Traffic Signal Modifications
Warner Avenue and Ash Lane
Main Street and Delaware Street
5/16/2023
Project Scope
Installation of east-west left turn arrows at Warner Avenue and Ash Lane Installation of left turn arrows on Main Street at Delaware Street Left turns would only be permitted on a green arrow
Project includes sidewalk and curb ramp improvements
Project Budget
Bids opened on March 28, 2023
Low Apparent Bid is $757,880
Project Cost Estimate is $1,260,000 including City furnished traffic signal equipment, construction contingency and contract administration Available Funds: $764,000 - resulting in an estimated shortfall of $496,000 Staff recommendation is to reject all bids
Project Locations
Questions?