Heil Storm Water Pump Station Replacement Project, CC1290 CC 1290
PROJECT NEED
The existing pump station and culvert are under capacity.
These photos are from February 21, 2005, from a 10-year storm event.
The box culvert under Heil Ave. is under capacity and causes a backwater condition up- stream of Heil Ave.
PROJECT PURPOSE
Increase the capacity of the Heil Pump Station to convey the 100-year storm The project will:
Increase the Heil box culvert capacity by installing a parallel culvert under Heil Ave.
Increase the pump station capacity by increasing the number of pumps from two to four. The station will operate with three pumps in service with a fourth pump reserved for operational redundancy.
Remove approximately 87 acres from the FEMA 100-year flood zone.
Funding
FEMA Grant $6,598,950
Drainage Fund $2,000,000
Infrastructure Fund $4,200,050
Heil Storm Water Pump Station Project,Project Overview: