Glen Mar Frontage Road Improvement Project
Table of Contents
Project Overview
Project History
Current Condition
Prior Improvements
Project Scope
Project Phasing
Questions
Project Overview
Construction bids received in December 2022
Total Funding - $500,000 (Infrastructure Funds)
Request award to lowest bidder – MBC Enterprises, Inc.
Recommended action includes award of:
Base Bid scope (Schedule A)
Additive Alternative scope (Schedule D)
Alternative actions:
Reject all bids
Award base bid scope only (Schedule A) –> Total Cost = $427,852.30 Award complete project scope (Schedule A, B, C, D) -> Total Cost = $1,570,789.68
Project History - Current Condition
Project History - Prior Improvements
Project Scope
Monument Sign Renovation
Pilaster Renovation
Fencing Removal & Replacement
Street Tree Removal & Replacement
Landscape Improvements
Asphalt removal
Mulch and plant bedding
Irrigation
Project Phasing
Project Budget - $500,000
Project Bid with alternatives for budget consideration
Phased Construction
4 total sections
Budget allows for completion of 2 sections (A & D)
City to seek approval for additional funding in FY23/24
Questions?