Heil Storm Water Pump Station Replacement Project, CC1290 CC 1290

PROJECT NEED
The existing pump station and culvert are under capacity.

These photos are from February 21, 2005, from a 10-year storm event.

The box culvert under Heil Ave. is under capacity and causes a backwater condition up- stream of Heil Ave.

PROJECT PURPOSE
Increase the capacity of the Heil Pump Station to convey the 100-year storm The project will:

Increase the Heil box culvert capacity by installing a parallel culvert under Heil Ave.

Increase the pump station capacity by increasing the number of pumps from two to four. The station will operate with three pumps in service with a fourth pump reserved for operational redundancy.

Remove approximately 87 acres from the FEMA 100-year flood zone.

Funding
FEMA Grant $6,598,950
Drainage Fund $2,000,000
Infrastructure Fund $4,200,050

Heil Storm Water Pump Station Project,Project Overview:

Questions?