Traffic Signal Modifications
Warner Avenue and Ash Lane
Main Street and Delaware Street
5/21/2024

Project Scope
Installation of east-west left turn arrows on Warner Avenue at Ash Lane Installation of left turn arrows on Main Street at Delaware Street Left turns would only be permitted on a green arrow
Project includes sidewalk and curb ramp improvements
Construction estimated to begin November 2024 and be completed by April 2025

Project Budget
Bids opened on April 30, 2024
Low Apparent Bid is $1,146,920
Project Cost Estimate is $1,320,000 including construction contingency and contract administration Available Funds: $755,068 - resulting in an estimated shortfall of $564,932 Staff recommendation is to award contract and appropriate $564,932 from undesignated Traffic Impact Fee fund balance

Project Locations

Questions?