AGENDA
Updates from Local Agencies
Ascon
Updates from City of Huntington Beach
Community Development
Community & Library Services
Public Works
Police Department
UPDATES FROM
LOCAL AGENCIES
ASCON
PATH TO RESTART
Update for July 24, 2024 City of Huntington Beach Southeast Area meeting.
For Discussion Only.
Ascon team
submits
Engineered
Misting
Containment, Soil
Vapor Extraction
Pre-Treatment
Pilot Test
Completion
Reports to DTSC
DTSC
reviews
reports
and works
to finalize
with
Ascon
Ascon
coordinates
with DTSC
on restart
plan based
on pilot
work
DTSC and
Ascon
finalize
restart
plan, and
DTSC
holds a
community
meeting
Restart work
begins at
Ascon
We are here
ONSITE ACTIVITIES
Ascon team member conducting onsite vegetation management work, June 2024
5 This includes:
• Conducting vegetation management including weed
abatement during drier months
• Coordinating with Orange County Mosquito and
Vector Control for onsite treatment
• Maintaining barrier fencing and stormwater best
management practices
During the current, pre-restart phase, regular onsite
summer maintenance continues.
Update for July 24, 2024 City of Huntington Beach Southeast Area meeting.
For Discussion Only.
ASCON RESTART COMMUNITY
MEETING
Location:
• Edison Community Center
Proposed Date of Community Meeting:
• Tuesday-Thursday evening,
September/October 2024
This will be a hybrid in-person townhall
style meeting also offered virtually for
those who do not wish to attend in person.
DTSC and Ascon are coordinating with a
professional facilitator.
6 Update for July 24, 2024 City of Huntington Beach Southeast Area meeting.
For Discussion Only.
DTSC to review and approveAscon SVE pre-treatment pilot test report.
Coordinate with DTSC on restart plan and community meeting.
Routine Site maintenance.
NEXT STEPS – JULY/AUGUST
7 DTSC to finalize and approve restart plan.
Update for July 24, 2024 City of Huntington Beach Southeast Area meeting.
For Discussion Only.
How to Stay Up to Date and Contact Us
Visit asconhb.com to sign up to receive Ascon updates, including Weekly Site Updates covering onsite activities and field work, and sign up for AsconAlert.
You can reach the Ascon team at our information line, 714-388-1825, or via email at [email protected].
Update for July 24, 2024 City of Huntington Beach Southeast Area meeting.
For Discussion Only.
HB UPDATES
Community Development
COMMUNITY DEVELOPMENT
Pending Planning Applications
9300 Indianapolis: Sowers Middle School – CUP for maintenance and storage building, bus yard
- APPLICATION INCOMPLETE
8750 Dorsett Drive: former Kettler School – CUP for maintenance and operations building
- ZONING ADMINISTRATOR APPROVED 6/19/24
- PLANNING COMMISSION APPEAL 7/23/24
Coastal Commission
Magnolia Tank Farm
- APPROVED WITH MODIFICATIONS 7/10/24
- CITY HAS 180 DAYS TO ACCEPT THE MODIFICATIONS
Community & Library Services
PARK IMPROVEMENTS
• Edison Park
• Conceptual Plan: bit.ly/hbedisonpark
• Pickleball Rules Survey – Closes August 7
• LeBard Park
BEACH EVENTS
• City Beach
• US Open: August 3 – August 11 (Southside Pier)
• OC Yoga Fest: August 24 – August 25 (Pier Plaza)
• Surf City 10: September 15 (PCH Closed 5am – 11am)
• Wodapalooza: September 20 – September 22
(Northside Pier)
• State Beach
• No scheduled events
Public Works
BANNING
IMPROVEMENTS
Rapid Flashing Beacons (RRFB’s) are completed
Street light work under design. Improvements with a few changes/additions to the utility pole mounted street lights
PUBLIC WORKS
LeBard Park (under construction, completed mid-Sept)
Gisler Park – completed.
OCTA/SCAG AWARD:
$5M for Banning Roundabout along with improvements
along Newland (Adams-PCH)& Bushard (Adams-
Brookhurst) includes planting 140 new trees, enhanced
bike lanes, replacing sidewalks & radar feedback signs
$3.9M for Hamilton between Magnolia & Brookhurst
includes new landscaped medians, curb & gutter,
sidewalks, 50 new trees, enhanced bike lanes.
DRAIN SYSTEM AT THE CORNER OF
HAMILTON AND MAGNOLIA
ZONE 1 MAINTENANCE
ZONE 1 RESIDENTIAL PAVING
• Tree Plantings 90% complete
• JUNE-AUG: Asphalt overlay of
streets (done)
• JULY-AUG: Slurry seal of streets
(now)
Police Department
PART I CRIMES
JANUARY – JUNE 2024
• Citywide - Part I Crimes are down 6.7%
• Southeast – Part I Crimes are down 41%
TRAFFIC COLLISIONS
JANUARY – JUNE 2024
Citywide Data:
• Citywide Collisions - 832
• Bicycle Collisions
• Total Citywide: 119
• Involving E-bikes: 72
• Pedestrian Collisions
• Total Citywide: 39
• Southeast Area Collisions
• 154 collisions
THANK YOU