Zone 2 Residential Curb Ramp Project
Zone 2
Residential Zone Maintenance Program
Residential Paving
Phases within program
Tree Maintenance - Fall
Concrete Rehabilitation/ADA Ramps – Winter/Early Spring Street Paving – Spring/Early Summer
Slurry Seal – Early Summer
Zone 2 Residential Curb Ramp Project
This project consists of approx. 22 curb access ramps (comply with the American Disabilities Act - ADA).
ADA requires City to install ADA compliant ramps on streets with paving.
Includes ramps for streets to be paved within zone 2
Zone 2 Residential Curb Ramp Project
Curb Ramp Construction
Completed Curb Ramp