Text extracted from the city's file for reading and search. Open the original on huntingtonbeach.legistar1.com. That file is the official record.

Fiscal Year
2023-2024
Water Main
Replacement
Project
April 16, 2024

CC-1716 Alley East of Alabama Street,
Between Lincoln and Knoxville Avenues
CC-1717 Alley East of Alabama Street,
Between Memphis and Lincoln Avenues
Community Benefits
• Replace old 4-inch asbestos cement pipeline (AC)
• Install 6-inch polyvinyl chloride pipeline (PVC)
• Enhance water systems redundancy and reliability with new water improvements
• Provide greater fire protection to area with larger diameter pipeline • Repave and grade alley to improvement pre-existing
drainage issues and aesthetics
Funding & Schedule
• Engineer’s Estimate $1.6M
• Lowest Responsible and Responsive Bidder Excel Paving Company • Bid Amount $1,398,435
• Funding Source Water Master Plan
• Tentative Construction Timeline June 2024 – December 2024 • Construction Duration Approximately Six Months