Humboldt Lift Station Replacement
CC 1634
November 7, 2023

BACKGROUND AND PROJECT SCOPE
Humboldt Lift Station, located at the southeast corner of Humboldt Drive and Wayfarer Lane, was constructed in 1967.

Recent inspections indicate the concrete structure is failing and the wet well capacity is insufficient.

This project will replace the existing facility with a new lift station. The new lift station will be predominantly underground, with only control and electrical cabinets above ground. It will have increased wet well capacity and an airtight system to reduce sewer odors.

VICINITY MAP - HUMBOLDT ISLAND

PROJECT LAYOUT

PROJECT BENEFITS
Increases lifespan of facility by 50 years
Prevents sewer lift station failures that may result in Sanitary Sewer Overflows (SSOs) into Huntington Harbour Enlarged wet well affords increased response time to deploy generators during power outages Airtight system reduces sewer odors

SCHEDULE AND FUNDING
Construction Bids Received October 5, 2023
Current Budget: $4,101,918 (Sewer Funds)
Request Award to Lowest Bidder – Vido Artukovich & Son Inc./Vidmar Inc. A JV Total Low Bid = $4,193,450
Total Project Cost with Inspection = $5,035,000
Recommended Action: Accept the lowest responsive bid and authorize execution of construction contract with Vido Artukovich and authorize a budget revision of $933,082 from the PCH Restroom Sewer Lift Station Project Construction Start: January 2024
Construction Duration: 13 months
Alternative Recommendation: Reject All Bids