The electrical equipment at the Central Library substation failed as of April 14, 2023 resulting in the Library’s closure to staff and patrons.
NEED/WHY/BENEFITS
The electrical equipment at the Central Library substation exhibits extensive signs of failures and does not meet crucial safety standards.
Repairs and updates are necessary before permanent power can safely be restored to these substations.
Temporary power will be supplied through rental equipment while design for custom built switchgear and permanent replacement equipment is ordered and delivered.
DETAILS
Repairs and rental equipment to be provided per the utilization of the existing service agreement with Snowden Electric Company, Inc., dated January 1, 2023.
Proposal submitted by Snowden Electrical for rental equipment, up to one year is $535,000 plus 10% contingency totaling $585,850.
Public Works will make an additional request for funding from Council at a later date once the full scope and costs for the permanent repairs and equipment is known.
RECOMMENDATION
Authorize the appropriation of $585,850 from the HB Recovery Fund to account 31440006.82800