Arterial
Complete
Streets Projects
December 17, 2024

BACKGROUND
• Newland Street (Adams Avenue to Pacific Coast Highway) • 2 street miles of construction
• Bushard Street (Adams Avenue to Brookhurst Street)
• 2 street miles of construction
• Hamilton Avenue (Magnolia Street to East City Limit)
• 1 street mile of construction

• New slurry coat or asphalt overlay required to existing paveme nt for extending life of street
• Reconstruct damaged and uneven concrete
• Landscape enhancement with tree replacement
• Striping and signage improvements including enhance bike lines and pedestrian crosswalks
• New Roundabout at Banning and Bushard

NEEDS/WHY/BENEFITS

FUNDING
Proposed Project Costs $11M
o Orange County Transportation Grant (OCTA )
Total OCTA Funding $8,971,000
o $5M for Newland and Bushard Project
o $3,971,000 for Hamilton Project
o Local Funds: AES/Measure M/RMRA
o $2M

SCHEDULE
• Design in FY 2024/25
• Construction in 2025/26
Questions?