 1 through August 31). If vegetation cannot be removed outside the bird nesting season, a pre‐construction nesting bird survey by a qualified biologist is required prior to vegetation removal. This requirement is outlined in MM-BIO-15. Also, the Project would result in the loss of 192.5 acres of suitable habitat for loggerhead. As required by MM-BIO-1, mitigation for direct impacts to weste rn Joshua trees will be fulfilled through conservation of Western Joshua tree through purchase of credits at a CDFW - approved mitigation bank or other conservation mechanism approved by the City of Hesperia and CDFW.

Page 62 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
37 March 2022
Conservation efforts for western Joshua tree associated with this mitigation will focus on the conservation of large, interconnected Joshua tree woodlands on lands where edge effects are limited, versus lands in urban settings that are subject to habitat fragmentation and edge effects, such as t he Project site. Thus, mitigation for impacts to western Joshua tree will also mitigate for impacts to loss of suitable habitat for loggerhead shrike.

Indirect Impacts
Construction activities have the potential to result in indirect impacts to loggerhead shrike and their habitat. Those impacts could include dust, noise and vibration, increased human presence, vehicle collisions, chemical spills, and night-time lighting. These potential short -term or temporary indirect impacts to loggerhead shrike are consid ered significant absent mitigation.

MM-BIO-15 would require nesting bird surveys and would result in establishment of construction buffers around nests, thus limiting effects from most short-term indirect impacts, including noise and vibration, increased human presence, night-time lighting, and vehicle collisions. MM-BIO-11 would require night-time lighting during construction within 50 feet of habitat for special-status species to be shielded downward. MM-BIO-3, MM-BIO-4, and MM-BIO-6 would require that all workers complete a WEAP training and would require ongoing biological monitoring and compliance with all biological resource mitigation requirements. MM-BIO-8 would ensure that a prompt and effective response to any accidental chemical spills will be implemented and that repair and clean-up of any hazardous waste occurs. To reduce fugitive dust resulting from project construction and to minimize adverse air quality impacts, the Project would employ dust mitigation measures in accordance with the Mojave Desert Air Quality Management District’s Rules 401 and 403.2, which limit the amount of fugitive dust generated during construction.

Potential long-term indirect impacts that could result from development within or adjacent to loggerhead shrike habitat include nighttime lighting and increased invasive plant species that may degrade habitat. MM-BIO-11 would require night-time lighting during operations within 50 feet of habitat for special -status species to be shielded downward. MM-BIO-4 would result in restoration of temporary impact areas that would limit the introduction of non- native species in burrowing owl habitat and avoid long-term habitat degradation.

With the incorporation of mitigation, direct and indirect impacts to loggerhead shrike would be less than significant.

Desert Kit Fox and American Badger
Neither the Biological Resources Letter Report nor any other subsequent fieldwork and reporting observed desert kit fox (Vulpes macrotis arsipus) or American badger (Taxidea taxus) on the Project site or identified suitable habitat for these species within the Project area. The desert kit fox lives in the open desert, on creosote bush flats, and amongst the sand dunes, while American badgers prefer open scrub or grassy areas (NPS 2015; USGS 2020). The Project site is predominated by Joshua tree woodland, and lacks creosote bush flats, sand dunes, or larger areas of open scrub or grassy areas. Thus, the Project site is not expected to support either desert kit fox or American badger.

Notwithstanding, in their scoping comment letter dated December 19, 2019, CDFW staff requested that development of a desert kit fox and American badger mitigation and monitoring plan be developed. As such, in an abundance of caution and to ensure that potential impacts to these species are less than significant, the Project Applicant shall prepare a mitigation and monitoring plan that addresses desert kit fox and American badger if either species is determined to occur on the Project site prior to the start of construction, pur suant to MM-BIO-14. With the incorporation of mitigation, impacts associated with desert kit fox and American badger would be less than significant.

Page 63 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
38 March 2022
Nesting Migratory Birds and Raptors
Similar to most other sites containing trees, shrubs, and other vegetat ion, the Project site contains opportunities for birds of prey (raptors) and other avian species to nest on site. Native nesting bird species with potential to occur within the Project site are protected by California Fish and Game Code Sections 3503 and 3 503.5, and by the federal MBTA (16 USC 703 –711). In particular, Section 3503 provides that it is unlawful to take, possess, or needlessly destroy the active nests or eggs of any bird in California; Section 3503.5 protects all raptors and their eggs and active nests; and the MBTA prohibits the take (including killing, capturing, selling, trading, and transport) of native migratory bird species throughout the United States. Recently, the Department of Interior ruled that the MBTA should apply only to “… affirmative actions that have as their purpose the taking or killing of migratory birds, their nests, or their eggs” and will not be applied to incidental take of migratory birds pursuant to otherwise lawful activities However, that ruling is now under review a s a revision to the MBTA that would include prohibitions to incidental take has recently been proposed.

To ensure compliance with the California Fish and Game Code and MBTA and to avoid potential impacts to nesting birds, it is recommended that the vegetat ion removal activities be conducted outside the general bird nesting season (February 1 through August 31, depending on the species), and if vegetation cannot be removed outside the bird nesting season, a pre‐construction nesting bird survey by a qualified biologist is required prior to vegetation removal. This requirement is outlined in MM-BIO-15. With the incorporation of mitigation, impacts associated with nesting birds, including raptors, would be less than significant.

Adverse Impact on Riparian Habitat/Sensitive Natural Communities Joshua tree woodland is a sensitive CDFW natural community. As described above, western Joshua trees are also protected under CESA as a candidate species.

Direct Impacts
All ground-disturbing activities, even areas temporarily impacted, are considered permanent impacts to Joshua tree woodland. The Project will result in permanent impacts to 192.5 acres of Joshua tree woodland, which would be considered a significant impact under CEQA.

The Project would also result in permanent impacts to 12.4 acres and temporary impacts to 2.6 acres of disturbed habitat and urban/developed lands. These land cover types are not considered sensitive by CDFW and provide little biological value. Therefore, these direct impacts are considered less than significant under CEQA.

As required by MM-BIO-1, mitigation for direct impacts to 1,367 western Joshua trees will be fulfilled through conservation of Western Joshua tree through purchase of credits at a CDFW -approved mitigation bank or oth er conservation mechanism approved by the City of Hesperia and CDFW. Conservation efforts for western Joshua tree will focus on the conservation of large, interconnected Joshua tree woodlands on lands where edge effects are limited, versus lands in urban settings that are subject to habitat fragmentation and edge effects, such as the Project site. Thus, mitigation for impacts to western Joshua tree will also mitigate for impacts to Joshua tree woodland.

Additionally, as required by MM-BIO-2 and In accordance with Chapter 16.24 of the Hesperia Municipal Code, the preparation of a Joshua tree and desert native plants relocation plan is required to mitigate impacts to western Joshua trees as a result of the Project. As such, a Joshua Tree Preservation, Protect ion, and Relocation Plan was prepared for Project to provide detailed specifications for the Project Applicant to meet the requirements of Chapter

Page 64 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
39 March 2022

16.24 of the Hesperia Municipal Code to protect, preserve, and mitigate impacts to Joshua trees. Thus, mitigation for impacts to western Joshua tree will also mitigate for impacts to Joshua tree woodland.

Indirect Impacts
Potential construction- and operation-related indirect impacts to Joshua tree woodland, would be the same as the indirect impacts to western Joshua tree, as described above.

With the incorporation of mitigation, and with adherence to both the CDNPA and the Hesperia Municipal Code, impacts associated with Joshua tree woodland would be less than significant.

Adverse Effect on Wetlands
No potential jurisdictional features subject to regulation by ACOE, CDFW, or RWQCB were found to be present within the limits of the Project site. The Off-Site Utilities Alignments would traverse and come in close proximity to waters of the state and waters potential ly subject to CDFW jurisdiction. As currently designed, the Off -Site Utilities Alignments traverse several upland ephemeral drainage features associated with Oro Grande Wash.

Based on current site plans, the proposed Off-Site Utilities Alignments would bore beneath the Oro Grande Wash at two different locations both east and south/southeast of the Project site, with the proposed sanitary sewer line and domestic water line will be placed outside of any potentially jurisdictional limits. By boring beneath the jurisdictional limits within this drainage, the Project will eliminate the potential impacts to regulated waters of the state, including RWQCB and CDFW.

However, if the final Project design results in the encroachment or placement of fill within the jur isdictional limits of Oro Grande Wash, adherence to the Porter-Cologne Water Quality Act and Section 1600, et seq., of the California Fish and Game Code will be required. A Waste Discharge Requirement from the RWQCB and a Streambed Alteration Agreement from CDFW would be required. These permits would need to be issued prior to the start of construction within Oro Grande Wash.

Direct Impacts
The Project could potentially result in significant direct impacts to areas under the jurisdiction of CDFW and RWQCB absent mitigation. As described, to the extent practicable, the Project shall be designed to avoid impacts to the jurisdictional waters of the state; if jurisdictional areas cannot be avoided, necessary resource agency permits shall be obtained, and compensatory mitigation would occur at a ratio not less than 1:1 for the impacts to jurisdictional waters in accordance with MM-BIO-16.

Indirect Impacts
Construction-related indirect impacts may include inadvertent spillover impacts outside of the construction footprint, chemical spills, and stormwater erosion and sedimentation.

Implementation of MM-BIO-3 gives the Project’s Designated Biologist the authority to stop work if construction is not compliant with this CEQA document. MM-BIO-4 requires that an experienced biologist oversee compliance with the protective measures, including limiting impacts within the Project footprint. MM-BIO-5 would provide construction personnel with training related to waters of the state that are present on and adjacent to the imp act footprint. MM-BIO-6 provides for documentation that the education program was administered to applicable

Page 65 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
40 March 2022
personnel. MM-BIO-7 requires that impacts occur within the fenced, staked, or flagged area that is clearly delineated within the Project impact footprint. The construction crew will be responsible for unauthorized impacts from construction activities to waters of the state that are outside the permitted project footprint. Thus, implementation of MM-BIO-3 through MM-BIO-7 will enable the Project to avoid and minimize inadvertent spillover impacts outside of the approved impact footprint.

MM-BIO-8 would ensure that a prompt and effective response to any accidental chemical spills will be implemented and that repair and clean-up of any hazardous waste occurs. Thus, implementation of MM-BIO-8 would help to avoid and minimize impacts to waters of the state from any construction-related chemical spills.

A Stormwater Pollution Prevention Plan would be prepared and implemented to prevent all construction pollutants from contacting stormwater during construction activities, with the intent of keeping sediment and any other pollutants from moving off site and into receiving waters. Best management practice categories employed on site would include erosion contr ol, sediment control, and non -stormwater good housekeeping. Preparation and implementation of a Stormwater Pollution Prevention Plan would help to avoid and minimize the potential effects of stormwater erosion during construction.

Potential long-term (post-construction) indirect impacts from operations and maintenance activities may include changes in water quality and accidental chemical spills.

Implementation of low-impact-development features and best management practices would, to the maximum extent practicable, reduce the discharge of pollutants into receiving waters, including inadvertent release of pollutants (e.g., hydraulic fluids and petroleum); the improper management of hazardous materials; trash and debris; and the improper management of portable restroom facilities (e.g., regular service) in accordance with all relevant local and state development standards. In addition, in accordance with CalGreen requirements (California Green Building Standards Code, CCR, Title 24, Part 11), Project source controls to improve water quality would be provided for outdoor material storage areas, outdoor trash storage/waste handling areas, and outdoor loading/unloading areas. Therefore, impacts to western Joshua trees due to changes in water quality would be avoi ded and minimized through implementation of low-impact-development features and best management practices.

BIO-MM-8 would ensure that a prompt and effective response to any accidental chemical spills will be implemented, and repair and clean -up of any haz ardous waste occurs. Thus, implementation of BIO-MM-8 would help to avoid and minimize impacts to western Joshua tree from any operations-related chemical spills.

With the incorporation of mitigation, and with adherence to both the Porter-Cologne Water Quality Act and Section 1600, et seq., of the California Fish and Game Code, potential impacts to waters of the state would be less than significant.

Conflict with Biological Resources Protection Policies and Ordinances California Desert Native Plants
In addition to western Joshua tree, one desert native plant species, Wiggins’ cholla ( Cylindropuntia echinocarpa), was recorded on the Project site and within the Off-Site Utilities Alignments. A total of 66 living and 6 dead plants were documented on the Project site and within the Off-Site Utility Alignments. Because the focused desert native plant survey was positive for Wiggins’ cholla, and in accordance with the California Desert Native Plants Act and the Hesperia Municipal Code, Chapter 16.24, a native plant removal permit must be obtained from the City of Hesperia prior to the removal of Wiggins’ cholla. Additionally, Wiggins’ cholla is addressed in the Joshua Tree Preservation,

Page 66 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
41 March 2022
Protection, and Relocation Plan, and Desert Native Plant Relocation Plan, pre pared to provide detailed specifications for the Project Applicant to meet the requirements of Chapter 16.24 of the Hesperia Municipal Code to protect, preserve, and mitigate impacts to desert native plants.

Pursuant to MM-BIO-2, the Project Applicant sha ll submit an application and applicable fee paid to the City of Hesperia for removal or relocation of protected native desert plants under Hesperia Municipal Code Chapter 16.24.

The application shall include certification from a qualified Joshua tree and native desert plant expert(s) to determine that proposed removal or relocation of protected native desert plants are appropriate, supportive of a healthy environment, and in compliance with the City of Hesperia Municipal Code. The application will include t he Joshua Tree Preservation, Protection, and Relocation Plan and Desert Native Plant Relocation Plan. The plan shall be prepared by a qualified Joshua tree and native desert plant expert(s). With the incorporation of mitigation, and with adherence to both the CDNPA and the Hesperia Municipal Code, impacts associated with desert native plants would be less than significant.

Joshua Trees
In accordance with Chapter 16.24 of the Hesperia Municipal Code, the preparation of a Joshua tree and desert native plants relocation plan is required to mitigate impacts to Joshua trees as a result of the Project. As such, a Joshua Tree Preservation, Protection, and Relocation Plan and Desert Native Plant Relocation Plan was prepared for the Project to provide detailed specifications for the Project Applicant to meet the requirements of Chapter 16.24 of the Hesperia Municipal Code to protect, preserve, and mitigate impacts to Joshua trees.

The Joshua Tree Preservation, Protection, and Relocation Plan addresses the requirements of the City’s Protected Plant Policy and provides details for the initial survey of the Project site’s Joshua trees, detailed speci fications for the protection of trees to be preserved on site, and relocation/salvage requirements for those trees requiring removal and relocation.

Pursuant to MM-BIO-2, the Project Applicant shall submit an application and applicable fee paid to the Cit y of Hesperia for removal or relocation of protected native desert plants under Hesperia Municipal Code Chapter 16.24.

The application shall include certification from a qualified Joshua tree and native desert plant expert(s) to determine that proposed rem oval or relocation of protected native desert plants are appropriate, supportive of a healthy environment, and in compliance with the City of Hesperia Municipal Code. The application shall include a detailed plan for removal of all protected plants on the Project site. The plan shall be prepared by a qualified Joshua tree and native desert plant expert(s). With the incorporation of mitigation, and with adherence to both the CDNPA and the Hesperia Municipal Code, impacts associated with Wiggins’ cholla and J oshua tree woodland would be less than significant.

Cumulative Biological Resources Impacts
The Project would result in potentially cumulatively considerable impacts to western Joshua trees and Joshua tree woodland vegetation on the Project site and Off-Site Utilities Alignments. Western Joshua trees are a state candidate species for listing under CESA and are locally protected by the City of Hesperia and by the California Desert Native Plant Act. Joshua tree woodlands are considered a sensitive natural community by CDFW. As required by MM-BIO-1, mitigation for direct impacts to 1,367 western Joshua trees will be fulfilled through conservation of Western Joshua tree through purchase of credits at a CDFW-approved mitigation bank or other conservation mechanism approved by the City of Hesperia and CDFW. Additionally, as required by MM-BIO-2 and in accordance with Chapter 16.24 of the Hesperia Municipal Code, the preparation of a Joshua tree and desert native plants relocation plan is required

Page 67 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
42 March 2022
to mitigate impac ts to western Joshua trees as a result of the Project. As such, a Joshua Tree Preservation, Protection, and Relocation Plan, and Desert Native Plant Relocation Plan was prepared.

Conservation efforts for western Joshua tree (MM-BIO-1) would focus on the conservation of large, interconnected Joshua tree woodlands on lands where edge effects are limited, versus lands in urban settings that are subject to habitat fragmentation and edge effects, such as the Project site. Mitigation efforts would contribute to the conservation of large, interconnected Joshua tree woodlands. Larger preserves have a greater chance of preserving habitat diversity at all scales, support larger local populations, help maintain functioning metapopulations (partially isolated subpopula tions of the same species that support immigration and emigration and provide for recolonizations following local extirpations), support greater species genetic diversity, and are more likely to maintain intact watershed functions. Larger preserves also ha ve less habitat fragmentation and provide greater protection from edge effects due to a larger area -to-perimeter ratio compared to smaller preserves. Additionally, large preserves usually facilitate more cost -effective land management. Pursuant to MM-BIO-2, the Project Applicant shall submit an application and applicable fee paid to the City of Hesperia for removal or relocation of protected native desert plants, including western Joshua tree, under Hesperia Municipal Code Chapter 16.24. The application shall include certification from a qualified Joshua tree and native desert plant expert(s) to determine that proposed removal or relocation of protected native desert plants are appropriate, supportive of a healthy environment, and in compliance with the City of Hesperia Municipal Code. The application shall include a detailed plan for removal of all protected plants on the Project site. The plan shall be prepared by a qualified Joshua tree and native desert plant expert(s). Implementing these mitigation measure (MM-BIO-1 and MM-BIO-2) would reduce potential impacts to a less than significant level and would significantly reduce the potential for a cumulative considerable impact to Joshua tree.

Potential impacts to special-status wildlife species and nesting b irds would be reduced to a less than significant level through Project implementation of MM-BIO-3 through MM-BIO-15. Implementing these mitigation measures would reduce potential impacts to a less than significant level and would significantly reduce the potential for direct or indirect impacts to special-status species. Therefore, there would not be a cumulatively considerable impact on any special-status species.

Potential impacts to jurisdictional waters of the state, if necessary, would be reduced to a less than significant level through implementation of MM-BIO-3, MM -BIO-4, MM -BIO-5, MM -BIO-6, MM -BIO-7, MM -BIO-8, and MM-BIO-16.

Implementing these mitigation measures would reduce potential impacts to a less than significant level and would significantly reduce the potential for direct or indirect impacts to waters of the state. Therefore, there would not be a cumulatively considerable impact to waters of the state.

Additionally, the Project would not result in a significant impact to wildlife corridors and linkages, nor to local policies and regional conservation plans. The Project would therefore not contribute to a cumulative impact on these resources.

2.3.3.2 Mitigation Measures
MM-BIO-1 Conservation of Western Joshua Tree Lands. Mitigation for direct impacts to western Joshua trees will be fulfilled through conservation of western Joshua trees at a 1:1 habitat replacement of equal or better functions and values to those impacted by the project. Mitigation can be through purchases of credits at a California Department of Fish and Wildlife-approved mitigation bank for western Joshua tree or through conservation lands that meet the functions and values criteria. If mitigation is not purchased through a mitigation bank and lands are conserved separately, a cost estimate will be prepared to estimate the initial start -up costs, and ongoing annual costs, of

Page 68 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
43 March 2022
management activities for the management of the conservation easement(s) area in perpetuity.

The funding source will be in the form of an endowment to help the qualified natural lands management entity that is ultimately selected to hold the conservation easement(s). The endowment amount will be established following the completion of a project -specific Property Analysis Record (PAR) to calculate the costs of in perpetuity land management. The PAR will take into account all of the management activities required in the Incidental Take Permit to fulfill the requirements of the conservation easement(s), which are currently in review and development.

Additionally, no take of western Joshua tree will occur without authorization from CDFW in the form of an Incidental Take Permit pursuant to Fish and Game Code 2081. The Project Applicant will adhere to measures and conditions set forth within the Incidental Take Permit.

MM-BIO-2 Relocation of Desert Native Plants. Prior to the issuance of grading permits, the Project Applicant shall submit an application and applicable fee paid to the City of Hesperia for removal or relocation of protected native desert plants under Hesperia Municipal Code Chapter 16.24 as required and schedule a pre -construction site inspection with the Planning Division and the Building Division.

The application shall include certification from a qualified Joshua tree and native desert plant expert(s) to determine that proposed removal or relocation of protected native desert plants are appropriate, supportive of a healthy environment, and in compliance with the City of Hesperia Municipal Code. Protected plants subject to Hesperia Municipal Code Cha pter 16.24 may be relocated on-site, or within an area designated as an area for species to be adopted later.

The application shall include a detailed plan for removal of all protected plants on the Project site.

The plan shall be prepared by a qualified Joshua tree and native desert plant expert(s). The plan shall include, but not be limited to, the following measures:
• Salvaged plants shall be transplanted expeditiously to either their final on -site location, or to an approved off -site area. If the plants cannot be expeditiously taken to their permanent relocation area at the time of excavation, they may be transplanted in a temporary area (stockpiled) prior to being moved to their permanent relocation site(s). • Western Joshua trees shall be marked on their north facing side prior to excavation.

Transplanted western Joshua trees shall be planted in the same orientation as they currently occur on the Project site, with the marking on the north side of the trees facing north at the relocation site(s).
• Transplanted plants shall be watered prior to and at the time of transplantation. The schedule of watering shall be determined by the qualified tree expert and desert native plant expert(s) to maintain plant health. Watering of the transplanted plants shall continue under the guidance of qualified tree expert and desert native plant expert(s) until it has been determined that the transplants have become established in the permanent relocation site(s) and no longer require supplemental watering.

MM-BIO-3 Designated Biologist Authority. The Designated Biologist shall have authority to immediately stop any activity that does not comply with the biological resources mitigation measures and/or to order any reasonable measure to avoid the unauthorized take of an individual western Joshua tree.

MM-BIO-4 Compliance Monitoring. The Designated Biologist shall be on site daily when impacts occur. The Designated Biologist shall conduct compliance inspections to minimize incidental take of western

Page 69 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
44 March 2022
Joshua trees and impacts to other sensitive biological resources; prevent unlawful take of western Joshua trees; and ensure that signs, stakes, and fencing are intact, and that impacts are only occurring within the permitted impact footprint. Weekly written observation and inspection records that summarize oversight activities and compliance inspections and monitoring activities required by the Incidental Take Permit shall be prepared.

MM-BIO-5 Education Program. An education program (Worker Environmental Awareness Program [WEAP]) for all persons employed or otherwise working in the Project area shall be administered before performing impacts. The WEAP shall consist of a presentation from the Designated Biologist that includes a discussion of the biology and status of western Joshua tree, burrowing owl, and loggerhead shrike; and other biological resources mitigation measures described in the CEQA document .

Interpretation for non-English-speaking workers will be provided, and the same instruction shall be provided to any new workers before they are authorized to perform work in the Project area. Upon completion of the WEAP, employees shall sign a form stating they attended the program and understand all protection measures. This training shall be repeated at least once annually for long- term and/or permanent employees who will be conducting work in the Project area.

MM-BIO-6 Construction Monitoring Notebook . The Designated Biologist shall maintain a construction - monitoring notebook on site throughout the construction period, which shall include a copy of the biological resources mitigation measures with attachments and a list of signatures of all personnel who have successfully completed the education program. The permittee shall ensure that a copy of the construction monitoring notebook is available for review at the Project site upon request by the California Department of Fish and Wildlife.

MM-BIO-7 Delineation of Property Boundaries . Before beginning activities that would cause impacts, the contractor shall, in consultation with the Designated Biologist, clearly delineate the boundaries, consistent with the grading plan, within which the impacts will take place with fencing, stakes, or flags. All impacts within the fenced, staked, or flagged areas shall be avoided and all fencing, stakes, and flags shall be maintained until the completion of impacts in that area.

MM-BIO-8 Hazardous Waste. The Applicant shall immediately stop work and, pursuant to pertinent state and federal statutes and regulations, arrange for repair and clean up by qualified individuals of any fuel or hazardous waste leaks or spills at the time of occurrence, or as soon as it is safe to do so.

MM-BIO-9 Herbicides. The Applicant shall limit herbicide use for invasive plant species and shall use herbicides only it has been determined that hand or mechanical efforts are infeasible. To prevent drift, the permittee shall apply herbicides only when wind speeds are less th an 7 miles per hour.

All herbicide application shall be performed by a licensed applicator and in accordance with all applicable federal, state, and local laws and regulations.

MM-BIO-10 Pre-Construction Surveys for Burrowing Owl and Avoidance. One pre‐construction burrowing owl clearance survey shall be completed no more than 14 days before initiation of site preparation or grading activities, and a second survey shall be completed within 24 hours of the start of site preparation or grading activities. If ground-disturbing activities are delayed or suspended for more than 30 days after the pre -construction surveys, the Project site shall be resurveyed. Surveys for burrowing owl shall be conducted in accordance with protocols established in the Staff Report on Burrowing Owl Mitigation (CDFW 2012) or current version.

Page 70 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
45 March 2022
If burrowing owls are detected, disturbance to burrows shall be avoided during the nesting season (February 1 through August 31). Buffers will be established around occupied burrows in accordance with guidance provided in the Staff Report on Burrowing Owl Mitigation (CDFW 2012) or current version. No Project activities shall be allowed to encroach into established buffers without the consent of a monitoring biologist. The buffer shall remain in pl ace until it is determined that occupied burrows have been vacated or the nesting season has completed.

Outside of the nesting season, passive owl relocation techniques approved by the California Department of Fish and Wildlife (CDFW) shall be implemented. Owls shall be excluded from burrows in the immediate Project area and within a buffer zone by installing one -way doors in burrow entrances. These doors will be placed at least 48 hours prior to ground -disturbing activities.

Compensatory mitigation for permanent loss of owl habitat will be provided following the guidance in the Staff Report on Burrowing Owl Mitigation (CDFW 2012) or current version. The Project area shall be monitored daily for one week to confirm owl departure from burrows prior to any g round- disturbing activities.

Where possible, burrows will be excavated using hand tools and refilled to prevent reoccupation.

Sections of flexible plastic pipe shall be inserted into the tunnels during excavation to maintain an escape route for any wildlife inside the burrow.

See Burrowing Owl Relocation Plan for more details on avoidance buffers and relocation methods.

MM-BIO-11 Lighting . Lighting for construction activities and operations within 50 feet of the outside edge of the impact footprint containing habitat for special -status wildlife will be directed away from natural areas.

MM-BIO-12 Trash and Debris. The following avoidance and minimization measures shall be implemented during project construction.
(1) Fully covered trash receptacles that are animal-proof will be installed and used by the operator to contain all food, food scraps, food wrappers, beverage containers, and other miscellaneous trash. Trash contained within the receptacles will be removed at least once a week from the Project site.
(2) Construction work areas shall be kept clean of debris, such as cable, trash, and construction materials. All construction/contractor personnel shall collect all litter, vehicle fluids, and food waste from the Project site on a daily basis.

MM-BIO-13 Restoration of Temporary Impacts. Site construction areas subjected to temporary ground disturbance shall be recontoured to natural grade (if the grade was modified during the temporary disturbance activity), and revegetated with an application of a native seed mix, if necessary, prior to or during seasonal rains to promote passive restoration of the area to pre-project conditions. An area subjected to “temporary” disturbance means any area that is disturbed but will not be subjected to further disturbance as part of the Project. This measure does not apply to areas that are disturbed habitat and urban/developed lands. Prior to seeding temporary ground disturbance areas, the Designated Biologist will review the seeding palette to ensure that no seeding of invasive plant species, as identified in the most recent version of the California Invasive Plant Inventory for the region, will occur.

Page 71 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
46 March 2022
MM-BIO-14 Pre-Construction Survey for American Badger and Desert Kit Fox and Avoidance. A pre-construction survey for American badger and desert kit fox shall be conducted in suitable habitat areas on the Project site and Off -Site Utilities Alignments within 10 days prior to the start of construction to determine the presence/absence of either species. If ei ther species is discovered during the survey, an American Badger/Desert Kit Fox Mitigation and Monitoring Plan shall be developed as recommended by the California Department of Fish and Wildlife (CDFW) in their Notice of Preparation comment letter dated December 19, 2019. The Mitigation and Monitoring Plan shall include avoidance and minimization measures to reduce potential impacts to either species, as well as compensatory mitigation to offset direct or indirect impacts. The plan will be developed in consultation with CDFW. At a minimum, the plan shall:
• Identify pre-construction survey methods for American badger and desert kit fox • Describe feasible pre-construction and construction-phase avoidance methods • Describe pre-construction and construction-phase relocation methods, including the possibility for passive relocation
• For burrows that will not be impacted by the Project, identify an appropriate construction exclusion zones for both active and natal burrows
• Coordinate survey findings prior to and dur ing construction to meet the information needs of wildlife health officials in monitoring the health of kit fox populations MM-BIO-15 Pre-Construction Nesting Bird Surveys and Avoidance. Construction activities shall avoid the migratory bird nesting season (typically February 1 through August 31), to reduce any potential significant impact to birds that may be nesting on the survey area. If construction activities must occur during the migratory bird nesting season, an avian nesting survey of the Project si te and within 500 feet of all impact areas must be conducted to determine the presence/absence of protected migratory birds and active nests. The avian nesting survey shall be performed by a qualified wildlife biologist within 72 hours prior to the start of construction in accordance with the MBTA (16 USC 703–712) and California Fish and Game Code Sections 3503, 3503.5, and 3513.

If an active bird nest is found, the nest shall be flagged and mapped on the construction plans along with an appropriate buffer established around the nest, which will be determined by the biologist based on the species’ sensitivity to disturbance (typically 300 feet for passerines and 500 feet for raptors and special-status species). The nest area shall be avoided until the nest is vacated and the juveniles have fledged. The nest area shall be demarcated in the field with flagging and stakes or construction fencing. On -site construction monitoring shall also be conducted when construction occurs in close proximately to an active nest buffer. No Project activities may encroach into established buffers without the consent of a monitoring biologist. The buffer shall remain in place until is determined the nestlings have fledged and the nest is no longer considered active.

MM-BIO-16 Jurisdictional Waters of the State Mitigation. To the extent practicable, the Project shall be designed to avoid impacts to the jurisdictional waters of the state within the Project site, and the following avoidance/minimization measures shall be implemented:

If jurisdictional waters cannot be avoided, minimization measures shall be applied and all necessary resource agency permits shall be obtained. This may include Waste Discharge Requirements from the Regional Water Quality Control Board (RWQCB) and a Streambed Alteration Agreement from the California Department of Fish and Wildlife (CDFW).

Page 72 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
47 March 2022
All temporary impacts to state-jurisdictional waters will be restored on site. Restoration will include recontouring and erosion control with a native seed mix. Prior to seeding temporary ground disturbance areas, the Designated Biologist will review the seeding palette to ensure that no seeding of invasive plant species, as identified in the most recent version of the California Invasive Plant Inventory for the region, will occur.

Compensatory mitigation for permanent impacts shall occur either off site, at a mitigation bank, or with an in-lie fee program and would occur at a ratio not less than 1:1 for the impact to jurisdictional waters or at a ratio determined in the jurisdictional waters permits. If a mitigation bank or in -lieu fee program is not utilized and the Applicant proceeds with off-site mitigation, a waters mitigation and monitoring plan shall be prepared that outlines the compensatory mitigation in coordination with the RWQCB and CDFW. Mitigation lands shall be comprised of drainages simi lar to those impacted. Off‐site mitigation lands shall be preserved through a conservation easement and the waters mitigation and monitoring plan shall identify an approach for funding assurance for the long‐ term management of the conserved land. Suitable mitigation lands provided for species and vegetation communities may be used for jurisdictional waters of the state mitigation.

2.3.3.3 Findings Per CEQA Guidelines
Consistent with the CEQA Guidelines Section 15126.4(a)(1), feasible measures that can mini mize significant adverse impacts were developed for the potentially significant impacts described in Section 2.3.3.1. These feasible measures, MM-BIO-1 through MM-BIO-16, are listed in Section 2.3.3.2.

The City finds that these mitigation measures are feas ible, are adopted, and will reduce the potential biological resources impacts of the proposed project to less than significant levels. Accordingly, the City finds that, pursuant to CEQA Section 21081(a)(1) and CEQA Guidelines Section 15091(a)(1), changes or alterations have been required in, or incorporated into, the proposed project that mitigate or avoid potentially significant biological‐related impacts of the proposed project identified in the Final EIR.

2.3.3.4 Facts in Support of the Findings Related to Biological Resources Implementation of MM-BIO-1 through MM-BIO-16 would reduce potentially significant impacts related to biological resources to a less than significant level. There would be no significant, unavoidable impacts related to biological resources after implementation of these mitigation measures.

2.3.4 Cultural Resources

2.3.4.1 Potentially Significant Impacts to Cultural Resources Historical Resources
A cultural resources records search, a review of historic period aerial ph otographs and maps, and a field survey were conducted for the Project site. Previously-documented historic period cultural resources were identified within the Project site, along with a number of undocumented resources of the same era. The majority of pre viously documented resources are related to the transportation -related use of the greater Project area, as noted in a

Page 73 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
48 March 2022
previously conducted cultural resources assessment for another project located in the broader Project area (Pollock and Becker 2006):

This portion of the Mojave Desert has been a transportation corridor for more than a hundred years.

During that time, numerous roads have been created, used, and abandoned. Some of these roads were important links between communities, such as the Old Spanish Trail, whereas others were shortcuts or other seldom -used routes. During the mid - to late-twentieth century and up to the current day, abandoned road sections were frequently used for illegal refuse dumping, and the sites found during our survey probably r esulted from such activities. The early - to mid-twentieth century also saw an increase in the popularity of the desert, as the number of amateur prospectors increased during the Depression and again after World War II. More recently, the desert has been an off-road vehicle use and target shooting area. Typically, these recreational activities occur on weekends, with the participants camping for one or two nights and discarding their camp debris at the campsite. Many of the recent refuse deposits reflect this kind of activity.” As the newly recorded resources are predominantly similar to those previously documented (historic period refuse), the above assessment applies to them as well. With the exception of a fragment of the Old Spanish Trail/Salt Lake- Santa Fe Trail, which was determined to lack integrity and is not a contributing element to the resource, none of the potential historic resources sites within the Project area is associated with any known historical events or important persons. They are typical examples of isolated historic -period refuse deposits with no specific associations and fail to meet the CEQA criteria of “historical resources” or “unique archaeological resources,” and their cultural resources value has been exhausted by previous and current documentation. Overall, the potential of the Project to affect previously recorded or currently undocumented historic resources of significance on the Project site is low.

In regard to the Off-Site Utilities Alignments, a cultural resources records search, a review of historic period aerial photographs and maps, and intensive field survey were conducted for the routes of the Off-Site Utilities Alignments.

No historic resources associated with these Off -Site Utilities Alignments were identified during these efforts; however, potential historical resources were observed that are in the vicinity of the proposed Off -Site Utilities Alignments. The conceptual plans for these off-site utilities has been reviewed and construction of these utilities is not proposed to intersect these potential historical resources and the Project would not impact these resources; as such, no formal recordation or evaluation of the potential historical resources was conducted.

These potential historic resources are similar to other the resources previously observed, recorded, and evaluated on and near the Project site (i.e., isolated historic -period and modern -era refuse deposits with no specific associations). Because the significance of these potential historic resources has ye t been determined, should construction of the Off -Site Utilities Alignments ultimately require equipment and activities to come into close proximity or traverse the locations of the potential historic resources, there would be a potential for construction activities to impact the potential historic resources. As a result, to ensure that impacts to potential historic resources remain less than significant, implementation of MM -CUL-1 and MM-CUL-2 shall be required. With incorporation of MM-CUL-1 and MM-CUL-2, impacts associated with potential historic resources within and adjacent to the Off -Site Utilities Alignments would be less than significant.

Archaeological Resources
A cultural resources record search, a review of historic period aerial photographs and maps, and a field survey were conducted for the Project site and Off-Site Utilities Alignments. The records search included a review of all recorded

Page 74 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
49 March 2022
historic and prehistoric archaeological sites within one mile of the Project. Despite the presence of minor prehistoric resources within a mile of the Project site and Off-Site Utilities Alignments, the Project site has been surveyed twice over the course of approximately a decade with no trace of any prehistoric resources identified. In addition, a survey of the Off-Site Utilities Alignments did not reveal or indicate the presence of any archaeological resources. As a result of these findings, the potential of the Project to affect previously undocumented/unknown significant archaeological resources is low. How ever, it is impossible to completely rule out the presence of archaeological resources within the Project site. For this reason, the Project site should be treated as potentially sensitive for archaeological resources, and MM -CUL-1 through MM -CUL-3 is requ ired to reduce potential impacts to unanticipated archaeological resources. With incorporation of MM-CUL-1 through MM-CUL-3, impacts associated with archaeological resources would be less than significant.

Disturbance of Human Remains
A cultural resources records search, a review of historic period aerial photographs and maps, and a field survey were conducted for the Project site. These activities did not provide any indication that human remains could be located within the Project site. However, in the u nlikely event that human remains are encountered, California Health and Safety Code Section 7050.5 states that no further disturbance shall occur until the County Coroner has made a determination of origin and disposition pursuant to PRC Section 5097.98, p ursuant to MM -CUL-4. The County Coroner must be notified of the find immediately. If the remains are determined to be Native American, the County Coroner will notify the NAHC, which will determine and notify an MLD. With the permission of the landowner or his/her authorized representative, the MLD may inspect the site of the discovery. The MLD shall complete the inspection within 48 hours of notification by the NAHC. The MLD will have the opportunity to offer recommendations for the disposition of the remains. With incorporation of MM-CUL-4, impacts associated with human remains would be less than significant.

Cumulative Cultural Resources Impact
The geographic scope of the cumulative cultural resources analysis is the region surrounding the Project site.

Ongoing development and growth in the broader Project area may result in a cumulatively significant impact to cultural resources due to the conti nuing disturbance of undeveloped areas, which could potentially contain significant, buried archaeological resources. However, as discussed above, the individual, Project -level impacts associated with cultural resources were found to be less than significant with incorporation of mitigation measures (MM-CUL-1 through MM-CUL-4). The Project would be required by law to comply with all applicable federal, state, and local requirements related to historical and archaeological resources. Other related cumulative projects would similarly be required to comply with all such requirements and regulations, to be consistent with the provisions set forth by CEQA and the CEQA Guidelines, and to implement all feasible mitigation measures should a significant project-related and/or cumulative impact be identified. As such, cumulative impacts would be less than significant with mitigation incorporated.

2.3.4.2 Mitigation Measures
MM-CUL-1 Prior to start of ground-disturbing activities, a qualified archaeologist meeting the Secretary of the Interior’s Professional Qualifications Standards for archaeology (or an archaeologist working under the direct supervision of the qualified archaeologist) shall be retained by the Project Applicant and shall conduct cultural resources sens itivity training for all construction personnel. Construction personnel shall be informed of the types of archaeological resources that may be encountered, the proper procedures to be enacted in the event of an inadvertent discovery of archaeological

Page 75 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
50 March 2022
resources or human remains, and safety precautions to be taken when working with archaeological monitors. The construction contractor shall ensure that construction personnel are made available for and attend the training and retain documentation demonstrating attendance.

MM-CUL-2 If construction of the Off -Site Utilities Alignments requires deviation from the routes and disturbance footprints shown in the conceptual plans for these off-site utilities (domestic water and sanitary sewer), and thus, results in increased potential for construction equipment and activities to come into close proximity or to traverse the locations of the potential historic resources observed in the vicinity of the Off-Site Utilities Alignments, a historic resources survey shall be conducted by a qualified historic resources expert to determine the significance of these potential resources.

The survey shall entail the taking of detailed notes and photographs of potential resources, including documentation of character defining features, spatial relationships, and overall existing conditions of the resources. The potential historic resources shall be recorded on State of California Department of Parks and Recreation Series 523 Forms (DPR forms), and will be evaluated in consideration of National Register of Historic Places and California Register of Historic Resources designation criteria and integrity requirements. Archival research, as applicable, shall also be conducted to develop the appropriate historic context for the potential historic resources. The findings of this evaluation shall be included in a historic resources report. If the resources are found to be historically significant and/or eligible for listing pursuant to National Register of Historic Places and California Register of Historic Resources designation criteria, and if avoidance of these resources and redesign of the off-site utilities is deemed infeasible, the report shall include detailed procedures to the City and Project Applicant on how to minimize effects to these resources to acceptable levels of significance, and these recommendations must be implemented by the Project Applicant.

This requirement shall be noted on all grading plans, and the construction contractor shall be obligated to comply with the note.

MM-CUL-3 If archaeological resources (sites, features, or artifacts) or tribal cultural resources are exposed during construction activities, all construction work occurring within 100 feet of the find shall immediately stop until a qualified archaeologist, meeting the Secretary of the Interior’s Professional Qualification Standards, can evaluate the significance of the find and determine whether or not additional study is warranted. Additionally, the San Manuel Band of Mission Indians Cultural Resources Depar tment (SMBMI) shall be contacted regarding any pre -contact finds and be provided information after the archaeologist makes his/her initial assessment of the nature of the find, so as to provide Tribal input with regards to significance and treatment.

Construction activities may continue on other parts of the Project site while evaluation occurs. If the find is determined by the archaeologist to constitute a potentially significant archaeological resource, time allotment sufficient to allow for implementatio n of avoidance measures shall be made available. In accordance with CEQA Guidelines Section 15064.5(f) and/or California Public Resources Code, Sections 21083.2(b), if the discovery proves significant under the California Environmental Quality Act (CEQA), a treatment and monitoring plan shall be prepared by a qualified archaeologist for the resource(s), in coordination with SMBMI. The drafts of the treatment and monitoring plan shall be provided to SMBMI for review and comment. All subsequent finds shall be subject to the treatment and monitoring plan. The treatment and monitoring plan shall allow for a

Page 76 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
51 March 2022
monitor to be present that represents SMBMI for the remainder of the Project, should SMBMI elect to place a monitor on site.

Treatment may include preservati on in place or implementation of archaeological data recovery excavations to remove the resource along with subsequent analysis. Any archaeological material that is not Native American in origin shall be curated at a public, non -profit institution with a research interest in the material. If the find is Native American in origin, the tribe(s) that consider the Project area to be within their ancestral land or traditional use area, including the SMBMI, shall be contacted by the City of Hesperia to coordinate treatment and curation.

Any and all archaeological/cultural documents created as a part of the Project (isolate records, site records, survey reports, testing reports, etc.) shall be supplied by the Project Applicant and City of Hesperia for dissemination to SMBMI. The City of Hesperia and/or Project Applicant shall, in good faith, consult with SMBMI throughout the life of the Project.

This requirement shall be noted on all grading plans, and the construction contractor shall be obligated to comply with the note.

This requirement shall be noted on all grading plans, and the construction contractor shall be obligated to comply with the note.

MM-CUL-4 In accordance with Section 7050.5 of the California Health and Safety Code, if human remains are found, the county coroner shall be immediately notified of the discovery. No further excavation or disturbance of the site or any nearby area reasonably suspected to overlie adjacent remains shall occur until the county coroner has determined, within 2 working days o f notification of the discovery, the appropriate treatment and disposition of the human remains. If the county coroner determines that the remains are, or are believed to be, Native American, he or she shall notify the Native American Heritage Commission (NAHC) in Sacramento within 24 hours. In accordance with California Public Resources Code, Section 5097.98, the NAHC must immediately notify those persons it believes to be the most likely descendant of the deceased Native American. The most likely descendant shall complete her/his inspection within 48 hours of being granted access to the site. The designated Native American representative shall then determine, in consultation with the property owner, the proper disposition of the human remains.

This requirement shall be noted on all grading plans, and the construction contractor shall be obligated to comply with the note.

2.3.4.3 Findings per CEQA Guidelines
Consistent with CEQA Guidelines Section 15126.4(a)(1), feasible measures that can minimize significant adverse impacts were developed for the potentially significant impacts described in Section 2 .3.4.1. These feasible measures, MM-CUL-1 through MM-CUL-4, are listed in Section 2.3.4.2.

The City finds that these mitigation measures are feasible, are adopted, and will reduce the potential cultural resources impacts of the proposed project to less than significant levels. Accordingly, the City finds that, pursuant to CEQA Section 21081(a)(1 ) and CEQA Guidelines Section 15091(a)(1), changes or alterations have

Page 77 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
52 March 2022
been required in or incorporated into the proposed project that will mitigate or avoid potentially significant impacts on cultural resources.

2.3.4.4 Facts in Support of the Findings Related to Cultural Resources Implementation of MM -CUL-1 through MM -CUL-4 would reduce potentially significant impacts related to cultural resources to a less than significant level. There would be no significant, unavoidable impacts related to cultural resources after implementation of these mitigation measures.

2.3.5 Geology and Soils

2.3.5.1 Potentially Significant Impacts to Geology and Soils Unique Paleontological Resource or Site or Unique Geologic Feature The City encompasses a wide variety of geologi cal formations that differ in age and fossil -bearing sensitivity. The Project site, however, is overlain by Holocene age deposits. Late Quaternary (late Holocene, or “modern”) alluvium and alluvial fan deposits are generally considered to be too young geologically to contain significant nonrenewable paleontological resources (i.e., fossils) and are typically assigned a low paleontological sensitivity. Additionally, the Technical Background Report in Support of the Cultural Resource Element: City of Hesperia General Plan Update (City of Hesperia 2010b) determined that the Project site has a low paleontological sensitivity.

Despite the low potential for paleontological resources to occur on the Project site, it is always possible that intact fossil deposits are present at subsurface levels and could be uncovered during ground-disturbing activities. As such, MM-CUL-5 is required, which would ensure that if paleontological resources (sites, features, or fossils) are exposed during construction activities, all construction work occurring within the vicinity of the find would stop until a qualified paleontologist can evaluate the significance of the find and determine whether or not additional study is warranted.

With incorporation of MM-CUL-5, impacts associated with paleontological resources would be less than significant.

2.3.5.2 Mitigation Measures
MM-CUL-5 If paleontological resources (sites, features, or fossils) are exposed during Project construction activities, all construction work occurring within 100 feet of the find shall immediately stop until a qualified paleontologist can evaluate the significance of the find and determine whether or not additional study is warranted. If the discovery proves significant under the California Environmental Quality Act, discovered fossils or samples of such fossils shall be collected and identified by the qualified paleontologist. Significant specimens recovered shall be properly recorded, treated, and donated to the San Bernardino County Museum, Division of Geological Sciences, or other repository with permanent retrievable paleontological storage. A final report shall be prepared and submitted to the City of Hesperia that itemizes any fossils recovered, with maps to accurately record the original location of recovered fossils and evidence that the resources were curated by an established museum repository.

This requirement shall be noted on all grading plans, and the construction contractor shall be obligated to comply with the note.

Page 78 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
53 March 2022

2.3.5.3 Findings per CEQA Guidelines
Consistent with CEQA Guidelines Section 15126.4(a)(1), feasible measures that can minimize significant adverse impacts were developed for the potentially significant impacts described in Section 2.3.5.1. This feasible measure, MM-CUL-5, is listed in Section 2.3.5.2.

The City finds that th is mitigation measures is feasible, is adopted, and will reduce th e potential paleontological impacts of the proposed project to less than significant levels. Accordingly, the City finds that, pursuant to CEQA Section 21081(a)(1) and CEQA Guidelines Section 15091(a)(1), changes or alterations have been required in or incorporated into the proposed project that will mitigate or avoid potentially significant impacts on geology and soils.

2.3.5.4 Facts in Support of the Findings Related to Geology and Soils Implementation of MM-CUL-5 would reduce potentially significant impacts related to paleontological resources to a less than significant level. There would be no significant, unavoidable impacts related to geology and soils after implementation of these mitigation measures.

2.3.6 Hazards and Hazardous Materials

2.3.6.1 Potentially Significant Impacts to Hazards and Hazardous Materials Routine Transport, Use, or Disposal of Hazardous Materials During construction, a variety of hazardous substances and wastes would be stored, used, and generated on the Project site, including fuels for machinery and vehicles, new and used motor oils, cleaning solvents, paints, and storage containers. Accidental spills, leaks, fires, explosions, or pressure releases involving hazardous materials represent a potential threat to human health and the environment if not properly treated. Provisions to properly manage hazardous substances and wastes during construction are typically included in construction specifications and are under the responsibility of th e construction contractors. For example, construction contractors would be required to comply with Cal/OSHA regulations concerning the use of hazardous materials, including requirements for safety training, exposure warnings, availability of safety equipme nt, and preparation of emergency action/prevention plans. Adherence to the construction specifications and applicable regulations regarding hazardous materials and hazardous waste, including disposal, would ensure that construction of the Project would not create a significant hazard to the public or the environment during the construction phase of the Project.

Based on observed soil staining associated with on-site full and partially full motor oil canisters and used tire piles, shallow soil impacts may be encountered during Project construction. MM-HAZ-1 requires the removal and disposal of on-site tires and oil containers (e.g., retail motor oil containers and commercial oil drums) from the Project area in accordance with all applicable local, state, and federal guidelines. For excavation and grading activities that occur in areas with the potential for residual contamination, a qualified environmental professional shall screen soils in the identified area prior to excavation and grading based on the nature of the potential contamination. In the event that potential contamination is encountered, the contamination shall be evaluated by a qualified environmental professional using the appropriate collection and sampling techniques as determined by the enviro nmental professional based on the nature of the contamination. The nature and extent of contamination shall be determined and the appropriate handling, disposal, and/or treatment shall be implemented in accordance with applicable regulatory requirements.

Page 79 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
54 March 2022
Furthermore, adherence to all emergency response plan requirements set forth by the San Bernardino County Fire Department would be required throughout the duration of Project construction. Therefore, based on compliance with existing regulations and with incorporation of MM-HAZ-1, short-term construction impacts associated with the routine transport, use, or disposal of hazardous materials would be less than significant.

Upon completion of Project construction, the Project would involve the operation and ma intenance of the industrial/warehouse facilities. Operation of the Project would likely involve the use of industrial -grade chemicals used in the day-to-day operation of the facilities as well as commercially available cleaning products, landscaping chemicals and fertilizers, and various other commercially available products. While these materials could be stored on the Project site, storage would be required to comply with the guidelines established by the manufacturer’s recommendations. Consistent with federal, state, and local requirements, the transport, removal, and disposal of hazardous materials from the Project site would be conducted by a permitted and licensed service provider. Any handling, transport, use, or disposal must comply with all applicab le federal, state, and local agencies and regulations, including the USEPA, DTSC, CAL/OSHA, RCRA, and the San Bernardino County Fire Department.

Although the future tenants are not known yet, in the event that a future tenant’s operations require them to transport, use, or dispose of quantities of hazardous materials identified by the state, pursuant to the Health and Safety Code and in accordance with the San Bernardino County Fire Department’s CUPA requirements, the owner/operator must complete and submit a Hazardous Materials Business Plan to the California Environmental Reporting System. A Hazardous Materials Business Plan is a document containing detailed information on the inventory of hazardous materials at a facility; emergency response plans and procedures in the event of a reportable release or threatened release of a hazardous material; training for all new employees and annual training, including refresher courses, for all employees in safety procedures in the event of a release or threatened rel ease of a hazardous material; and a site map that contains north orientation, loading areas, internal roads, adjacent streets, storm and sewer drains, access and exit points, emergency shutoffs, evacuation staging areas, hazardous material handling and storage areas, and emergency response equipment. The Hazardous Materials Business Plan intends to provide basic information necessary for use by first responders to prevent or mitigate damage to the public health and safety and the environment from a release or threatened release of hazardous materials, as well as to satisfy federal and state Community Right -To-Know laws. Therefore, long -term operational impacts associated with the routine transport, use, or disposal of hazardous materials would be less than significant.

In summary, the Project would result in potentially significant impacts with regard to the creation of a significant hazard to the public or the environment through the routine transport, use, or disposal of hazardous materials. MM- HAZ-1 would be implemented, and Project impacts would be less than significant with mitigation incorporated.

Release of Hazardous Materials and the Potential for Upset Conditions During construction, hazardous materials such as fuels and lubricants would be transported to and used on site in construction vehicles and equipment. Construction waste is a potential pollutant source of concern for the Oro Grande Wash and Mojave River, which are located hydrologically down gradient of the Project site. Concrete, paint, and other materials that are also used on construction sites are major contributors to polluted habitats, in the event that such materials exit a construction site. However, the potential for the use of these materials to result in significant hazards to the public or the environment would be low for the reasons described below.

The Project contractor and construction crews would be required to comply with all applicable regulations governing the storage, handling, and disposal of hazardous materials and waste. As discussed in Section 4.8, Hydrology and Water Quality, prior to issuance of grading permits, the City of Hesperia requires the submittal, review, and approval

Page 80 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
55 March 2022
of an Erosion and Sediment Control Plan. Implementation of an Erosion and Sediment Control Pl an would ensure that construction -related BMPs are enacted to prevent, to the maximum extent practicable, construction site pollutants from leaving the site during all phases of construction. The Project would also be required to comply with the NPDES MS4 Permit, including the regulation of surface water quality. Under the NPDES MS4 Permit, the development of 1.0 acre or more of land must file a notice of intent with the SWRCB to comply with the state NPDES General Construction Permit. Implementation of thi s Permit would require the development of a site -specific Stormwater Pollution Prevention Permit (SWPPP) for construction activities. The SWPPP is required to identify BMPs that protect stormwater runoff and ensure avoidance of substantial degradation of water quality. Typical BMPs that could be incorporated into the SWPPP to minimize the off-site runoff of pollutants would include the following:
• Diverting off-site runoff away from the construction site • Vegetating landscaped/vegetated swale areas as soon as feasible following grading activities • Using drop inlet protection (filters and sandbags or straw wattles), with sandbag check dams within paved areas • Implementing specifications for construction waste handling and disposal • Using contained equipment wash-out and vehicle maintenance areas • Training, including for subcontractors, on general site housekeeping Incorporation of required BMPs would help control the use of hazardous substances during construction and would minimize the potential for such substances to leave the site. As a result, there would be reduced potential for the public and environment to be exposed to hazardous chemicals and materials as a result of construction activities.

The implementation of applicable construction BMPs and adherence to applicable hazardous materials and waste regulations would minimize the risk and exposure of the release of hazardous materials to the public and environment to less than significant levels.

Based on the Phase I ESA Report, on -site RECs we re identified, consisting of motor oil containers and used automotive tires along the east and northwest portions of the Project site. Multiple (50+) 5 -gallon buckets and 5- quart jugs labeled as containing motor oil were observed in these areas. The contai ners were observed to be full, partially full, or empty and several areas of stained soil were observed stemming from these containers.

Project grading and excavation could encounter soils impacted by petroleum hydrocarbons, resulting in potentially significant health and safety impacts to construction personnel, as well as potential off-gassing of petroleum from impacted soil excavations and associated soil stockpiles. However, MM-HAZ-1 would require the removal and disposal of on-site tires and oil containers (e.g., retail motor oil containers and commercial oil drums) from the Project area in accordance with all applicable local, state, and federal guidelines. For excavation or grading activities that occur in areas with the potential for residual contamination, a qualified environmental professional shall screen soils in the identified area prior to excavation and grading activities based on the nature of the potential contamination. If potential contamination is encountered, the contamination shall be evaluated by a qualified environmental professional using the appropriate collection and sampling techniques as determined by the environmental professional based on the nature of the contamination. The nature and extent of contamination shall be determined and the appropriate handling, disposal, and/or treatment shall be implemented in accordance with applicable regulatory requirements.

Therefore, based on compliance with applicable regulations and with the incorporation of MM -HAZ-1, short-term construction impacts associated with creating a significant hazard to the public or the environment through reasonably foreseeable upset and accident conditions would be less than significant.

Upon completion of Project construction, routine operation of the Project would involve likely use industrial grade chemicals used in the operation of the facilities as well as commercially available cleaning products, landscaping

Page 81 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
56 March 2022
chemicals and fertilizers, and various other commercially available products. These materials would be used for the day-to-day operation of the facilities and may involve the use of hazardous materials.

As previously discussed above, the future tenants are not known yet. In the event that a future tenant’s operations require them to transport, use, or dispose of quantities of hazardous materials identified by the state, pursuant to the Health and Safety Code and in accordance with the San Bernardino County Fire Department’s CUPA requirements, the owner/operator must complete and submit a Hazardous Mater ials Business Plan to California Environmental Reporting System. Completion of a Hazardous Materials Business Plan would ensure that an emergency spill response and containment plan is in place in the event of hazardous spills.

Furthermore, the use, stora ge, and transport of hazardous materials and wastes would be subject to applicable federal, state, and local health and safety regulations (e.g., RCRA and the Hazardous Waste Control Act “cradle to grave” requirements). All hazardous materials generated an d/or used on the Project site would be managed in accordance with all relevant federal, state, and local laws, including the California Hazardous Waste Control Law (California Health and Safety Code Division 20, Chapter 6.5) and the Hazardous Waste Control Regulations (22 CCR

4.5). Moreover, compliance with CAL/OSHA workplace and work practices requirements would avoid the exposure of persons and the environment to hazardous materials.

In addition to the regulations and practices described above, the following requirements would apply to storage and handling of hazardous wastes at the Project site: (1) hazardous materials are required to be stored in designated areas designed to prevent accidental release in accordance with state law, including the Californi a Hazardous Waste Control Act and the California Health and Safety Code; (2) CAL/OSHA requirements prescribe safe work environments for workers working with materials that present a moderate explosion hazard, high fire or physical hazard, or health hazard; (3) federal and state laws related to the storage of hazardous materials would be complied with to maximize containment and provide for prompt and effective clean-up in case of an accidental release; and (4) Hazardous Materials Inventory and Response Planning Reports would be filed with the City in accordance with Unified Program Permit requirements.

Compliance with applicable regulations involving hazardous materials during operation would ensure that such materials are transported, used, stored, and dis posed of in a manner that minimizes the potential for upset and accident conditions resulting in the release of hazardous materials into the environment. Due to the existing regulations that are required, it is not expected that the Project would create a significant hazard to the public or the environment through reasonably foreseeable upset and accident conditions. Therefore, based on compliance with applicable regulations, long-term operational impacts associated with creating a significant hazard to the public or the environment through reasonably foreseeable upset and accident conditions would be less than significant.

In summary, the Project would result in potentially significant impacts with regard to the creation of a significant hazard to the publ ic or the environment through reasonably foreseeable upset and accident conditions involving the release of hazardous materials into the environment. MM -HAZ-1 would be implemented, and Project impacts would be less than significant with mitigation incorporated.

Cumulative Hazards and Hazardous Materials Impacts
The geographic scope of the cumulative hazards and hazardous materials analysis is the immediate Project area, including surrounding land uses and other nearby properties. Adverse effects of hazards and hazardous materials tend to be localized; therefore, impacts from nearby projects would be limited, if any, and the Project site would be primarily affected by Project activities.

Page 82 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
57 March 2022
During construction, hazardous materials such as fuels and lubricants would be transported to and used on site in construction vehicles and equipment. In addition, Project excavations could encounter shallow soil contaminants as a result of on-site used motor oil containers and tires. These contaminants, if improperly handled, could expose the public environment to pollutants. However, water quality enhancement components of the Project, including the implementation of an Erosion and Sediment Control Plan, a SWPPP, stormwater BMPs, and MM-HAZ-1, would minimize the potential release of construction-related pollutants on and off site.

Post-development, routine operation of the Project would include the use of various hazardous materials, including chemical reagents, solvents, fuels, paints, and cleansers. These materials would be used for day-to-day operations as well as building and landscaping maintenance. However, compliance with applicable regulations involving hazardous materials during operation would ensure that such materials are transported, used, stored, and disposed of in a manner that minimizes the potential for upset and accident conditions resulting in the release of hazardous materials into the environment. In addition, the owner/operator must complete and submit a Hazardous Materials Business Plan to the California Environmental Reporting System. This would ensure that in the event that an emergency spill response and containment plan is in place in the event of hazardous spills. As such, it is not expected that the Project would create a significant hazard to the pu blic or the environment through routine operations or reasonably foreseeable upset and accident conditions or result in the release or exposure of hazardous materials into the environment. Therefore, cumulative hazards and hazardous materials impacts would be less than significant.

2.3.6.2 Mitigation Measures
MM-HAZ-1 Prior to the issuance of a grading permit, the Project Applicant shall retain a qualified environmental specialist that has documented experience in the identification, characterization, and removal of hazardous materials and includes a California licensed professional engineer, geologist, or hydrogeologist to remove and dispose of all refuse located on the Project site, including but not limited to, the illegally -dumped tires and oil containers currently found on site . The removal, transport, and disposal of refuse shall be done in accordance with all applicable local, state, and federal guidelines related to hazardous materials handling. Prior to the removal of refuse deposits from the site, the environmental specialist shall inspect each refuse pile for indications that the refuse may contain – or may have once contained – hazardous materials, including, but not limited to, motor oil, solvents, paints, and/or other petro leum products. In addition, the environmental specialist shall inspect the soils surrounding each refuse deposit for evidence of any contamination (staining) or volatilization of contaminants (odors).

If contamination indicators are identified, work shall stop in the immediate proximity of the potential contamination. The Project applicant and/or their construction contractor shall be responsible for engaging a qualified environmental specialist to design and perform an investigation to verify the presence and extent of contamination on the Project site. Subsurface investigation shall determine appropriate worker protection and hazardous material and disposal procedures appropriate for the Project site. Contaminated soil or groundwater determined to be hazardous shall be removed by personnel who have been trained through the Occupational Safety and Health Administration –recommended 40 -hour safety program with an approved plan for groundwater extractions, soil excavation, control of contaminant releases to the air, and off -site transport or on-site treatment.

Page 83 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
58 March 2022

2.3.6.3 Findings per CEQA Guidelines
Consistent with CEQA Guidelines Section 15126.4(a)(1), feasible measures that can minimize significant adverse impacts were developed for the potentially significant impacts described in Section 2.3.6.1. This feasible measure, MM-HAZ-1, is listed in Section 2.3.6.2.

The City finds that this mitigation measure is feasible, is adopted, and will reduce the potential hazardous impacts of the proposed project to less-than-significant levels. Accordingly, the City finds that, pursuant to CEQA Section 21081(a)(1) and CEQA Guidelines Section 15091(a)(1), changes or alterations have been required in or incorporated into the proposed project that will mitigate or avoi d potentially significant impacts on hazards and hazardous materials.

2.3.6.4 Facts in Support of the Findings Related to Hazards and Hazardous Materials
Implementation of MM -HAZ-1 would reduce potentially significant impacts related to hazards and hazardo us materials to a less than significant level. There would be no significant, unavoidable impacts related to hazardous and hazardous materials after implementation of this mitigation measure.

2.3.7 Tribal Cultural Resources

2.3.7.1 Potentially Significant Impacts to Tribal Cultural Resources Register of Historical Resources/Public Resource Code Section 5024.1 The Project is subject to compliance with AB 52 (PRC Section 21074), which requires consideration of impacts to “tribal cultural resources” as part of the CEQA process, and requires the City of Hesperia, as the CEQA lead agency, to notify any groups who have requested notification of proposed projects within the City and who are traditionally or culturally affiliated with the geographic area of the Project.

In May 2020, the City sent out AB 52 notification letters to three tribal representatives who had requested to be notified of proposed projects within the City. The City has received one response to the AB 52 notification letters from Jessica Mauck, Director of Cultural Resources Management of the San Manuel Band of Mission Indians (SMBMI), dated June 27, 2020. Ms. Mauck stated that the Project area exists within Serrano ancestral territory and, therefore, is of interest to the SMBMI. However, Ms. Mauck stated that due to the nature and location of the Project, and given the Cultural Resources Management Department’s present state of knowledge, the SMBMI does not have any concerns with implementation of the Project. Notwithstanding, because there is always the possibility of unexpected discovery of archaeological resources, Ms. Mauck requested that mitigation measures be implemented during Project construction to reduce potential impacts to tribal cultural resources to a less-than-significant level. The mitigation measures requested by the SMBMI have been incorporated into MM-CUL-3 and MM-CUL-4.

The Project site has been thoroughly researched, surveyed, and analyzed to identify the level of potential for archaeological and tribal cultural resources. No a rchaeological and tribal cultural resources were identified as a result of these efforts. Notwithstanding, MM-CUL-1 through MM-CUL-4 are required to help ensure the integrity of archaeological resources and human remains during ground -disturbing activities. With the incorporation of MM - CUL-1 through MM-CUL-4, impacts associated with tribal cultural resources would be less than significant.

Page 84 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
59 March 2022
Cumulative Tribal Cultural Resources Impacts
The geographic scope of the cumulative tribal cultural resources analysis is the region surrounding the Project site.

Ongoing development and growth in the broader Project area may result in a cumulatively significant impact to cultural resources due to the continuing disturbance of undeveloped areas, which could potentially co ntain significant, buried tribal cultural resources. However, as discussed above, the individual, Project -level impacts associated with tribal cultural resources were found to be less than significant with incorporation of mitigation measures (MM -CUL-1 thr ough MM -CUL-4). The Project would be required by law to comply with all applicable federal, state, and local requirements related to tribal cultural resources. Other related cumulative projects would similarly be required to comply with all such requirements and regulations, to be consistent with the provisions set forth by CEQA and the CEQA Guidelines, and to implement all feasible mitigation measures should a significant project-related and/or cumulative impact be identified. As such, cumulative impacts would be less than significant with mitigation incorporated.

2.3.7.2 Mitigation Measures
MM-CUL-1 through MM-CUL-4 can be found in Section 2.3.3.2 of Cultural Resources, above.

2.3.7.3 Findings per CEQA Guidelines
Consistent with CEQA Guidelines Section 15126.4(a)(1), feasible measures that can minimize significant adverse impacts were developed for the potentially significant impacts described in Section 2.3.7.1. These feasible measures, MM-CUL-1 through MM-CUL-4, are listed in Section 2.3.4.2.

The City finds that these mitigation measures are feasible, are adopted, and will reduce the potential tribal cultural resource impacts of the proposed project to less than significant levels. Accordingly, the City finds that, pursuant to CEQA Section 21081(a)(1) and CEQA Guidelines Section 15091(a)(1), changes or alterations have been required in or incorporated into the proposed project that will mitigate or avoid potentially significant impacts on tribal cultural resources.

2.3.7.4 Facts in Support of the Findings Related to Tribal Cultural Resources Through Assembly Bill 52 consultation with local tribes, additional mitigation measures addressing the potential to discover tribal cultural resources are also included to reduce potential impacts to archaeolo gical resources.

Implementation of MM-CUL-1 through MM-CUL-4 would reduce potentially significant impacts related to the register of historic resources and related to a resource determined to be significant pursuant to criteria set forth in subdivision (c) of Public Resources Code Section 5024.1 to a less than significant level. There would be no significant, unavoidable impacts related to tribal cultural resources after implementation of these mitigation measures.

2.4 Impacts Determined to Be Less Than Significant
Based on the analysis contained in the EIR, the following issue areas have been determined to fall within the “less than significant impact” category for all thresholds : agriculture and forestry resources, energy, hydrology and water quality, land use, mineral resources, population and housing, public services, recreation, utilities and service systems, and wildfire .

Page 85 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
60 March 2022
Other impacts under aesthetics, air quality, biological resources, geology and soils, greenhouse gas emissions, hazards and hazardous materials, noise, and transportation not addressed below are addressed in Section 2.2 and Section 2.3.

2.4.1 Aesthetics
Scenic Resource Damage within a State Scenic Highway
There are no officially designated scenic roads or highways within City boundaries (City of Hesperia 2010 c). The nearest designated state scenic highway, Route 38, is located approximately 34 miles southeast of the Project site.

The nearest eligible scenic highway, Route 138, is located 7 miles to the south of the Project site (Caltrans 2019).

Due to distance and intervening terrain, vegetation and development, none of these officially designated or eligible scenic highways are visible from the Project site, nor is the Project site visible f rom the highways. Therefore, no impacts associated with scenic resources within in a state scenic highway would occur.

Sources of Light or Glare
The Project site is currently undeveloped and does not support any existing sources of light or glare, and development of the Project would introduce new sources of light and glare to the Project site. However, developed portions of the City contain numerous sources of light and glare typical of urban and semi -rural environments.

Existing sources of light or glare include streetlights, freestanding lights, building -mounted lights, illuminated signage, reflective building materials, and vehicular headlights. The undeveloped portions of the City, such as the Project site, contain few, if any, sources of light and glar e. New sources of nighttime lighting resulting from the implementation of the Project include parking lot and loading area lighting, as well as building mounted lights. The Project would include a variety of exterior building light fixtures and parking lot lighting fixtures, including LED Type 3, 4, and 5 building mounted and pole mounted light fixtures. Additionally, building materials would primarily include concrete, metal, aluminum, and glass windows. These features could result in light trespass, light pollution, and glare to the neighboring light sensitive land uses, which include rural residential areas located north, west, east and south of the Project site.

The majority of construction activities associated with the Project would occur during daytime hours consistent with standard industry practices. In the event that work is required outside the standard construction hours (to reduce traffic or other impacts), lighting would be focused directly on work activity areas and would be temporary. As such, nighttime construction lighting impacts would be less than significant.

Upon Project implementation, the Project could potentially result in significant adverse light and glare impacts on nighttime views due to the addition of building and parking lot l ighting. However, the Project would be required to minimize light and glare impacts to sensitive land uses through the incorporation of setbacks, site planning, and other design techniques (consistent with General Plan Policy LU -3.5). Section 16.20.135 of the City’s Municipal Code contains general performance standards related to light and glare such that any industrial activity shall not cause light trespass above 0.5 footcandles when measured in a residential district or lot (City of Hesperia 2020).

According to the photometric plan prepared for the Project, Project lighting would result in light trespass of less than

0.2 footcandles along the entire Project perimeter. Therefore, the Project would not result in light trespass above

0.5 footcandles within any nearby residential areas.

Further, all light fixtures would be required to be consistent with the California Green Building Standards Code for illumination. The California Green Building Standards Code sets forth minimum requirements based on Lighting Zones, as defined in Chapter 10 of the California Administrative Code. The requirements are designed to minimize light pollution in an effort to maintain darks skies and ensure new development reduces backlight, uplight, and

Page 86 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
61 March 2022
glare (BUG) from exterior light sources (CALGreen 2019). The Project would be required to comply with the CALGreen BUG rating for Lighting Zone 3. Further, all lights would be shielded and directed downward, and the proposed lighting plan does not include blinking, flashing, or oscillating light sources.

The warehouse buildings would incorporate a variety of building materials. Building materials would primarily include concrete, metal, aluminum, and glass windows. Metal canopy overhangs for shading would be included above building entrances, and aluminum entrance fronts would include glass and metal attachments. Blue reflective glazing and high gloss paint is proposed for the entrance fronts and canopies. Glass windows would consist of tempered vision insulated glass with a solarban 60 rating, which has a low exterior reflectance percentage to maximize daylighting opportunities to interior building spaces. Although metallic materials and glass have been incorporated into Project design, Project setbacks and proposed landscaping would provide screening to screen such Project elements from view, and all paint finishes would be flat (with the exception of the high gloss proposed for entrance fronts and canopies). As such, building materials would not create a new source of substantial light or glare that would adversely affect day or nighttime views in the area. Therefore, based on compliance with the City’s Development Code and CALGreen lighting standards, impacts associated with light and glare would be less than significant.

Finding
The City finds that, based upon substantial evidence in the record, the proposed project would have a less than significant impact on aesthetics and visual resources as it relates to scenic resource damage within a state scenic highway and sources of light and glare; therefore, no mitigation is required.

2.4.2 Agriculture and Forestry Resources
Conversion of Agricultural Lands and Forestlands
According to the California Department of Conservation (CDOC) Important Farmland Finder (CDOC 2016a), the Project site is designated as “grazing land.” The Project site does not contain Prime Farmland, Unique Farmland, or Farmland of Statewide Importance ( collectively, “Important Farmland”). The Project would not occur within any farmland locations, and would not result in the conversion of this land to nonagricultural use. In addition, based on the CDOC’s 2015/2016 San Bernardino County Williamson Act map (CDOC 2016b), there are no Williamson Act contracts on site or within the Project area. Further, the Project site and surrounding area are not zoned for agricultural uses, but instead for commercial, industrial, business park, rural estate residential, and neighborhood commercial uses (City of Hesperia 2010a). As such, implementation of the Project would not conflict with existing zoning for agricultural use or land under a Williamson Act contract.

In regard to forestland or timberland, Project site is not located on or adjacent to forestland, timberland, or timberland zoned timberland production (City of Hesperia 2010a). Therefore, no impacts associated with Important Farmland, Williamson Act contracts/Farmland Security Zones, forestland, or timberland would occur.

Cumulative Agricultural and Forestry Resource Impacts
As analyzed above, the proposed project would experience no impacts related to all agricultural and forestry resource issue areas. Considering the proposed project would not be located on farmland or forestland, the proposed project would not combine with cumulative projects resulting in a significant impact to an agricultural or forestry resource.

Therefore, impacts to agricultural and forestry resources would not be cumulatively considerable.

Page 87 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
62 March 2022
Finding
The Initial Study for the proposed project found no potential for significant impacts to agriculture and forestry resources; therefore, agriculture and forestry resources was not addressed in the Draft EIR. No mitigation would be required and no significant, unavoidable adverse impacts would occur.

2.4.3 Air Quality
Expose Sensitive Receptors to Substantial Pollutant Concentrations Local Carbon Monoxide Concentrations
Mobile source impacts occur on two scales of motion. Regionally, Project -related travel would add to regional trip generation and increase vehicle-miles traveled within the local airshed and the MDAB. Locally, Project -generated traffic would be added to th e roadway system near the Project site. If such traffic occurs during periods of poor atmospheric ventilation, is composed of a large number of vehicles “cold -started” and operating at pollution - inefficient speeds, and is operating on roadways already crow ded with non-Project traffic, there is a potential for the formation of microscale CO hotspots in the area immediately around points of congested traffic. However, because of continued improvement in vehicular emissions at a rate faster than the rate of ve hicle growth and/or congestion, the potential for CO hotspots in the MDAB is steadily decreasing.

The MDAQMD thresholds of significance for local CO emissions is the 1 -hour and 8-hour CAAQS of 20 ppm and 9 ppm, respectively. By definition, these represent levels that are protective of public health. As noted previously, the MDAB is currently designated attainment for both state and national CO ambient air quality standards, and the City typically experiences low background CO concentrations.

To verify that the Project would not cause or contribute to a violation of the CO standard, a screening evaluation was conducted comparing the highest hourly traffic volumes at any studied intersection in proximity to the Project site to the 100,000 vehicles per day criterion from the SCAQMD AQMP (SCAQMD 2003). The highest average daily trips on a segment of road would be 61,500 daily trips on Interstate 15 Northbound Ramps and Main Street, which would be substantially less than the 100,000 vehicles per day screening cri terion applied. Therefore, impacts associated with CO hotspots would be less than significant.

Toxic Air Contaminant Exposure
As the Project consists of 2,361,648 square -feet of High-Cube Fulfillment Center use and 1,383,781 square-feet of General Light I ndustrial use, the potential impact of Project -generated air pollutant emissions at sensitive receptors has been evaluated.

Receptors in the Project study area include existing residences to the north, south, east, and west of the Project site, with the n earest residence at 11345 Phelan Road, approximately 217 feet south of the Project site. The residential land use with the greatest potential exposure to Project DPM source emissions is at the existing West Main Villas apartments as 9800 Mesa Linda Street, approximately 2,165 feet southeast of the Project site, and immediately adjacent to the north of Main Street, which is the Project’s primary truck travel route. While all of the residences surrounding the Project site have been accounted for in this analy sis, this analysis focuses on the residential land use with the greatest potential exposure to Project DPM source emissions, as any residences located further away from the Project site or primary truck travel route than the residence with the greatest potential for exposure would experience a lesser impact because concentrations dissipate with distance. The maximum

Page 88 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
63 March 2022
incremental cancer risk attributable to Project DPM source emissions at the MEIR is estimated at 7.37 in one million, which is less than the MD AQMD’s significance threshold of 10 in one million. At this same location, non - cancer risks were estimated to be 0.003, which would not exceed the applicable significance threshold of 1.0.

Because all other modeled residential receptors are exposed to lesser concentrations and are located at a greater distance than the MEIR, and DPM generally dissipates with distance from the source, all other receptors in the vicinity of the Project site would be exposed to less emissions and therefore less risk than the M EIR identified herein. Therefore, impacts associated with toxic air contaminants and cancer and non-cancer health risk would be less than significant.

Valley Fever
Valley Fever is not highly endemic to San Bernardino County; within San Bernardino County the incident rate is 1.8 cases per 100,000 people (CDPH 2017). In contrast, in 2016 the statewide annual incident rate was 13.7 per 100,000 people. The California counties considered highly endemic for Valley Fever include Kern (251.7 per 100,000), Kings (157.3 per 100,000), San Luis Obispo (82.8 per 100,000), Fresno (60.8 per 100,000), Tulare (45.3 per 100,000), Madera (31.5 per 100,000), and San Joaquin (25.3 per 100,000) and accounted for 70% of the reported cases in 2016 (CDPH 2017).

Even if present at the site, construction activities may not result in increased incidence of Valley Fever. Propagation of Valley Fever is dependent on climatic conditions, with the potential for growth and surface exposure highest following early seasonal rains and long dry spells. Valley Fever spores can be released when filaments are disturbed by earth-moving activities, although receptors must be exposed to and inhale the spores to be at increased risk of developing Valley Fever. Moreover, exposure to Valley Fever does not guarantee that an individual will become ill— approximately 60% of people exposed to the fungal spores are asymptomatic and show no signs of an infection (USGS 2000).

In order to reduce fugitive dust from the Project and minimize adverse air quality impacts, the Project would employ dust mitigation measures in accordance with the MDAQMD Rules 401 and 403.2, which limit the amount of fugitive dust generated during construction. These requirements are consistent with CDPH recommendations for the implementation of dust control measures, including regular application of water during soil -disturbance activities, to reduce exposure to Valley Fever – the watering minimizes the potential that the fungal spores become airborne (CDPH 2013). Further, regulations designed to minimize exposure to Valley Fever hazards are included in Title 8 of the California Code of Regulations and would be complied with during the Project’s construction phase (California Department of Industrial Relations 2017).

In summary, the Project would not result in a significant impact attributable to Valley Fever exposure based on its geographic location and compliance with applicable regulatory standards and dust mitigation measures, which will serve to minimize the release of and exposure to f ungal spores. Therefore, impacts associated with Valley Fever exposure for sensitive receptors would be less than significant.

Other Emissions
Land uses generally associated with odor complaints generally include: agricultural uses (livestock and farming) , wastewater treatment plants, food-processing plants, chemical plants, composting operations, refineries, landfills, dairies, and fiberglass molding facilities. The Project does not propose uses that would be substantive sources of objectionable odors. Potential temporary and intermittent odors may result from construction equipment exhaust, the application of asphalt, and architectural coatings. Temporary and intermittent construction -source emissions

Page 89 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
64 March 2022
are controlled through existing requirements and industry Best Management Practices (BMPs) addressing proper storage of and application construction materials.

Over the life of the Project, odors may result from storage of municipal solid waste pending its transport to area landfills. Project -generated refus e would be stored in covered containers and removed at regular intervals in compliance with the City of Hesperia’s solid waste regulations.

The Project would also be required to comply with MDAQMD Rule 402 (Nuisance). Rule 402 provides that “[a] person shall not discharge from any source whatsoever such quantities of air contaminants or other material which cause injury, detriment, nuisance or annoyance to any considerable number of persons or to the public, or which endanger the comfort, repose, health or safety of any such persons or the public, or which cause, or have a natural tendency to cause, injury or damage to business or property” (MDAQMD 1976). Based on the preceding, the potential for the Project to create objectionable odors affecting a substantial number of people would be less than significant.

Finding
The City finds that, based upon substantial evidence in the record, the proposed project would have a less than significant impact on air quality as it relates to health impacts of CO hotspots, toxic air contaminant exposure and valley fever, and other emissions; therefore, no mitigation is required.

2.4.4 Biological Resources
Candidate, Sensitive, or Special-Status Species
The following section evaluates the Project’s effects on plant and wildlife species identified as candidate, sensitive, or special status species in local or regional plans, policies, or regulations, or by the CDFW or USFWS.

Special-Status Wildlife Species
Desert Tortoise
The results of the survey determined that desert tortoise are currently considered absent from the Project site and Off-Site Utilities Alignments. The on-site vegetation has been determined to provide low‐quality habitat for the desert tortoise. While suitable (albeit low-quality) habitat for this species will be removed as a result of construction of the Project, this habitat is unoccupied, and the Project would not result in any direct or indirect impacts to desert tortoise. Therefore, impacts to desert tortoise associated with the Project and Off-Site Utilities Alignments would be less than significant.

Mohave Ground Squirrel
The Project site is located in an area that is cut off from known Mohave ground squirrel populations by Interstate 15 and U.S. Highway 395 to the east and by the California Aqueduct to the north. Disturbances from human presence and fragmentation from surrounding roadways, including off -highway vehicle use and illegal waste dumping within the Project site and Off -Site Utilities Al ignments has had a negative effect on habitat quality for Mohave ground squirrel. Records from the CNDDB reveal two occurrences of Mohave ground squirrel near the Project site and Off-Site Utility Alignment that were detected in 2005 and 2011. However, bot h these records are from sites located across the California Aqueduct, making dispersal to the Project site highly unlikely, because the aqueduct creates a considerable barrier to dispersal.

Page 90 ends

FINDINGS OF FACT, HESPERIA COMMERCE CENTER II EIR, SCH NO. 2019110418 12122
65 March 2022
The Project site and Off-Site Utilities Alignments provides have a low likelihood of Mohave ground squirrel to occur.

No Mohave ground squirrel were detected at the camera stations or captured during the trapping surveys.

Additionally, the high density of California juniper on site is indicative that the area is within the Mohave - transmontane transition zone, an area with low likelihood of use by Mohave ground squirrel. As such, the survey results indicate that Mohave ground squirrel do not inhabit the Project site or Off-Site Utility Alignment.

Therefore, the Project would not result in any direct or indirect impacts to Mohave ground squirrel. Therefore, impacts to Mohave ground squirrel associated with the Project and Off-Site Utilities Alignments would be less than significant.

Interference with Wildlife Movement/Use of Nursery Sites The Project site is located in an area of encroaching development and has been regionally isolated by U.S. Highway 395 to the east and by the California Aqueduct to the north. As a result, the Project site does not provide for regional wildlife movement or serve as a regional wildlife corridor. However, on a local level, wildlife may move across the site when migrating or foraging/hunting. Therefore, wildlife movement may be temporarily disrupted during the construction phase of the Project, although this effect would be both localized and short -term in nature. Nearby corridors that could support wildlife movement in the region, include the La Bureau of Power and Light Road immediately to the west and the Oro Wash further to the east, would n ot be impacted by the Project. Further, the Project site does not contain nursery sites, such as bat colony roosting sites or colonial bird nesting areas.

All off-site utilities would be located below grade, and thus, would not represent an impedance to wildlife movement.

Similar to the construction work being conducted on the Project site, the construction activities associated with the off-site utilities have the potential to temporarily disrupt wildlife movement in the immediate vicinity of construction; however, any impact would be both localized and short-term in nature. Therefore, impacts associated with wildlife movement, wildlife corridors, and wildlife nursery sites would be less than significant.

Habitat Conservation Plan, Natural Community Conservation Plan, or other Conservation Plan The Project site and the Off-Site Utilities Alignments are located within the California Desert Conservation Area Plan (BLM 1980). The Project site and the Off-Site Utilities Alignments are also located within the Draft West Mojave Plan (BLM 2005) and the Desert Renewable Energy Conservation Plan (BLM 2016) areas. The West Mojave Plan and Desert Renewable Energy Conservation Plan are amendments to the California Desert Conservation Area Plan. The BLM issued a Record of Decision for the West Mojave Plan in 2006, although the West Mojave Plan has not been formally adopted. The Project will not conflict with the conservation criteria associated with the California Desert Conservation Area Plan or Desert Renewable Energy Conservation Plan. Therefore, impacts associated with an adopted habitat conservation plan would be less than significant.

Finding
The City finds t hat, based upon substantial evidence in the record, the proposed project would have a less than significant impact on biological resources as it relates to specific special-status wildlife species; the interference with the movement of any native resident or migratory fish or wildlife species; and as it relates to a habitat conservation plan, natural community conservation plan, or other conservation plan. Therefore, no mitigation is required.

Page 91 ends