Tasks Total Hours Senior
Engineer
Associate
Engineer
Average
Billing
Rates
Total Cost
Project Management, Meeting & Coordination 12 217.25$ 2,607.00$ Project Management 12 2,607.00$

Respond to Information (RFI) and Prepare CCO plans
Respond to RFIs and Prepare CCOs as requested by city 100 20 80 151.45$ 15,145.00$

Complete remaining UPRR grade crossing revisions 20 4 16 151.45$ 3,029.00$

Prepare revised UPRR waterline casing design 20 20 0 217.25$ 4,345.00$

As-built
Prepare as-builts 50 10 40 151.45$ 7,572.50$

Design Support During Construction (DSDC) 190 30,091.50$

-$

32,698.50$

EXHIBIT B
Amendment No. 2 - Design Support During Construction

TASK SUMMARY
Total
Other Direct Cost (ODC)
Attachment 1