Facilities Condition Assessment
September 17, 2024
BACKGROUND
The City occasionally undertakes conditional assessments of its facilities to determine:
Current state
Identify necessary repairs
Prioritize capital improvement projects.
The last City-wide assessment was done in 2007.
FUNDING/SCHEDULE
Gordian Facility Condition Assessment
Funding
Total Project Cost $424,581.00
General Fund account number 31440028.82200
Schedule
Assessment – 90 Days
Options – 30 Days
Final Recommendation – 20 Days
NEED/WHY/BENEFITS
Accurate and consistent assessments are critical to maintaining the safety, functionality, and longevity of these assets and the overall infrastructure
NEED/WHY/BENEFITS
Key attributes of Gordian’s FCA
Comprehensive Data Collection
Standardization and Consistency
Accurate Cost Estimation
Efficient Planning and Prioritization
Integration with Facility Management
Risk Management
Support for Funding Requests
Long-Term Asset Management