Edinger Avenue and Heil Avenue Traffic Signal Improvements 5/20/2025
Project Location
Project Scope
Highway Safety Improvement Program (HSIP)
Awarded March 13th, 2023
Grant Fund Awarded Amount: $675,090.00
Project Corridor Segments
Edinger Avenue between (Bolsa Chica Street to Parkside Lane), Heil Avenue between (Bolsa Chica Street to Gothard Street) Traffic Safety Improvements
Retro-Reflective Backplates
Near-Sided Traffic Signal Heads
Pedestrian Audible Buttons
Green Striping Bike Lanes
Leading Pedestrian Intervals Timing
Project Budget
Construction Cost Estimate
Contractor’s Bid $ 950,702.50
15% Contingency $ 95,070.25
Construction Administration $ 95,070.25
TOTAL $ 1,140,843.00
Project Funding
$ 675,090.00 from Edinger Heil Corridor Project Grant Fund $ 76,485.00 from Traffic Impact Fund
$ 389,298.00 is requested to be appropriated from the Traffic Impact Fund to fund the project in the amount of $1,140,843.00
Questions?