Goldenwest St. &
Graham St. Bridge
Maintenance
Project, CC-1713
September 19, 2023
City Council Meeting

Project Location Map
GOLDENWEST ST. BRIDGE
Project Location Map
GRAHAM ST. BRIDGE
• 2-span pre-cast/ pre-stressed
concrete cored deck bridge with
reinforced concrete pile bents and
abutments
• Originally constructed 1959
• Length = 67’
• Width = 84’
Goldenwest Bridge
Graham Bridge
• 4-span cast-in-place concrete bridge
with reinforced concrete pier walls
and abutments
• Originally constructed 1961
• Length = 152’
• Width = 62’

Scope of Work - Goldenwest
• Remove asphalt concrete (AC)
pavement, seal deck, and
reconstruct AC pavement.

Scope of Work - Goldenwest
• Repair existing wing wall
Scope of Work - Goldenwest
• Repair unsound concrete and
damaged curb
Scope of Work - Goldenwest
• Remove graffiti
Scope of Work - Graham
• Remove and construct new
concrete barrier and chain link
fence
Scope of Work - Graham
• Remove unsound concrete and
patch spalls on piers and
abutments
Scope of Work - Graham
• Waterproof piers
Scope of Work - Graham
• Replace joint seals
in sidewalk
Scope of Work - Graham
• Remove graffiti
Funding and Schedule
Current Funding
• Prop 42 Fund Account 21985202: $750,000.00
• FY 22-23 Prop 42 Fund Account 21985201: $100,000.00
$850,000.00
• Applied Restoration, Inc. Bid: $754,451.80
• 10% Contingency: $ 75,445.18
• Supplemental Costs: $ 20,103.02
$850,000.00
Recommended Action: Accept the lowest responsive and responsible bid submitted by Applied Restoration, Inc.

Begin Construction: 10/30/23
End Construction: 05/06/24
Questions?