Le Bard Park
Improvements
Project

• Project Location

Cost Summary
• Total Funding - $1,065,049.80
• Funds available - $409,957.60
• To finish project, request award to 2nd lowest bidder – Klassic Engineering & Construction
• Recommended action includes award:

Award $ 273,425.90
Construction Contingency $ 41,013.89
Construction Administration$ 41,013.89
Total Project Cost $ 355,453.68
Project History - Prior Efforts

Completed Work - demolished the clubhouse building,
replaced the tennis courts concrete slab, and installed irrigation

Remaining work to be done
• Repair of the existing tennis court fencing, windscreen, court resurfacing, netting, and replacement with park greenspace and table seating and renovations to adjacent park landscaping