5/20/2025
19 (25-386)
Edinger Avenue
and Heil Avenue
Traffic Signal
Improvements
5/20/2025
Project Location
Project Scope
• Highway Safety Improvement Program (HSIP)
• Awarded March 13th, 2023
• Grant Fund Awarded Amount: $675,090.00
• Project Corridor Segments
• Edinger Avenue between (Bolsa Chica Street to Parkside Lane), • Heil Avenue between (Bolsa Chica Street to Gothard Street) • Traffic Safety Improvements
• Retro-Reflective Backplates
• Near-Sided Traffic Signal Heads
• Pedestrian Audible Buttons
• Green Striping Bike Lanes
• Leading Pedestrian Intervals Timing
Project Budget
• Construction Cost Estimate
• Contractor’s Bid $ 950,702.50
• 10% Contingency $ 95,070.25
• Construction Administration $ 95,070.25
• TOTAL $ 1,140,843.00
• Project Funding
• $ 675,090.00 from Edinger Heil Corridor Project Grant Fund • $ 76,485.00 from Traffic Impact Fund
• $ 389,268.00 is requested to be appropriated from the Traffic Impact Fund to fund the project in the amount of $1,140,843.00