FY 2023/24 - FY 2029/30 Capital Improvement Program
TIP ID CP-10389 IMPLEMENTING AGENCY Huntington Beach,City of Local Project Number: Project Title
Additional Project IDs: Arterial Rehabilitation FY 2023 Type of Work: Road Maintenance Project Description
Type of Work Description: Road Maintenance -Rehabilitation of roadway Rehabilitate arterials including Magnolia (Atlanta-Indianapolis), Hamilton (Magnolia-Bushard), Orange(Goldenwest-17th), Talbert (Edwards-End), Banning (Magnolia-Brookhurst), Heil (Saybrook-BolsaChica), Garfield (Brookhurst-East City Limit), Edinger Limits
Magnolia, Hamilton, Orange, Heil, Garfield,Talbert, Edinger, Banning Project Notes
FISCALYEAR FUND TYPE ENGROWCON/IMP O&MTOTAL TOTALESCALATED 2024 Measure M2 LocalFairshare $0 $0 $1,000,000 $0 $1,000,000 $1,030,000 2024 Local Streets and Roadsapportionments $0 $0 $4,600,000 $0 $4,600,000 $4,738,000 2025 Local Streets and Roadsapportionments $0 $0 $4,600,000 $0 $4,600,000 $4,880,140 2025 Measure M2 LocalFairshare $0 $0 $1,000,000 $0 $1,000,000 $1,060,900 2026 Local Streets and Roadsapportionments $0 $0 $4,600,000 $0 $4,600,000 $5,026,544 2026 Measure M2 LocalFairshare $0 $0 $1,000,000 $0 $1,000,000 $1,092,727 2027 Local Streets and Roadsapportionments $0 $0 $4,600,000 $0 $4,600,000 $5,177,341 2027 Measure M2 LocalFairshare $0 $0 $1,000,000 $0 $1,000,000 $1,125,509 2028 Local Streets and Roadsapportionments $0 $0 $4,600,000 $0 $4,600,000 $5,332,661 2028 Measure M2 LocalFairshare $0 $0 $1,000,000 $0 $1,000,000 $1,159,274 2029 Measure M2 LocalFairshare $0 $0 $1,000,000 $0 $1,000,000 $1,194,052 2029 Local Streets and Roadsapportionments $0 $0 $4,600,000 $0 $4,600,000 $5,492,641 2030 Local Streets and Roadsapportionments $0 $0 $4,600,000 $0 $4,600,000 $5,657,420 2030 Measure M2 LocalFairshare $0 $0 $1,000,000 $0 $1,000,000 $1,229,874 Totals: $0 $0 $39,200,000 $0 $39,200,000 $44,197,083
Last Revised: 23-00 - In Progress Total Programmed: $39,200,000 TIP ID CP-11286 IMPLEMENTING AGENCY Huntington Beach, Cityof Local Project Number: Project Title
Additional Project IDs: Bridge Preventive Maintenance
Type of Work: Bridge Project Description
Type of Work Description: Bridge -Rehabilitation of existing pavement/structure Removal and replacement of unsound concrete, bearings; clean and paint structural steel Limits
Davenport Dr. Bridge (over Weatherly Channel)
Project Notes
Project added in the event that M2 local fair sharefunds are used to pay for costs that are notreimbursed through HBP grant funding. Davenportbridge may be upgraded to a bridge rehabilitationproject if funding is approved.
FISCAL YEAR FUND TYPE ENG ROW CON/IMP O&M TOTAL TOTAL ESCALATED 2024 Other $0 $0 $2,403,000 $0 $2,403,000 $2,475,090
Totals: $0 $0 $2,403,000 $0 $2,403,000 $2,475,090
Last Revised: 23-00 - In Progress Total Programmed: $2,403,000 6/13/23, 1:50 PM ocfundtracker.octa.net/CIP/report_project_listing https://ocfundtracker.octa.net/CIP/report_project_listing 2/8 TIP ID CP-11279 IMPLEMENTING AGENCY Huntington Beach,City of Local Project Number: Project Title
Additional Project IDs: Bridge Rehabilitation Projects
Type of Work: Bridge Project Description
Type of Work Description: Bridge -Rehabilitation of existing pavement/structure Design and rehabilitation of City bridges. Admiralty and Humboldt bridges are planned for constructionin FY 23/24 and FY 24/25, respectively.
Limits
Admiralty Dr. Bridge (over Queen ElizabethPassage) and Humboldt Dr. Bridge (over ShortChannel) Project Notes
Project added in the event that M2 local fair sharefunds are used to pay for costs that are notreimbursed through HBP grant funding. Davenportbridge BPMP may be upgraded to a bridgerehabilitation project if funding is approved.
FISCAL YEAR FUND TYPE ENG ROW CON/IMP O&M TOTAL TOTAL ESCALATED 2024 Other $0 $0 $3,780,000 $0 $3,780,000 $3,893,400
2025 Other $0 $0 $3,314,000 $0 $3,314,000 $3,515,823
Totals: $0 $0 $7,094,000 $0 $7,094,000 $7,409,223
Last Revised: 23-00 - In Progress Total Programmed: $7,094,000 TIP ID CP-11826 IMPLEMENTING AGENCY Huntington Beach,City of Local Project Number: Project Title
Additional Project IDs: City-Funded Bridge Maintenance Projects Type of Work: Bridge Project Description
Type of Work Description: Bridge -Rehabilitation of existing pavement/structure Program will correct minor structural defects, repair deficiencies, and extend the service life of existingbridges.
Limits
Citywide
Project Notes
Other indicates Traffic Congestion Relief (Prop 42)
FISCAL YEAR FUND TYPE ENG ROWCON/IMP O&MTOTAL TOTAL ESCALATED 2024 Other $250,000 $0 $750,000 $0 $1,000,000 $1,022,500 2025 Other $250,000 $0 $750,000 $0 $1,000,000 $1,045,675 2026 Other $250,000 $0 $750,000 $0 $1,000,000 $1,069,545 2027 Other $250,000 $0 $750,000 $0 $1,000,000 $1,094,132 2028 Other $250,000 $0 $750,000 $0 $1,000,000 $1,119,456 2029 Other $250,000 $0 $750,000 $0 $1,000,000 $1,145,539 2030 Other $250,000 $0 $750,000 $0 $1,000,000 $1,172,405 Totals: $1,750,000 $0 $5,250,000 $0 $7,000,000 $7,669,252 Last Revised: 23-00 - In Progress Total Programmed: $7,000,000 TIP ID CP-10391 IMPLEMENTING AGENCY Huntington Beach,City of Local Project Number: Project Title
Additional Project IDs: Concrete Replacements
Type of Work: Pedestrian Project Description
Type of Work Description: Pedestrian -Reconstruction or rehabilitation of sidewalk Replace worn, damaged, lifted, and broken sections of concrete sidewalk, curb and gutter, and curbramps in support of the zone maintenance program and in various locations city-wide.
Limits
Citywide
Project Notes
FISCALYEAR FUND TYPE ENGROWCON/IMP O&MTOTAL TOTALESCALATED 2024 Measure M2 LocalFairshare $0 $0 $500,000 $0 $500,000 $515,000 2025 Measure M2 LocalFairshare $0 $0 $500,000 $0 $500,000 $530,450 2026 Measure M2 LocalFairshare $0 $0 $500,000 $0 $500,000 $546,364 2027 Measure M2 LocalFairshare $0 $0 $500,000 $0 $500,000 $562,754 2028 Measure M2 LocalFairshare $0 $0 $500,000 $0 $500,000 $579,637 2029 Measure M2 LocalFairshare $0 $0 $500,000 $0 $500,000 $597,026 2030 Measure M2 LocalFairshare $0 $0 $500,000 $0 $500,000 $614,937 Totals: $0 $0 $3,500,000 $0 $3,500,000 $3,946,168
Last Revised: 23-00 - In Progress Total Programmed: $3,500,000 6/13/23, 1:50 PM ocfundtracker.octa.net/CIP/report_project_listing https://ocfundtracker.octa.net/CIP/report_project_listing 3/8 TIP ID CP-10392 IMPLEMENTING AGENCY Huntington Beach,City of Local Project Number: 12-OCTA-TSP-3625 Project Title
Additional Project IDs: Edinger Avenue Synchronization
Type of Work: Traffic Signals Project Description
Type of Work Description: Traffic Signals -Interconnect traffic signals to improve coordinationand communications OCTA leading joint project with Westminster, Fountain Valley, and Santa Ana. OCTA applying for SB-1funding.
Limits
From Bolsa Chica Street to Newland Street
Project Notes
Other: Funding from FY 20/21 carried over throughFY 23/24. Other indicates Traffic Congestion Relief(Prop 42).
FISCAL YEAR FUND TYPE ENG ROW CON/IMP O&M TOTAL TOTAL ESCALATED 2024 Other $15,000 $0 $80,000 $0 $95,000 $97,400
Totals: $15,000 $0 $80,000 $0 $95,000 $97,400
Last Revised: 23-00 - In Progress Total Programmed: $95,000 TIP ID CP-12141 IMPLEMENTING AGENCY Huntington Beach,City of Local Project Number: Project Title
Additional Project IDs: Fire Station Signal - Murdy Fire Station Type of Work: Traffic Signals Project Description
Type of Work Description: Traffic Signals - Installnew traffic signals and equipment Improve safety by installing a fire signal which will enable the Fire Department to stop traffic onGothard Street while egressing the fire station.
Limits
Murdy Fire Station on Gothard Street betweenEdinger Avenue and Heil Avenue Project Notes
FISCAL YEAR FUND TYPE ENG ROW CON/IMP O&M TOTAL TOTAL ESCALATED 2024 Traffic Impact Fees $0 $0 $345,000 $0 $345,000 $355,350 Totals: $0 $0 $345,000 $0 $345,000 $355,350
Last Revised: 23-00 - In Progress Total Programmed: $345,000 TIP ID CP-10393 IMPLEMENTING AGENCY Huntington Beach,City of Local Project Number: Project Title
Additional Project IDs: General Street Maintenance for Public Works Type of Work: Pedestrian Project Description
Type of Work Description: Pedestrian -Reconstruction or rehabilitation of sidewalk Annual maintenance work for concrete, slurry seal, potholes and failed asphalt; O&M of traffic signals,replacement of striping and signage, including engineering and inspection as needed on an annualbasis.
Limits
Citywide
Project Notes
FISCALYEAR FUND TYPE ENGROWCON/IMP O&MTOTAL TOTALESCALATED 2024 Measure M2 LocalFairshare $0 $0 $2,000,000 $0 $2,000,000 $2,060,000 2025 Measure M2 LocalFairshare $0 $0 $2,000,000 $0 $2,000,000 $2,121,800 2026 Measure M2 LocalFairshare $0 $0 $2,000,000 $0 $2,000,000 $2,185,454 2027 Measure M2 LocalFairshare $0 $0 $2,000,000 $0 $2,000,000 $2,251,018 2028 Measure M2 LocalFairshare $0 $0 $2,000,000 $0 $2,000,000 $2,318,548 2029 Measure M2 LocalFairshare $0 $0 $2,000,000 $0 $2,000,000 $2,388,105 2030 Measure M2 LocalFairshare $0 $0 $2,000,000 $0 $2,000,000 $2,459,748 Totals: $0 $0 $14,000,000 $0 $14,000,000 $15,784,673
Last Revised: 23-00 - In Progress Total Programmed: $14,000,000 6/13/23, 1:50 PM ocfundtracker.octa.net/CIP/report_project_listing https://ocfundtracker.octa.net/CIP/report_project_listing 4/8 TIP ID CP-10394 IMPLEMENTING AGENCY Huntington Beach, City of Local Project Number: 14-HBCH-ECP-3742 Project Title
Additional Project IDs: Huntington Beach Catch Basin Retrofit Project Type of Work: Environmental Cleanup Project Description Type of Work Description: EnvironmentalCleanup - Automatic Retractable Screen and otherdebris screens or inserts Maintenance of 111 catch basins retrofitted with Bio Clean Round Curb Inlet Filters.
Limits
Citywide
Project Notes
FISCAL YEAR FUND TYPE ENG ROW CON/IMP O&M TOTAL TOTAL ESCALATED 2024 Developer $0 $0 $0 $14,429 $14,429 $14,429
2025 Developer $0 $0 $0 $14,429 $14,429 $14,429
Totals: $0 $0 $0 $28,858 $28,858 $28,858
Last Revised: 23-00 - In Progress Total Programmed: $28,858 TIP ID CP-10395 IMPLEMENTING AGENCY Huntington Beach,City of Local Project Number: 13-HBCH-ECP-3687 Project Title
Additional Project IDs: Huntington Beach Northwest Catch Basin Retrofit Project Type of Work: Environmental Cleanup Project Description Type of Work Description: EnvironmentalCleanup - Catchment Retrofit Maintenance of 102 catch basins retrofitted with Bio Clean Round Curb Inlet Filters and Skimmer Box.
Limits
Citywide in Northwest Part of City
Project Notes
FISCAL YEAR FUND TYPE ENG ROW CON/IMP O&M TOTAL TOTAL ESCALATED 2024 General Fund $0 $0 $0 $13,583 $13,583 $13,583
Totals: $0 $0 $0 $13,583 $13,583 $13,583
Last Revised: 23-00 - In Progress Total Programmed: $13,583 TIP ID CP-12140 IMPLEMENTING AGENCY Huntington Beach,City of Local Project Number: 22-HBCH-ECP-4036 Project Title
Additional Project IDs: Huntington Beach Trash Removal Project Phase II – Atlanta Pump Station Retrofit Project Type of Work: Environmental Cleanup Project Description Type of Work Description: EnvironmentalCleanup - Other
Construction and installation of an in-line trash removal device (TrashTrap) at the Atlanta PumpStation (8151 Atlanta Avenue). The device is an extra large fixed basket designed to removetrash/debris larger than 5mm in size.
Limits
Atlanta Pump Station - 8151 Atlanta Avenue
Project Notes
Other indicates Infrastructure Fund and OCTANew Fund
FISCAL YEAR FUND TYPE ENG ROW CON/IMP O&M TOTAL TOTAL ESCALATED 2024 Other $30,000 $0 $854,000 $0 $884,000 $909,620
Totals: $30,000 $0 $854,000 $0 $884,000 $909,620
Last Revised: 23-00 - In Progress Total Programmed: $884,000 TIP ID CP-10396 IMPLEMENTING AGENCY Huntington Beach,City of Local Project Number: 16-OCTA-TSP-3795 Project Title
Additional Project IDs: Magnolia Street Synchronization Type of Work: Traffic Signals Project Description
Type of Work Description: Traffic Signals -Interconnect traffic signals to improve coordinationand communications Provide operational and infrastructure improvements; carry-over from FY 17/18. OCTA leading jointproject with other cities along Magnolia Street. Funding only reflects Huntington Beach work.
Limits
From Garfield Avenue to Pacific Coast Highway
Project Notes
Other indicates Traffic Congestion Relief (Prop42).
FISCAL YEAR FUND TYPE ENG ROW CON/IMP O&M TOTAL TOTAL ESCALATED 2024 Other $5,000 $0 $189,789 $5,000 $199,789 $205,483
Totals: $5,000 $0 $189,789 $5,000 $199,789 $205,483
Last Revised: 23-00 - In Progress Total Programmed: $199,789 6/13/23, 1:50 PM ocfundtracker.octa.net/CIP/report_project_listing https://ocfundtracker.octa.net/CIP/report_project_listing 5/8 TIP ID CP-10399 IMPLEMENTING AGENCY Huntington Beach,City of Local Project Number: Project Title
Additional Project IDs: Residential Curb Ramp Project
Type of Work: Pedestrian Project Description
Type of Work Description: Pedestrian -Installation of ADA access ramps Install ADA Access Ramps . This is an annual project that will install Ramps at locations whereadjacent streets are altered or rehabilitated.
Limits
Citywide - Maintenance Zone 1
Project Notes
Other indicates Infrastructure Fund.
FISCALYEAR FUND TYPE ENGROWCON/IMP O&MTOTAL TOTALESCALATED 2024 Other $0 $0 $72,502 $0 $72,502 $74,677
2024 Measure M2 LocalFairshare $0 $0 $500,000 $0 $500,000 $515,000 2024 Community DevelopmentBlock Grant $0 $0 $127,498 $0 $127,498 $131,323 2025 Other $0 $0 $200,000 $0 $200,000 $212,180
2025 Measure M2 LocalFairshare $0 $0 $500,000 $0 $500,000 $530,450 2026 Other $0 $0 $200,000 $0 $200,000 $218,545
2026 Measure M2 LocalFairshare $0 $0 $500,000 $0 $500,000 $546,364 2027 Measure M2 LocalFairshare $0 $0 $500,000 $0 $500,000 $562,754 2027 Other $0 $0 $200,000 $0 $200,000 $225,102
2028 Measure M2 LocalFairshare $0 $0 $500,000 $0 $500,000 $579,637 2028 Other $0 $0 $200,000 $0 $200,000 $231,855
2029 Other $0 $0 $200,000 $0 $200,000 $238,810
2029 Measure M2 LocalFairshare $0 $0 $500,000 $0 $500,000 $597,026 2030 Measure M2 LocalFairshare $0 $0 $500,000 $0 $500,000 $614,937 2030 Other $0 $0 $200,000 $0 $200,000 $245,975
Totals: $0 $0 $4,900,000 $0 $4,900,000 $5,524,635
Last Revised: 23-00 - In Progress Total Programmed: $4,900,000 TIP ID CP-10400 IMPLEMENTING AGENCY Huntington Beach,City of Local Project Number: Project Title
Additional Project IDs: Residential Overlay - Maintenance Zone 1 Type of Work: Road Maintenance Project Description
Type of Work Description: Road Maintenance -Rehabilitation of roadway Rehabilitation of residential streets with asphalt overlay within Maintenance Zone 1. This annualproject will provide street overlay rehabilitation based on the PMP ratings Limits
Citywide - Maintenance Zone 1
Project Notes
Other indicates Sewer Service Fund, Water Fund,and Infrastructure Fund.
FISCAL YEAR FUND TYPE ENG ROW CON/IMP O&M TOTAL TOTAL ESCALATED 2024 Gas Tax $0 $0 $2,000,000 $0 $2,000,000 $2,060,000
2024 Other $0 $0 $4,700,000 $0 $4,700,000 $4,841,000
2025 Other $0 $0 $5,000,000 $0 $5,000,000 $5,304,500
2025 Gas Tax $0 $0 $2,000,000 $0 $2,000,000 $2,121,800
2026 Other $0 $0 $5,000,000 $0 $5,000,000 $5,463,635
2026 Gas Tax $0 $0 $2,000,000 $0 $2,000,000 $2,185,454
2027 Gas Tax $0 $0 $2,000,000 $0 $2,000,000 $2,251,018
2027 Other $0 $0 $5,000,000 $0 $5,000,000 $5,627,544
2028 Other $0 $0 $5,000,000 $0 $5,000,000 $5,796,370
2028 Gas Tax $0 $0 $2,000,000 $0 $2,000,000 $2,318,548
2029 Gas Tax $0 $0 $2,000,000 $0 $2,000,000 $2,388,105
2029 Other $0 $0 $5,000,000 $0 $5,000,000 $5,970,261
2030 Other $0 $0 $5,000,000 $0 $5,000,000 $6,149,369
2030 Gas Tax $0 $0 $2,000,000 $0 $2,000,000 $2,459,748
Totals: $0 $0 $48,700,000 $0 $48,700,000 $54,937,352
Last Revised: 23-00 - In Progress Total Programmed: $48,700,000 6/13/23, 1:50 PM ocfundtracker.octa.net/CIP/report_project_listing https://ocfundtracker.octa.net/CIP/report_project_listing 6/8 TIP ID CP-11542 IMPLEMENTING AGENCY Huntington Beach,City of 6/13/23, 1:50 PM ocfundtracker.octa.net/CIP/report_project_listing https://ocfundtracker.octa.net/CIP/report_project_listing 7/8 Local Project Number: 21-OCTA-TSP-4002 Project Title
Additional Project IDs: TS Synchronization - Bolsa
Type of Work: Traffic Signals Project Description
Type of Work Description: Traffic Signals -Interconnect traffic signals to improve coordinationand communications Provide operational & infrastructure improvements along Bolsa Ave from Bolsa Chica to Edwards. Thisis a multijurisdictional project w/ Caltrans, Westminster, Santa Ana, & Tustin. Work within HB inclsignal timing, new controllers, & battery back-up Limits
Bolsa Avenue from Bolsa Chica Street to EdwardsStreet
Project Notes
This is an OCTA grant. OCTA will manage theproject and is contributing $173,000 (HB segmentonly). Other indicates Traffic Congestion Relieffund. Other indicates Traffic Congestion ReliefFund.
FISCAL YEAR FUND TYPE ENG ROW CON/IMP O&M TOTAL TOTAL ESCALATED 2024 Other $5,000 $0 $60,000 $5,000 $70,000 $71,800
Totals: $5,000 $0 $60,000 $5,000 $70,000 $71,800
Last Revised: 23-00 - In Progress Total Programmed: $70,000 TIP ID CP-11847 IMPLEMENTING AGENCY Huntington Beach,City of Local Project Number: 20-HBCH-TSP-3973 Project Title
Additional Project IDs: TS Synchronization - Bolsa Chica Type of Work: Traffic Signals Project Description
Type of Work Description: Traffic Signals -Replace and upgrade traffic signals and equipment Provide operational and infrastructure improvements along Bolsa Chica St. This is a multijurisdictionalproject including Caltrans and the Cities of Westminister and Garden Grove. Work within HB includessignal timing, CCTV, and fiber optics.
Limits
Bolsa Chica Street from Warner Avenue to RanchoRoad
Project Notes
Other indicates Infrastructure Fund and OCTA CIPGrant.
FISCALYEAR FUNDTYPE ENG ROWCON/IMP O&M TOTAL TOTALESCALATED 2024 Other $342,800 $0 $1,940,300 $0 $2,283,100 $2,341,309 2025 Other $0 $0 $0 $30,400 $30,400 $30,400
2026 Other $0 $0 $0 $30,400 $30,400 $30,400
Totals: $342,800 $0 $1,940,300 $60,800 $2,343,900 $2,402,109 Last Revised: 23-00 - In Progress Total Programmed: $2,343,900 TIP ID CP-10401 IMPLEMENTING AGENCY Huntington Beach,City of Local Project Number: Project Title
Additional Project IDs: Talbert Avenue Synchronization
Type of Work: Traffic Signals Project Description
Type of Work Description: Traffic Signals -Interconnect traffic signals to improve coordinationand communications Provide operational and infrastructure improvements. OCTA leading joint project with Fountain Valleyand Santa Ana. OCTA applying for SB-1 funding.
Limits
Beach Boulevard to Newland Street
Project Notes
Other: Funding from FY 20/21 carried over throughFY 23/24.
FISCALYEAR FUND TYPE ENGROWCON/IMPO&MTOTALTOTALESCALATED 2024 Air Quality ManagementDistrict $0 $0 $6,000 $0 $6,000 $6,180 Totals: $0 $0 $6,000 $0 $6,000 $6,180
Last Revised: 23-00 - In Progress Total Programmed: $6,000 TIP ID CP-11540 IMPLEMENTING AGENCY Huntington Beach,City of Local Project Number: Project Title
Additional Project IDs: Traffic Signal Modification Main and Delaware Type of Work: Traffic Signals Project Description
Type of Work Description: Traffic Signals -Replace and upgrade traffic signals and equipment Install left-turn arrows at the intersection of Main St and Delaware St. Main St. will have left-turnarrows installed.
Limits
Main Street at Delaware Street
Project Notes
FISCAL YEAR FUND TYPE ENG ROWCON/IMP O&MTOTAL TOTAL ESCALATED 2024 Traffic Impact Fees $50,000 $0 $365,000 $0 $415,000 $425,950 Totals: $50,000 $0 $365,000 $0 $415,000 $425,950
Last Revised: 23-00 - In Progress Total Programmed: $415,000 6/13/23, 1:50 PM ocfundtracker.octa.net/CIP/report_project_listing https://ocfundtracker.octa.net/CIP/report_project_listing 8/8 TIP ID CP-11541 IMPLEMENTING AGENCY Huntington Beach,City of Local Project Number: Project Title
Additional Project IDs: Traffic Signal Modification Warner and Ash Type of Work: Traffic Signals Project Description
Type of Work Description: Traffic Signals -Replace and upgrade traffic signals and equipment Install left-turn arrows at the intersection of Warner Ave and Ash Ln. Warner Ave will have left-turnarrows installed.
Limits
Warner Avenue at Ash Street
Project Notes
FISCAL YEAR FUND TYPE ENG ROWCON/IMP O&MTOTAL TOTAL ESCALATED 2024 Traffic Impact Fees $40,000 $0 $410,000 $0 $450,000 $462,300 Totals: $40,000 $0 $410,000 $0 $450,000 $462,300
Last Revised: 23-00 - In Progress Total Programmed: $450,000 TIP ID CP-10402 IMPLEMENTING AGENCY Huntington Beach,City of Local Project Number: Project Title
Additional Project IDs: Warner Avenue Synchronization
Type of Work: Traffic Signals Project Description
Type of Work Description: Traffic Signals -Interconnect traffic signals to improve coordinationand communications Provide operational and infrastructure improvements. OCTA leading joint project with Fountain Valleyand Santa Ana.
Limits
From Magnolia Street to Pacific Coast Highway
Project Notes
Other: Funding from FY 20/21 carried over throughFY 23/24.
FISCAL YEAR FUND TYPE ENG ROW CON/IMP O&M TOTAL TOTAL ESCALATED 2024 Other $0 $0 $80,000 $0 $80,000 $82,400
Totals: $0 $0 $80,000 $0 $80,000 $82,400
Last Revised: 23-00 - In Progress Total Programmed: $80,000