Text extracted from the city's file for reading and search. Open the original on huntingtonbeach.legistar1.com. That file is the official record.

Admiralty Drive Bridge RehabCC-1450
December 17, 2024

Project Location Map
ADMIRALTY DR. BRIDGE

Admiralty Bridge
3-span steel girder bridge with 4-column reinforced concrete bents supported on timber piles Length = 155’-3”
Width = 52’
Originally constructed in 1963
Seismically retrofitted in 1994

Scope of Work
Replace concrete barriers and railing
Replace street lighting on bridge
Replace concrete sidewalk and bridge deck
Clean & paint steel girders and other steel members
Repair unsound concrete at bridge bents
Utility relocation and minor AC paving work

Funding
Beador Construction Bid: $4,565,300
15% Contingency: $ 684,795
Supplemental Costs: $ 629,905 $5,880,000 Current Funding
Federal Construction Funds: $3,280,000
Infrastructure Funds: $ 500,000
Measure M: $2,100,000 $5,880,000
Proposed Funding Dec 19
Federal Construction Funds: $5,196,490 (max.)
Measure M: $ 683,510 $5,880,000