RESOLUTION NO. 2022-13

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF HUNTINGTON BEACH

APPROVING THE APPLICATION FOR GRANT FUNDS FROM THE

RECREATIONAL TRAILS PROGRAM
WHEREAS, the "Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users" provides funds to the State of California for Grants to federal, state, local and non-profit organizations to acquire, develop and/or maintain motorized and non-motorized trail Projects; and
WHEREAS, the State Department of Parks and Recreation has been delegated the responsibility for the administration of the program within the State, setting up necessary procedures governing Project Application under the program; and WHEREAS, said procedures established by the State Department of Parks and Recreation require the Applicant to certify by resolution the approval of Application(s) before submission of said Application(s) to the State; and
WHEREAS, the Applicant will enter into a Contract with the State of California to complete the Projects);
NOW, THEREFORE, BE IT RESOLVED that the City Council hereby:

1. Approves the filing of an Application for the Recreational Trails Program; and

2. Certifies that the Project is consistent with the Applicant's general plan or the equivalent planning document; and
Certifies that said Applicant has or will have available prior to commencement of any work on the Projects) included in this Application, sufficient funds to operate and maintain the Projects); and

4. Certifies that the Applicant has reviewed, understands, and agrees to the General Provisions contained in the Contract shown in the Procedural Guide; and Appoints the Director of Public Works or his/her designee as agent to conduct all negotiations, execute and submit all documents, including, but not limited to Applications, agreements, amendments, payment requests and so on, which may be necessary for the completion of the Project.

6. Agrees to comply with all applicable federal, state and local laws, ordinances, rules, regulations and guidelines.
22-11129/278175
RESOLUTION NO. 2022-13
PASSED and ADOPTED by the City Council of the City of Huntington Beach at the regular meeting thereof held on the day of , 2022.

REVIEWED AND APPROVED:

Mayor
INITIATED AND APPROVED:

City Manager
APPROVED AS TO FORM:

City Attorney Me
2 RESOLUTION NO. 2022-13

GRANT SCOPE OF WORK
The Shipley Trail Project involves the realignment of portions of the existing Shipley Trail that are currently flooded because of the water level at the Blackbird pond raising approximately 2 ft. in the last tew years.

The Project involves realignment of approximately 850 ft. of trail from Trail Marker 7 to west of Trail Marker 9.

The project will consist of the following:

Removal of several willow trees, with large branches and trunks that extend several feet from their trunks. The willow trees would have to be removed completely or cut so the branches no longer infringe upon the proposed trail.

The work would also involve the removal of native and non-native vines such as Reed, Brazilian pepper trees and others. Please note that eradication of the plant material outside the trail path has not been added in order to keep the cost reasonable.

The work would include the clearing and grubbing of approximately 0.7 acre of terrain along the new proposed trail alignment.

Compaction of base material, and import of approximately 1800 cubic yards of fill material to elevate the trail above possible flooding stage.

5. Addition of a trail surface to match existing trail (i.e.: wood chips or decomposed granite).

Installation of trail edge headers, installation of trail markers and other required sign age.

The exact length of trail to be restored must be verified by field measurements.

Surveying will be necessary to determine the elevation of the trail relative to the bottom of the pond drain.

This Project would be classified as a non- motorized Project under Development and Rehabilitation of trails, trailside and Trailhead Facilities.