Bid Comparison Type: Non-Taxable
Bid Comparison Completed By: Purchasing
Date: 2/25/26
Pyramid Building &
Engineering, Inc
H L Hitchcock Construction
Inc Shiraz Construction Jeremy Harris Construction,
Inc. RE Chaffee Construction Inc.
Extended Amount Extended Amount Extended Amount Extended Amount Extended Amount 1 LS 1 $10,480.14 $8,500.00 $60,944.00 $24,850.00 $25,700.00 2 LS 1 $209,602.80 $196,500.00 $136,833.00 $151,305.00 $195,300.00 Total Bid $220,082.94 $205,000.00 $197,777.00 $176,155.00 $221,000.00 Mobilization, bonds, insurance, field office, clean-up, relocations, demobilization, all misc. work, etc. complete and in place Remove the sediment and debris (as identified in Section VI Special Provisions. Materials, labor, equipment, and traffic control shall be included with all improvements fully functional, complete and in place.) Item
No. Units Est. Qty Description
RFB 2025-26-009 H-01 Basin
Attachment 5