Police Department Women’s Locker Room Improvement
Project Overview
June 17, 2025

BACKGROUND
Existing women’s locker room is located on main level of Civic Center Police Station Current locker room is about 840 square feet, constructed in ~1975, has received minor upgrades over time.

Finishes are at end of life and need replacement
Locker room renovation addresses increased staffing levels and ADA compliance

BACKGROUND
Records area will be displaced by expanded locker room, need to be repositioned and renovated.

Vertical carousel storage system provides efficient use of reduced storage room size Many of the current offices consist of temporary partition walls.

Plumbing fixtures, flooring, ceiling tiles, electrical systems, HVAC, bathroom amenities and offices require modernization and ADA compliance.

NEED/WHY/BENEFITS
Project addresses increased staffing needs and ADA compliance Update facility infrastructure that has exceeded its service life Adjacent offices renovated with new technology and organizational systems

COMMUNITY OUTREACH
This project will not have an impact on the surrounding community during construction PD, City Facility Maintenance, IT, stakeholders were engaged throughout the course of the project

FUNDING/SCHEDULE
FUNDING:

Construction Cost:
$1,319,372
Infrastructure Fund account:
31440010
SCHEDULE:

February 6, 2025 – Bid project
April 7, 2025 – Open bids
June 17, 2025 – Award contract
Begin construction (Approx. Fall 2025)
Contingent on long lead items (lockers and vertical carousel)

Questions?