Attachment 1- Amendment No. 3 Project Funding Agreement

Hesperia City Council
June 3, 2025

Document
Attachment 1- Amendment No. 3 Project Funding Agreement
Meeting
June 3, 2025
Body
Hesperia City Council
Pages
3
Original file
775 KB
Text extracted from the city's file for reading and search. Open the original on legistar.granicus.com. That file is the official record.

17-
1001692-03

Page 1 of 3 ends

AMENDMENT NO. 3 TO PROJECT FUNDING AGREEMENT 17-1001692 FO
R
RANCH

ERO ROAD WIDENING PROJECT
(

CITY OF HESPERIA)
T
HIS Amendment No. 3 to Project Funding Agreement 17-1001692 is made and entered into by and between the City of Hesperia ("CITY") and the S an Bernardino County Transportation Authority ("SBCTA"). SBCTA and CITY are each a “Party” and collectively “Parties”.

R

ECITALS
A. T
he Parties entered into Project Funding Agreement 17-1001692 (“Agreement”) effective July 12, 2017, to fund the Right of Way Phase of the Ranchero Road Widening Project in the City of Hesperia (“Project”) with an approved allocation of $1,513,964; and B. On July 10, 2019, the SBCTA Board of Directors approved an allocation of $12,678,000 in Senate Bill 1 Local Partnership Program formulaic funds for the Construction Phase of the Project; and
C. A
mendment No. 1 to the Agreement , dated June 4, 2020, increased the allocation of Measure I Victor Valley Subarea Major Local Highway Program (“MLHP”) funds to $11,507,821 to fund through the Construction Phase, and extended the termination date to June 30, 2023; and D. A
mendment No. 2 to the Agreement, dated June 27, 2023, extended the termination date to June 30, 2025; and
E. C
ITY has requested an extension of the termination date to June 30, 2028.

NOW, THEREFORE, the Parties agree to amend the Agreement as follows:

1. S
ection III, Paragraph 7 is deleted in its entirety and replaced with the following:
“7. T
his Agreement will be considered terminated upon reimbursement of eligible costs by SBCTA or June 30, 2028, whichever is sooner, provided that the provisions of Paragraphs 5, 6, 7, 8, and 9 of Section II, and Paragraphs 5, 6 and 6.A of Section III, shall survive the termination of this Agreement.”

2. A
ttachment A to the Agreement is replaced with the Revised Description of Project and Milestones attached as Attachment A to this Amendment No. 3 and incorporated herein.

3. E
xcept as amended by this Amendment No. 3, all other terms and conditions of the A greement, and amendments thereto, shall remain in full force and effect and are incorporated herein by this reference.

Attachment 1

17-1001692-03

Page 2 of 3 ends

4. The Recitals set forth above are incorporated herein by this reference.

5. This Amendment No. 3 may be signed in counterparts, each of which shall constitute an original.

6. This Amendment No. 3 shall be effective on the date executed by SBCTA.

IN WITNESS WHEREOF, SBCTA and CITY have executed this Amendment No. 3 below.

SAN BERNARDINO COUNTY CITY OF HESPERIA

TRANSPORTATION AUTHORITY

By: _________________________________ By: _______________________________ Raymond W. Wolfe, Ph.D. Allison Lee
Executive Director Mayor

Date: ________________________________ Date: ______________________________

APPROVED AS TO FORM: APPROVED AS TO FORM:

By: __________________________________ By: _________________________________ Julianna K. Tillquist Pam Lee
SBCTA General Counsel City Attorney

Date: _________________________________ Date: _______________________________

Attachment 1

17-1001692-03

Page 3 of 3 ends

Attachment A

RANCHERO ROAD WIDENING PROJECT
Revised Description of Project and Milestones

Project Title
Ranchero Road Widening Project
Location, Project Limits, Description, Scope of Work, Legislative Description Widen Ranchero Road from .15 miles east of Mariposa Road to east of the completed Ranchero Road Undercrossing at 7th Avenue.

Project Milestone Proposed
Project Study Report Approved N/A
Begin Environmental (PA&ED) Phase 12/1/2007
Circulate Draft Environmental Document 6/1/2013
Draft Project Report N/A
End Environmental Phase (PA&ED Milestone) 7/1/2013
Begin Design (PS&E) Phase 3/1/2009
End Design Phase (Ready to List for Advertisement Milestone) 6/30/2021 Begin Right of Way Phase 11/1/2017
End Right of Way Phase (Right of Way Certification Milestone) 11/30/2020 Begin Construction Phase (Contract Award Milestone) 10/5/2021 End Construction Phase (Construction Contract Acceptance Milestone) 6/30/2027
Begin Closeout Phase 7/1/2027
End Closeout Phase (Closeout Report) 6/30/2028