Magnolia Street Regional Traffic Signal Synchronization Project, Amend Cooperative Agreement, CC-1552
PROJECT HISTORY
OCTA Managed Traffic Signal Synchronization Project along Magnolia Street from Fullerton to Huntington Beach Cooperative Agreement executed in November 2017, expires June 2023 Construction and Timing Complete Evaluation Ongoing
Amendment No. 1 Extends Agreement to June 2025 to allow continuing evaluation by OCTA No additional cost to City of HB
PROJECT DESCRIPTION
This project provided operational and infrastructure improvements at 50 intersections along Magnolia Street from Fullerton to Huntington Beach Improvements within Huntington Beach included:
Installation of fiber optic communication cable and conduit New traffic signal controllers
Updated traffic signal timing
Funding – City Matching Funds Appropriated in November 2017. No additional funding is requested.
City of Huntington Beach Matching Funds: $199,789
Project Cost Within Huntington Beach: $725,000
PROJECT DESCRIPTION (CONTINUED)
As OCTA has not completed their analysis of the corridor operation, this Amendment to the Cooperative Agreement is for a time extension with no additional funding requested.