Admiralty Drive Bridge RehabCC-1450November 21, 2023 City Council Meeting

Project Location Map
ADMIRALTY DR. BRIDGE
Admiralty Bridge
•3-span steel girder bridge with 4-column reinforced concrete bents supported on timber piles•Length = 155’-3”•Width = 52’•Originally constructed in 1963•Seismically retrofitted in 1994 Scope of Work
•Replace concrete barriers and railing•Replace street lighting on bridge•Replace concrete sidewalk and bridge deck•Clean & paint steel girders & other steel members•Repair unsound concrete at bridge bents•Utility relocation andminor AC paving work

Funding and Schedule
•Beador Construction Bid: $4,565,300•15% Contingency: $ 684,795•Supplemental Costs: $ 629,905•Total Construction Cost $5,880,000•Federal Construction Funds: $3,280,000•Infrastructure Funds: $ 500,000•Measure M Funds: $2,100,000•Total Available Funding: $5,880,000•Begin Construction: 2024 Q1•End Construction: 2025 Q1 Questions?