Bolsa Chica Street / Valley View Street Regional Traffic Signal Synchronization Project, CC-1622
PROJECT DESCRIPTION
This project provides operational and infrastructure improvements at 22 intersections along Bolsa Chica Street / Valley View Street from Garden Grove to Huntington Beach Improvements within Huntington Beach included:
Installation of fiber optic communication cable and conduit New traffic signal controllers
Updated traffic signal timing
The City of Huntington Beach is Lead Agency
The City of H.B. will manage engineering efforts for the entire corridor
All OCTA funds will be paid to and disbursed by the
City of Huntington Beach
PROJECT DESCRIPTION (CONTINUED)
Recommended City Council Actions:
Approve the Cooperative Agreement with the Cities of Garden Grove and Westminster. This agreement specifies the responsibilities and funding commitments for each agency.
Amend the 2022/2023 CIP to include this project.
Authorize City’s project funding.
PROJECT COSTS
TOTAL PROJECT COST: $2,243,900
OCTA Grant: $1,735,949
WORK WITHIN HUNTINGTON BEACH: $760,103
TOTAL CITY COSTS
City of Huntington Beach Matching Funds Required $ 155,533 City of Huntington Beach Construction Contingency $ 114,015 City of Huntington Beach Contract Administration $ 59,949 TOTAL $ 329,497
Questions?