Att#2 - Capital Improvement Costs

City Council/Public Financing Authority
November 15, 2022

Document
Att#2 - Capital Improvement Costs
Meeting
November 15, 2022
Body
City Council/Public Financing Authority
Original file
555 KB
Text extracted from the city's file for reading and search. Open the original on huntingtonbeach.legistar1.com. That file is the official record.

Pergola Replacement at Year 5 $56,275
Replace Irrigation Pump at Year 5 $39,393
Slurry Coat OVE Roadway at Year 5 $56,275
Slurry Driveways Per Unit at Year 5 $198,090
Total $350,033
Pergola Replacement at Year 5 $56,275
Replace Irrigation Pump at Year 5 $39,393
Asphalt Overlay Park Roadway at Year 5 $163,097
Slurry Driveways Per Unit at Year 5 $198,090
Clubhouse Paint and Interior at Year 10 $19,572
Tile Roof - (25-year Lifespan) at Year 10 $97,858
Clubhouse Gutters at Year 10 $13,048
Total $587,333
Pergola Replacement at Year 5 $56,275
Replace Irrigation Pump at Year 5 $39,393
Asphalt Overlay Park Roadway at Year 5 $163,097
Slurry Driveways Per Unit at Year 5 $198,090
Clubhouse Paint and Interior at Year 10 $19,572
Tile Roof - 25 Year Lifespan at Year 10 $97,858
Clubhouse Gutters at Year 10 $13,048
Slurry Coat OVE Roadway at Year 15 $75,629
Slurry Driveways Per Unit at Year 15 $266,216
Clubhouse Paint and Interior at Year 20 $26,303
Total $955,481

CAPITAL IMPROVEMENT PROJECTS

NEEDED TO CONTINUE OVE OPERATION
* Costs Include 3% CPI Inflation Factor
OVE 5-10 Year Operation
OVE 10-20 Year Operation
OVE 20 Years or More