Fiber Optic Installation
Garfield Avenue
6/6/2023
Project Scope
Installation of Fiber Optic Cable and Conduit
Along Garfield Avenue from the Utility Yard to Newland Street Connects to Existing Fiber at Utility Yard and along Newland Street Additional Traffic Signals Communicating with City Hall TMC Delaware Street
Florida Street
Communication Redundancy
Completes Fiber Optic Loop from City Hall to Warner Avenue Redundancy to City Yard and Central Library
Project Budget
Construction Cost Estimate
Contractor’s Bid $445,480
15% Contingency $ 66,822
Construction Administration $ 31,698
TOTAL $544,000
Infrastructure Fund
Project Location