Orange County Transportation Authority Warner Avenue Regional Traffic Signal Synchronization Program
PROJECT DESCRIPTION
This Warner Avenue Regional Traffic Signal Synchronization Program project aims to provide operational and infrastructure improvements at 42 intersections. Improvements in the City of Huntington Beach will be on Edinger Avenue from Pacific Coast Highway to Magnolia Street.
Improvements include:
Installation of fiber optic cable (completed)
Installation of new traffic signal controllers (completed) Updated traffic signal timing (partially completed)
Current Cooperative Agreement No. C-0-2039 is set to expire on June 30, 2025. Amendment No.1 is requesting to extend it for another year for completion before June 30, 2026.
PROJECT DESCRIPTION (CONTINUED)
Recommended City Council Action:
Approve and authorize the Mayor and City Clerk to execute “Amendment No.1 to the Cooperative Agreement No. C-0-2039 between Orange County Transportation Authority and Cities of Fountain Valley, Huntington Beach, and Santa Ana for Warner Avenue Regional Traffic Signal Synchronization Program Project”
PROJECT COSTS
With the approval of the Cooperative Agreement on September 9, 2020, the City Council appropriated $80,000 from the Air Quality Management District (AQMD) fund (Business Unit 20190008.82700) for the City’s share of the project costs. No further appropriation is requested for this action
Questions?