Traffic and Homeless Task Force Office Renovations Project
Table of Contents
Current Configuration
Renovated Design
Questions
Current Configuration - Obsolete
Traffic Office
Constructed in 1971.
Carpeting, temp wall partitions, HVAC, electrical and data systems are all outdated.
Traffic department needs additional space and equipment.
Evidence Room
Constructed in 1971.
Evidence room relocated, current room not in use.
Current wall finishes, flooring, HVAC, electrical, and data network are in poor condition.
TRAFFIC OFFICE
EVIDENCE ROOM
(E) CITY HALL BLDG
Renovated Design
New traffic open office, above left, and private office, above right.
New Homeless Task Force Open Office
Open office with 4 computers.
New Supervisor office.
New flooring, wall finishes, ceiling tiles, electrical, HVAC, and data network systems.
New Traffic Office
New investigator office.
Expanded report writing area with 5 desks.
Renovations to entire office space involve new permanent drywall, flooring, ceiling tile, HVAC, electrical, and data network systems.
Questions?