Fiber Optic Installation
Gothard Street
6/6/2023

Project Scope
Installation of Fiber Optic Cable and Conduit
Along Gothard Street from Edinger Avenue to Warner Avenue Connects to fiber being installed on Edinger and existing fiber on Warner Additional Signals/Facilities Communicating with City Hall Gothard Street and Heil Avenue traffic signal
Murdy Fire Station
Communication Redundancy
Completes Fiber Optic Loop from City Hall to Edinger Avenue

Project Budget
Construction Cost Estimate
Contractor’s Bid $625,650
15% Contingency $ 93,848
Construction Administration $ 30,502
TOTAL $750,000
Project Funding
$600,195 from the Infrastructure Fund
$149,805 is requested to be appropriated from the Traffic Impact Fee Fund

Project Location