Attachment 2 - Measure I CPNA Submittals

Hesperia City Council
September 20, 2022

Document
Attachment 2 - Measure I CPNA Submittals
Meeting
September 20, 2022
Body
Hesperia City Council
Original file
184 KB
Text extracted from the city's file for reading and search. Open the original on legistar.granicus.com. That file is the official record.

Nexus Project Cost 54,057,000$
Dev. Loan? No
5-Year Advance? No
Public Share: 41.1%
Dev. Share: 58.90%
Project Information Phase Funding PRIOR* FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28 FUTURE PA&ED
Total Cost: $816,162.00
Fund Type: MSI MLHP $ - $ - $ - $ - $ - $ - $ - DEV FEE $ 470,517.00 $ - $ - $ - $ - $ - $ - MI LOCAL ST $ 324,125.00 $ - $ - $ - $ - $ - $ - OTHER $ 21,520.00 $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - PS&E
Total Cost: $1,842,304.00
Fund Type: MSI MLHP $ - $ - $ - $ - $ - $ - $ - DEV FEE $ 253,856.00 $ - $ - $ - $ - $ - $ - MI LOCAL ST $ 443,259.00 $ - $ - $ - $ - $ - $ - OTHER $ 1,145,189.00 $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - ROW
Total Cost: $969,263.00
Fund Type: MSI MLHP $ 398,367.00 $ - $ - $ - $ - $ - $ - DEV FEE $ 570,896.00 $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - CONST
Total Cost: $42,655,154.00
Fund Type: MSI MLHP $10,232,559.00 $ 2,184,617.00 $ - $ - $ - $ - $ - DEV FEE $11,466,195.00 $ 2,426,783.00 $ - $ - $ - $ - $ - LPP $15,299,913.00 $ 795,087.00 $ - $ - $ - $ - $ - OTHER $ - $ 250,000.00 $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - *Prior should identify any expenses incurred in prior years that have not yet been reimbursed by SBCTA including anticipated F
Y 2022/2023 expenses.
 Total Measure I Requested exceeds Public Share Percentage  Total Project Cost (FY 15/16 - 19/20) does not match funding listed. 106309262184617
Capital Project Needs Analysis
City of Hesperia
Victor Valley Major Local Highway Program
Ranchero Road Corridor
Widening Project - Widen
Ranchero Road from Topaz Ave.
to 7th Ave. from 2 to 5 lanes
Current Total Project Cost
Estimate:
$0.00
Total Measure I Request:
$12,815,543.00
(Summation of Measure I)
Comments:
2024-2028 CPNA.xlsx - Proj 1
Attachment 2
Nexus Project Cost 31,862,003$
Dev. Loan? No
5-Year Advance? No
Public Share: 41.1%
Dev. Share: 58.90%
Project Information Phase Funding PRIOR* FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28 FUTURE PA&ED
Total Cost: $986,576.00
Fund Type: MSI MLHP $ - $ - $ - $ - $ - $ - $ - DEV FEE $ 95,307.00 $ - $ - $ - $ - $ - $ - MI LOCAL ST $ - $ - $ - $ 145,000.00 $ - $ 360,000.00 $ - OTHER $ 386,269.00 $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - PS&E
Total Cost: $1,164,855.00
Fund Type: MSI MLHP $ - $ - $ - $ - $ - $ - $ - DEV FEE $ 77,280.00 $ - $ - $ - $ - $ - $ - MI LOCAL ST $ - $ - $ - $ - $ 225,000.00 $ - $ 492,750.00 OTHER $ 369,825.00 $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - ROW
Total Cost: $5,421,348.00
Fund Type: MSI MLHP $ - $ - $ - $ 82,200.00 $ 549,332.00 $ 184,945.00 $ 1,411,702.00 DEV FEE $ - $ - $ - $ 117,800.00 $ 787,228.00 $ 265,044.00 $ 2,023,097.00 - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - CONST
Total Cost: $24,289,224.00
Fund Type: MSI MLHP $ - $ - $ - $ - $ - $ 3,699,159.00 $ 6,283,712.00 DEV FEE $ - $ - $ - $ - $ - $ 5,301,230.00 $ 9,005,123.00 - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - - Select Fund - $ - $ - $ - $ - $ - $ - $ - Other: ______ $ - $ - $ - $ - $ - $ - $ - Capital Project Needs Analysis
City of Hesperia
Victor Valley Major Local Highway Program
Main St. Widening - Widen Main
St from Escondido Ave to 11th
Ave from 4 to 6 lanes, including
aqueduct bridge widening
Current Total Project Cost
Estimate:
$0.00
Total Measure I Request:
$12,211,050.00
(Summation of Measure I)
*Prior should identify any expenses incurred in prior years that have not yet been reimbursed by SBCTA including anticipated FY 2022/2023 expenses.
 Total Measure I Requested exceeds Public Share Percentage  Total Project Cost (FY 15/16 - 19/20) does not match funding listed. 00 Comments:
2024-2028 CPNA.xlsx - Proj 2