Civic Center Underground Storage Tank (UST) Replacement Project Overview
July 18, 2023

BACKGROUND
Existing tank – 12,000 gallon, gasoline single wall steel underground storage tank (UST) Fueling island is original to the Civic Center (1975), though some upgrades have occurred (dispensers, underground containment sumps) Station mainly serves PD fleet
Existing UST is located under parking stalls

EXISTING FUELING ISLAND

EXISTING UST

NEED/WHY/BENEFITS
California SB-445 requires that all USTs be double wall by 2025 Maintaining City-owned fueling stations allows for ~$1/gallon fuel discount New FRP tank has brine-filled interstice and pressure sensor for leak detection system Replace old/outdated dispensers and fuel island/ canopy Upgrading Veeder-Root fuel management system
Relocate UST out of way of parking stalls, away from PD operations

DETAILS

STAKEHOLDER OUTREACH
The project team does not expect the construction phase to impact the public.

The project team worked closely with City Fleet, Police Department, Fire Marshall, AQMD, Orange County Health Care Agency (OCHCA), and the Department of Toxic Substances Control (DTSC) stakeholders to develop the work plan for this project.

FUNDING/SCHEDULE
The total cost of the project, including contingency, is $1,225,209.00. Funds for this project are available in the current fiscal year budget in the infrastructure fund account 31440005.82200.

The project is scheduled to start October 2, 2023 and is anticipated to run ~5 months.