Edinger Avenue Sewer Improvements
November 7, 2023

Background
The 8-inch and 10-inch sewer in Edinger Avenue, from railroad tracks east of Gothard St. to west of Beach Blvd., has a sag in the line west of the railroad tracks that has reduced the capacity of the sewer and the new development along Edinger Avenue has added sewer flows, resulting in the line being under capacity.

This project will replace the 8 and 10-inch sewers with 8 to 15-inch sewers from the railroad tracks to just west of Beach Boulevard to eliminate the sag and restore system capacity.

EXISTING SEWERS TO REMAIN

SHADED AREAS TO GET PAVEMENT OVERLAY
Edinger Avenue Sewer Improvements Location & Alignment

SPRINGHILL SUTIES

IN N OUT

SAG IN SEWER
WORK HOURS 9 AM TO 3 PM

DUE TO THE RESIDENCES AT BELLA TERRA
WORK HOURS 10 PM TO 5 AM

Funding and Schedule
Project Budget: $3,662,675
Contribution from Sewer Development Fee Fund: $800,000
Estimated Costs: $5,000,000
Construction Start: January 2024
Construction Duration: 16 – 20 weeks
Remaining project funds of $1,337,325 will come from the PCH Restroom Sewer Lift Station Project.

Additional Costs Due To:

Inflation: 11% Increase in 2 years
Premium for Night Construction
High Groundwater, 3-feet from surface
Gasoline Contamination: Sher Ln. and Beach Blvd.

Details
Prevent Sanitary Sewer Overflows due to lack of capacity during rain events Prevent Grease Build Up at sag in pipe that cause Sanitary Sewer Overflows Provide Design Capacity for new development along Edinger Avenue

Questions?