RESOLUTION NO. 2025-38
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF HUNTINGTON BEACH ADOPTING A LIST OF PROJECTS FOR FISCAL YEAR 2025/26 FUNDED BY SB 1: THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017
WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes of 2017) was passed by the Legislature and Signed into law by the Governor in April 2017 to address the significant multi-modal transportation funding shortfalls statewide; and
WHEREAS, SB 1 includes accountability and transparency provisions that will ensure the residents of our City are aware of the projects proposed for funding in our community and which projects have been completed each fiscal year; and WHEREAS, the City of Huntington Beach must adopt by resolution a list of projects proposed to receive fiscal year funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1, which must include a description and the location of each proposed project, a proposed schedule for the project's completion, and the estimated useful life of the improvement; and
WHEREAS, the City of Huntington Beach, will receive an estimated $5,203,411 in RMRA funding in Fiscal Year 2025/26 from SB 1; and
WHEREAS, this is the ninth year in which the City of Huntington Beach is receiving SB 1 funding and will enable the City to continue essential road maintenance and rehabilitation projects, safety improvements, repairing and replacing aging bridges, and increasing access and mobility options for the traveling public that would not have otherwise been possible without SB 1; and
WHEREAS, the City of Huntington Beach used a Pavement Management Plan (PMP) to assist in developing the SB 1 project list to ensure revenues are being used on the most cost- effective projects to maintain the City's pavement condition and also meet the community's priorities for transportation investment and mobility improvements; and WHEREAS, the funding from SB 1 will help the City of Huntington Beach maintain and rehabilitate the arterial street throughout the City this year and similar projects into the future; and
25-16424/377516
RESOLUTION NO. 2025-38
WHEREAS, the 2024 PMP found that the City of Huntington Beach's roads are in a good condition and this revenue will help us increase the overall quality of our road system and over the next decade will maintain our streets and roads in a good condition; and WHEREAS, the SB 1 project list and overall investment in our local streets and roads infrastructure with a focus on basic maintenance and safety, pavement rehabilitation and reconstruction, investing in complete streets infrastructure, and using cutting-edge technology, materials and practices, will have significant benefits to the City of Huntington Beach.
NOW, THEREFORE, the City Council of the City of Huntington Beach does hereby resolve as follows:
1. The foregoing recitals are true and correct.
2. The following list of newly proposed projects will be funded in-part or solely with Fiscal Year 2025/26 Road Maintenance and Rehabilitation Account revenues:
Project Title: Newland Street Rehabilitation Project
Project Description: Rehabilitate pavement on Newland Street from Slater Avenue to Heil Avenue. Project will include limited hardscape and landscape replacement along with striping and signage improvements.
Project Location: Newland Street, from Slater Avenue to Heil Avenue.
Estimated Project Schedule: Start (06/26) - Completion (9/26) based on the component being funded by the RMRA funds.
Estimated Project Useful Life: 20 years
Project Title: Heil Rehabilitation Project
Project Description: Rehabilitate pavement on Heil Avenue from Goldenwest Street to Gothard Street. Project will include limited hardscape and landscape replacement along with striping and signage improvements.
Project Location: Heil Avenue from Goldenwest Street to Gothard Street Estimated Project Schedule: Start (08/26) - Completion (12/26) based on the component being funded by the RMRA funds.
Estimated Project Useful Life: 20 years
Project Title: Hamilton Avenue Complete Street Project
Project Description: Rehabilitate pavement on Hamilton Avenue from Magnolia Street to City Limit East of Brookhurst Street. Project will include limited hardscape and landscape replacement, new landscape medians, and striping and signage improvements. 2 RESOLUTION NO. 2025-38
Project Location: Hamilton Avenue, from Magnolia Street to City Limit East of Brookhurst Street.
Estimated Project Schedule: Start (08/26) - Completion (12/26) based on the component being funded by the RMRA funds.
Estimated Project Useful Life: 20 years
Project Title: Bushard and Newland Complete Street Project Project Description: Rehabilitate pavement on Bushard Street and Newland Street including a Roundabout installation at Bushard Street And Banning Avenue. Project will include limited hardscape and landscape replacement, new roundabout, and striping and signage improvements.
Project Location: Bushard Street, from Adams Avenue to Brookhurst Street. Newland Street from Adams Avenue to Pacific Coast Highway.
Estimated Project Schedule: Start (06/26) - Completion (10/26) based on the component being funded by the RMRA funds.
Estimated Project Useful Life: 20 years
PASSED AND ADOPTED by the City Council of the City of Huntington Beach at a regular meeting thereof held on _ day of _ 2025.
Mayor
REVIEWED AND APPROVED: APPROVED AS TO FORM:
City Attorney
City Manager
INITIATED AND APPROVED:
Ella
Director of Public Works