Bid Comparison Type: Non-Taxable
Bid Comparison Completed By: Purchasing
Date: 2/24/26
Roadway Engineering &
Construction Corp.
H L Hitchcock Construction
Inc
Extended Amount Extended Amount
1 LS 1 $20,000.00 $25,050.00
2 LS 1 $274,400.00 $346,000.00
Total Bid $294,400.00 $371,050.00
Mobilization, bonds, insurance, field office, clean-up, relocations, demobilization, all misc. work, etc. complete and in place Removal of excess sand, fill the shoulders with clean dirt, establish new flow line, repair/raise any sunken water valve cans, clean driveway and street within the project area. (as listed in Chapter VI Special Provisions.
Materials, labor, equipment, and traffic control shall be included with all improvements fully functional, complete and in place.)
Item
No. Units Est. Qty Description
RFB 2025-26-011 Shoulder Repair
Attachment 3