Bolsa Chica Street / Valley View Street Regional Traffic Signal Synchronization Project, CC-1622
PROJECT DESCRIPTION
This project provides operational and infrastructure improvements at 22 intersections along Bolsa Chica Street / Valley View Street from Garden Grove to Huntington Beach Improvements within Huntington Beach included:
Installation of fiber optic communication cable and conduit New traffic signal controllers
Updated traffic signal timing
CCTV Cameras
The City of Huntington Beach is Lead Agency
The City of H.B. will manage engineering efforts for the entire corridor All OCTA funds will be paid to and disbursed by the City of Huntington Beach
PROJECT DESCRIPTION (CONTINUED)
Recommended City Council Actions:
Approve and authorize the Mayor and City Clerk to execute Professional Service Contract Between the City of Huntington Beach and Iteris, Inc. for the Valley View Street/ Bolsa Chica Street RTSSP Project, CC-1622, in an amount not to exceed $646,136.00
PROJECT COSTS
OCTA Grant: $1,735,949
WORK WITHIN HUNTINGTON BEACH: $ 329,347
WORK WITHIN WESTMINSTER: $ 142,846
WORK WITHIN GARDEN GROVE: $ 135,608
TOTAL PROJECT COST: $2,243,900
TOTAL CITY COSTS
City of Huntington Beach Matching Funds Required $ 155,533 City of Huntington Beach Construction Contingency $ 114,015 City of Huntington Beach Contract Administration $ 59,949 TOTAL $ 329,497
Questions?