Why/Benefits
CIP Project Support
• Projects may include up to 25% of preliminary construction cost for on-call design services • 15% to 20% for standard projects like street rehabilitation and projects that don't require underground construction
• 20% to 25% for complex infrastructure projects such as storm drain pump stations, sewer lift stations and facility projects where the designs are more complex and require extensive research and field investigation.
• In the last 5 years the value of CIP projects is $238 million and conservatively 25% of $238 million is $60 million in fees for professional services
Total CIP Budget (2021-2025)
Values are in millions
UN
$60 $63 Ок GTON BEACH
CITY
$39 $41
$35
DRANGE COUNT CALIFORNIA
2021. 2022 2023 2024 2025