Att #6 Estimated Design Costs for CIPs

City Council/Public Financing Authority
July 15, 2025

Document
Att #6 Estimated Design Costs for CIPs
Meeting
July 15, 2025
Body
City Council/Public Financing Authority
Original file
79 KB
Text extracted from the city's file for reading and search. Open the original on huntingtonbeach.legistar1.com. That file is the official record.

Why/Benefits
CIP Project Support
• Projects may include up to 25% of preliminary construction cost for on-call design services • 15% to 20% for standard projects like street rehabilitation and projects that don't require underground construction
• 20% to 25% for complex infrastructure projects such as storm drain pump stations, sewer lift stations and facility projects where the designs are more complex and require extensive research and field investigation.
• In the last 5 years the value of CIP projects is $238 million and conservatively 25% of $238 million is $60 million in fees for professional services
Total CIP Budget (2021-2025)
Values are in millions