Traffic Signal Installation
Gothard Street at the Murdy Fire Station
5/20/2025

Project Scope
Traffic signal will be installed to stop traffic on Gothard Street to allow for egress from the fire station The signal will be activated by fire department personnel

Project Budget
Bids opened on April 10, 2025
Low Apparent Bid is $254,266
Project Cost Estimate is $327,700 including construction contingency and contract administration Available Funds: $286,734 in Traffic Impact Fee Account 20690022.82700 and $40,966 in Traffic Impact Fee Account 20690020.82700 ($327,700 total)