Fiber Optic Installation
Central Library
6/6/2023

Project Scope
Installation of Fiber Optic Cable and Conduit
From the intersection of Goldenwest Street and the library driveway to the southwest corner of the library building Inside of building to computer room
Connects Central Library with City Hall
Improved speed and reliability
Identified in Fiber and Communications Master Plan

Project Budget
Construction Cost Estimate
Contractor’s Bid $145,763
15% Contingency $ 21,864
Construction Administration $ 16,373
TOTAL $184,000
Public Education and Government Access Funds (PEG)