Humboldt Sewer Lift Station Replacement
CC-1634
September 5, 2023

BACKGROUND AND PROJECT SCOPE
Replace the existing Humboldt Sewer Lift Station due to age and insufficient wet well capacity Located on Humboldt Island at the southeast corner of Humboldt Drive and Wayfarer Lane Constructed in 1967, the sewer lift station has reached its useful life and the existing concrete structure is failing The new lift station will mainly be underground with only the electrical and control cabinets above ground

VICINITY MAP - HUMBOLT ISLAND

PROJECT LAYOUT

PROJECT BENEFITS
Provides facility with 50 years of useful life.

Prevents sewer lift station failure and resulting Sanitary Sewer Overflow into Huntington Harbor.

Enlarged wet well provides more response time to bring out generators during electrical black outs.

System will be airtight with no sewer odors.

PROJECT OVERVIEW
Construction Bids Received July 6, 2023
Current Budget (Water Enterprise Fund) $4,933,000
Council Awarded to Mehta Mechanical Company, Inc. dba MMC July 18, 2023 ($4,134,200) Project not advertised in newspaper, as required by City Charter Recommended Action: Reject All Bids
Alternative Recommendation: Not Applicable
Project to be advertised on September 6, 2023
Proposed Bid Date October 5, 2023
Proposed Date for Council to Award Contract November 7, 2023

Questions?